| 1 | Construction of the Sanskritik Bhawan at Pachim Bhatnapaity, Education — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹2,500,000 against a ₹500,000 median for Education works in BARPETA (400% above, 38 peer works)
- 336 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹25.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 2 | Construction of the Sanskritik Bhawan at Pachim Bhatnapaity, Education — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹2,500,000 against a ₹500,000 median for Education works in BARPETA (400% above, 38 peer works)
- 336 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹25.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 3 | Construction of shed Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹1,500,000 against a ₹598,857 median for Community Buildings works in RAIGARH (150% above, 37 peer works)
- 310 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹15.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 4 | Construction of community center for the welfare of Halva Sa Community Buildings — KONDAGAON(DISTRICT COLLECTOR KONDAGAON_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KONDAGAON (100% above, 49 peer works)
- 350 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KONDAGAON | ₹10.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 5 | Construction of buildings for community cultural activities Community Buildings — KONDAGAON(DISTRICT COLLECTOR KONDAGAON_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KONDAGAON (100% above, 49 peer works)
- 350 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KONDAGAON | ₹10.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 6 | Construction of common work sheds/ common covered sitting ar Community Buildings — KONDAGAON(DISTRICT COLLECTOR KONDAGAON_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KONDAGAON (100% above, 49 peer works)
- 350 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KONDAGAON | ₹10.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 7 | Construction of community center for the welfare of Halva Sa Community Buildings — KONDAGAON(DISTRICT COLLECTOR KONDAGAON_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KONDAGAON (100% above, 49 peer works)
- 350 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KONDAGAON | ₹10.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 8 | Construction of buildings for community cultural activities Community Buildings — KONDAGAON(DISTRICT COLLECTOR KONDAGAON_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KONDAGAON (100% above, 49 peer works)
- 350 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KONDAGAON | ₹10.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 9 | Construction of common work sheds/ common covered sitting ar Community Buildings — KONDAGAON(DISTRICT COLLECTOR KONDAGAON_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in KONDAGAON (100% above, 49 peer works)
- 350 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KONDAGAON | ₹10.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 10 | C.C. ROAD NIRMAN KARYA Roads & Paving — MAHASAMUND(DISTRICT COLLECTOR MAHASAMUND_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in MAHASAMUND (100% above, 78 peer works)
- 254 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MAHASAMUND | ₹10.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 11 | Construction of community centers/community halls and its Bo Community Buildings — DURG(DISTRICT COLLECTOR DURG_IDA) - ₹3,000,000 against a ₹598,680 median for Community Buildings works in DURG (401% above, 122 peer works)
- 367 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| DURG | ₹30.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 12 | Construction of community centers/community halls and its Bo Community Buildings — DURG(DISTRICT COLLECTOR DURG_IDA) - ₹3,000,000 against a ₹598,680 median for Community Buildings works in DURG (401% above, 122 peer works)
- 367 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| DURG | ₹30.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 13 | Construction of Community Centre Building at Gram Panchayat Community Buildings — SAKTI(COLLECTOR SAKTI_IDA) - ₹2,300,000 against a ₹500,000 median for Community Buildings works in SAKTI (360% above, 12 peer works)
- 367 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAKTI | ₹23.00 L | HIGH 70
cost 25delay 25duplication 20 | |
| 14 | Construction of Community Centre Building at Gram Panchayat Community Buildings — SAKTI(COLLECTOR SAKTI_IDA) - ₹2,300,000 against a ₹500,000 median for Community Buildings works in SAKTI (360% above, 12 peer works)
- 367 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SAKTI | ₹23.00 L | HIGH 70
cost 25delay 25duplication 20 | |
| 15 | CC ROAD NIRMAN Roads & Paving — DURG(DISTRICT COLLECTOR DURG_IDA) - ₹1,000,000 against a ₹520,000 median for Roads & Paving works in DURG (92% above, 109 peer works)
- 724 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| DURG | ₹10.00 L | MEDIUM 70
delay 25cost 23duplication 20 | |
| 16 | construction of community hall Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹1,000,000 against a ₹598,857 median for Community Buildings works in RAIGARH (67% above, 37 peer works)
- 310 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹10.00 L | MEDIUM 69
delay 25duplication 20cost 17 | |
| 17 | Construction of community hall Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹1,000,000 against a ₹598,857 median for Community Buildings works in RAIGARH (67% above, 37 peer works)
- 310 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹10.00 L | MEDIUM 69
delay 25duplication 20cost 17 | |
| 18 | Construction of Community hall Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹1,000,000 against a ₹598,857 median for Community Buildings works in RAIGARH (67% above, 37 peer works)
- 310 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹10.00 L | MEDIUM 69
delay 25duplication 20cost 17 | |
| 19 | Construction of Community building Community Buildings — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) - ₹2,000,000 against a ₹598,857 median for Community Buildings works in RAIGARH (234% above, 37 peer works)
- 113 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| RAIGARH | ₹20.00 L | MEDIUM 68
cost 25duplication 20delay 16 | |
| 20 | C.C. ROAD NIRMAN KARYA Roads & Paving — MAHASAMUND(DISTRICT COLLECTOR MAHASAMUND_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in MAHASAMUND (100% above, 78 peer works)
- 136 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MAHASAMUND | ₹10.00 L | MEDIUM 67
cost 25duplication 20delay 19 | |
| 21 | kodoli devgudi ke samip samudayik bhavan me 200 metre bounda Community Buildings — BIJAPUR(Collector Bijapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 320 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 90% delay rate across its projects
| BIJAPUR | ₹13.21 L | MEDIUM 67
delay 25duplication 15agency 14 | |
| 22 | nelasnar ke devgudi ke samip samudayik bhavan me 200 metre Community Buildings — BIJAPUR(Collector Bijapur_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 320 days beyond expected completion
Read more (2 more)Show less- 98% similarity with another nearby work
- Implementing agency has a 90% delay rate across its projects
| BIJAPUR | ₹13.21 L | MEDIUM 67
delay 25duplication 15agency 14 | |
| 23 | samudayik bhawan Community Buildings — BALOD(Collector Balod_IDA) - 189 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 66% of this agency's ₹26,513,937 spend went to one vendor (CMHO BALOD), across 15 vendors and 43 transactions
| BALOD | ₹7.00 L | MEDIUM 65
delay 25duplication 20agency 10 | |
| 24 | Common work sheds Community Buildings — Uttar Bastar Kanker(DISTRICT COLLECTOR KANKER_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 765 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 56% of this agency's ₹53,357,768 spend went to one vendor (Samriddhi Enterprises), across 53 vendors and 113 transactions
| UTTAR BASTAR KANKER | ₹5.00 L | MEDIUM 64
delay 25duplication 20cost 12 | |
| 25 | 2 units Borewell drilling and installation of pump along wit Water — Sarangarh-Bilaigarh(Collector SB_IDA) - ₹500,000 against a ₹300,000 median for Water works in SARANGARH-BILAIGARH (67% above, 35 peer works)
- 309 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SARANGARH-BILAIGARH | ₹5.00 L | MEDIUM 64
delay 25duplication 20cost 17 | |