49 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Biswanath(Deputy Commissioner Biswanath_IDA) | 49 | 22 | ₹3.17 Cr | 31 | 37.6 | LOHIT BHUYAN 94% of spend · 2 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Pallab Lochan Das Sonitpur | 47 | ₹2.72 Cr | 29 |
| Pabitra Margherita Sitting Rajya Sabha | 1 | ₹15.00 L | 1 |
| Jogen Mohan Sitting Rajya Sabha | 1 | ₹30.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 17 | ₹99.99 L | 9 |
| Religious & Cultural | 16 | ₹1.25 Cr | 13 |
| Education | 10 | ₹49.97 L | 6 |
| Drainage & Sanitation | 2 | ₹14.99 L | 0 |
| Sports | 2 | ₹7.50 L | 2 |
| Boundary & Protection | 1 | ₹5.00 L | 1 |
| Health | 1 | ₹14.85 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of C/Hall at Uttar Sootea Yubak Sangha, Mudoi G ₹1,000,000 against a ₹500,000 median for Community Buildings works in BISWANATH (100% above, 46 peer works) | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹10.00 L | 555 d | +100% | 65.0 | MEDIUM |
| Construction of C/Hall near Thakurbari Mandir, Ward No. 5 Bi ₹1,000,000 against a ₹500,000 median for Community Buildings works in BISWANATH (100% above, 46 peer works) | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹10.00 L | 594 d | +100% | 65.0 | MEDIUM |
| Construction of Rangamancha at Bengabari Gaon, Baralimara, B Completed work has no photographic documentation on record | Biswanath(Deputy Commissioner Biswanath_IDA) | Completed | ₹15.00 L | — | +200% | 64.5 | MEDIUM |
| Re Construction of Dakhin Kalabari Shivmandir,LAC-Gahpur,784 ₹3,000,000 against a ₹500,000 median for Religious & Cultural works in BISWANATH (500% above, 34 peer works) | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹30.00 L | — | +500% | 60.0 | MEDIUM |
| Construction of Boundary Wall at Dhullie 3. No Cremation Gro 546 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹5.00 L | 546 d | -35% | 48.5 | MEDIUM |
| Construction of Cycle Stand at Dekorai High Secondary School 556 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹5.00 L | 556 d | 0% | 48.2 | MEDIUM |
| Construction of Additional Class Room at Kalahandi LP School 556 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹5.00 L | 556 d | 0% | 48.2 | MEDIUM |
| Construction of Community Hall near Kamona Mandir, Pabhoi TE 556 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹5.00 L | 556 d | 0% | 48.2 | MEDIUM |
| Development of Namghar at Hanupam Gaon, Chengamari, Sootea 581 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹5.00 L | 581 d | 0% | 47.9 | MEDIUM |
| Development of Aluk Library at Nagsankar, Naltali 581 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹5.00 L | 581 d | 0% | 47.9 | MEDIUM |
| Construction of Yoga Bhawan at Yoga Centre Pani Bharal, Bisw 581 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹5.00 L | 581 d | 0% | 47.9 | MEDIUM |
| Development of Kurmi Samaj Namghar, Ratowa 581 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹5.00 L | 581 d | 0% | 47.9 | MEDIUM |
| Construction of Rangamancha at Borkura Kuwari, Borkura 592 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹5.00 L | 592 d | 0% | 47.9 | MEDIUM |
| Development of Chaporial Namghar, Sootea 594 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹5.00 L | 594 d | 0% | 47.9 | MEDIUM |
| Construction of C/Hall near Balijan Patharbasti Hari Mandir, 594 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹5.00 L | 594 d | 0% | 47.9 | MEDIUM |