Open this link on a larger screen to see the verification queue.
77 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Biswanath(Deputy Commissioner Biswanath_IDA) | 77 | 13 | ₹7.06 Cr | 12 | 24.3 | R ENTERPRISE 42% of spend · 23 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Ranjit Dutta Sonitpur | 74 | ₹6.49 Cr | 10 |
| Pabitra Margherita Sitting Rajya Sabha | 1 | ₹15.00 L | 1 |
| Jogen Mohan Sitting Rajya Sabha | 1 | ₹30.00 L | 1 |
| Gaurav Gogoi JORHAT | 1 | ₹12.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 29 | ₹2.00 Cr | 2 |
| Religious & Cultural | 18 | ₹1.37 Cr | 3 |
| Roads & Paving | 11 | ₹1.03 Cr | 1 |
| Education | 8 | ₹1.26 Cr | 3 |
| Boundary & Protection | 7 | ₹57.45 L | 1 |
| Sports | 2 | ₹34.83 L | 1 |
| Other | 1 | ₹23.00 L | 1 |
| Equipment & Vehicles | 1 | ₹24.78 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Assam Type Conference Hall Building for SP O ₹1,540,264 against a ₹500,000 median for Community Buildings works in BISWANATH (208% above, 46 peer works) | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹15.40 L | 234 d | +208% | 56.1 | MEDIUM |
| Construction of Rangamancha at Bengabari Gaon, Baralimara, B Completed work has no photographic documentation on record | Biswanath(Deputy Commissioner Biswanath_IDA) | Completed | ₹15.00 L | — | +200% | 55.6 | MEDIUM |
| Re Construction of Dakhin Kalabari Shivmandir,LAC-Gahpur,784 ₹3,000,000 against a ₹500,000 median for Religious & Cultural works in BISWANATH (500% above, 34 peer works) | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹30.00 L | — | +500% | 51.1 | MEDIUM |
| Renovation of Karbi Hostel at Biswanath District, Falfali ₹1,000,000 against a ₹500,000 median for Education works in BISWANATH (100% above, 18 peer works) | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹10.00 L | 125 d | +100% | 48.4 | MEDIUM |
| Construction of One Floating Fountain at Gohpur Borpukhuri Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹23.00 L | 188 d | 0% | 45.4 | MEDIUM |
| Construction of Community Hall at RL Memorial English School ₹1,000,000 against a ₹500,000 median for Education works in BISWANATH (100% above, 18 peer works) | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹10.00 L | 90 d | +100% | 43.6 | MEDIUM |
| Construction of Behali Degree College (1st Floor) Ph-I ₹5,000,000 against a ₹500,000 median for Education works in BISWANATH (900% above, 18 peer works) | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹50.00 L | 90 d | +900% | 43.6 | MEDIUM |
| Construction of Community Hall near Sootea Natya Bhawan ₹1,000,000 against a ₹500,000 median for Community Buildings works in BISWANATH (100% above, 46 peer works) | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹10.00 L | 77 d | +100% | 41.8 | MEDIUM |
| Construction of Dining Room at Nagasankar Stadium Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹10.00 L | 252 d | 0% | 41.5 | MEDIUM |
| Construction of Boundary wall around Boidik Sewa Ashram Falf Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹10.00 L | 234 d | +30% | 41.1 | MEDIUM |
| Renovation of Anchalik Grammya Bikash Kendra Panibharal Namg 180 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹7.00 L | 180 d | +40% | 41.1 | MEDIUM |
| Construction of Single Cell 2mx2m Box Culvert at Birijan Vil 255 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹6.00 L | 255 d | -13% | 40.1 | MEDIUM |
| Construction of Bhakatchuk Community Hall 195 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹6.00 L | 195 d | +20% | 39.0 | LOW |
| Remaining works of Cultural Centre of Asom Boidik Vaishnab M 255 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹5.00 L | 255 d | 0% | 39.0 | LOW |
| Construction of Bilotia Ranga Mancha at Bilotia 195 days beyond expected completion | Biswanath(Deputy Commissioner Biswanath_IDA) | Recommended | ₹4.00 L | 195 d | -20% | 38.1 | LOW |