Open this link on a larger screen to see the verification queue.
40 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | 40 | 39 | ₹4.12 Cr | 0 | 16.6 | TUIKUAL NORTH LOCAL COUNCIL 12% of spend · 33 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| C. Lalrosanga MIZORAM | 40 | ₹4.12 Cr | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 26 | ₹2.81 Cr | 0 |
| Boundary & Protection | 5 | ₹32.00 L | 0 |
| Drainage & Sanitation | 4 | ₹39.00 L | 0 |
| Education | 2 | ₹30.00 L | 0 |
| Health | 1 | ₹10.00 L | 0 |
| Community Buildings | 1 | ₹10.00 L | 0 |
| Sports | 1 | ₹10.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of road - Concrete pavement approach road to Ve 554 days beyond expected completion | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Recommended | ₹6.00 L | 554 d | -11% | 35.6 | LOW |
| Construction of road (PCC Flooring) at Second lane, Phunchaw Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹15.00 L | — | +122% | 30.1 | LOW |
| Construction of boundary wall at Saikhamakawn Cemetery Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹10.00 L | — | +100% | 30.1 | LOW |
| Construction of Farmers Utility link road at Lungpherzau, Mu Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹20.00 L | — | +196% | 30.1 | LOW |
| Construction of Public Utility Community Centre at Chawngkhu Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹10.00 L | — | +300% | 30.1 | LOW |
| Construction of Library cum Committee Room at Women Centre a Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹10.00 L | — | +300% | 30.1 | LOW |
| Construction of Public Step/Passage and Hand Railing at Tuik Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹30.00 L | — | +344% | 30.1 | LOW |
| Construction of public road (PCC Flooring) at Muthi Village, Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹15.00 L | — | +122% | 30.1 | LOW |
| Construction of MUP Library cum Recreation Centre at N Khawd Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹20.00 L | — | +700% | 30.1 | LOW |
| Construction of dumping ground approach road (PCC Flooring) Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹25.00 L | — | +270% | 30.1 | LOW |
| Construction of road (PCC flooring) near Chhingtei’s road, D Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹13.00 L | — | +93% | 28.3 | LOW |
| Construction of farmers link road at Darlawng Village, Aizaw ₹1,500,000 against a ₹675,000 median for Roads & Paving works in AIZAWL (122% above, 50 peer works) | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹15.00 L | — | +122% | 25.6 | LOW |
| Construction of boundary wall at approach road to Vai Lui, M Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹10.00 L | — | +48% | 17.2 | LOW |
| Construction of road (RCC pavement) Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹10.00 L | — | +48% | 17.2 | LOW |
| Construction of boundary wall near Society road, Mualpui, Sa Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹10.00 L | — | +48% | 17.2 | LOW |