21 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BIJAPUR(Collector Bijapur_IDA) | 21 | 2 | ₹1.76 Cr | 13 | 43.7 | GRAM PANCHAYAT HALLOOR 15% of spend · 15 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Mahesh Kashyap BASTAR | 21 | ₹1.76 Cr | 13 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 11 | ₹1.01 Cr | 7 |
| Roads & Paving | 8 | ₹65.40 L | 5 |
| Education | 1 | ₹8.40 L | 0 |
| Equipment & Vehicles | 1 | ₹1.30 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| kodoli devgudi ke samip samudayik bhavan me 200 metre bounda Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹13.21 L | 320 d | +36% | 66.9 | MEDIUM |
| nelasnar ke devgudi ke samip samudayik bhavan me 200 metre Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹13.21 L | 320 d | +36% | 66.9 | MEDIUM |
| tarlaguda panchayat me 300 metre c.c.road nirman karya Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹8.91 L | 320 d | +3% | 50.0 | MEDIUM |
| gram hallor gaytri mandir ke samip me shed nirman karya Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹8.91 L | 320 d | -8% | 50.0 | MEDIUM |
| gram panchayat kotapalli me 300 metre c.c.road nirman karya Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹8.78 L | 320 d | +2% | 49.9 | MEDIUM |
| gram madded me 250 metre c.c.road nirman karya Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹7.50 L | 320 d | -13% | 49.1 | MEDIUM |
| jangti devraj ghar se n.h.63 tak 200 metre c.c.sadak nirman Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹6.93 L | 320 d | -20% | 49.0 | MEDIUM |
| gram toynar pitlapara me 02 metre span puliya nirman karya 320 days beyond expected completion | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹5.72 L | 320 d | -34% | 48.1 | MEDIUM |
| ram mandir prangan ke samip shed nirman karya 320 days beyond expected completion | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹4.76 L | 320 d | -51% | 47.3 | MEDIUM |
| bhadrakali mandir ke samip shed nirman karya 320 days beyond expected completion | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹4.76 L | 320 d | -51% | 47.3 | MEDIUM |
| chikatraj baba mandir ke samip shed nirman karya 320 days beyond expected completion | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹4.76 L | 320 d | -51% | 47.3 | MEDIUM |
| gram murkinar patel para ke malesh dubba (divyangjan) ko bat 240 days beyond expected completion | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹1.30 L | 240 d | 0% | 46.8 | MEDIUM |
| hinglajin gudi mata mandir ke samip samudayik bhavan hetu 20 Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹13.40 L | 130 d | +38% | 42.1 | MEDIUM |
| gram ilmidi ke kanya chatrawas me boundarywall nirman evam b 117 days beyond expected completion | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹9.73 L | 117 d | +0% | 37.9 | LOW |
| gram kutru ke guttakhandi para me samudayik bhavan nirman ka 117 days beyond expected completion | BIJAPUR(Collector Bijapur_IDA) | Recommended | ₹9.73 L | 117 d | 0% | 37.9 | LOW |