Construction of C/Hall near Balijan Patharbasti Hari Mandir,

Community Buildings

Assam / BISWANATH — Biswanath(Deputy Commissioner Biswanath_IDA) · Pallab Lochan Das (Sonitpur)

Construction of C/Hall near Balijan Patharbasti Hari Mandir, Chengamari, Sootea

Overall risk score
48/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost31
Delay100
Duplication0
Agency100
Compliance0
Sanctioned
₹5.00 L
Delay
594d
Cost deviation
0%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 594 days beyond expected completionPublished dates
  • 94% of this agency's ₹26,228,960 spend went to one vendor (LOHIT BHUYAN), across 2 vendors and 196 transactionsStatistics · Herfindahl-Hirschman index

Decision trail

Nobody has recorded a decision on this work yet.