77 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | 77 | 33 | ₹3.99 Cr | 1 | 10.4 | TUIKUAL SOUTH LOCAL COUNCIL 6% of spend · 49 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Richard Vanlalhmangaiha MIZORAM | 77 | ₹3.99 Cr | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 28 | ₹1.00 Cr | 0 |
| Roads & Paving | 24 | ₹1.32 Cr | 1 |
| Community Buildings | 11 | ₹52.40 L | 0 |
| Boundary & Protection | 6 | ₹37.20 L | 0 |
| Equipment & Vehicles | 2 | ₹20.57 L | 0 |
| Health | 2 | ₹20.57 L | 0 |
| Sports | 2 | ₹18.00 L | 0 |
| Water | 1 | ₹2.50 L | 0 |
| Drainage & Sanitation | 1 | ₹15.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Govt. Upper Primary School Road PCC Flooring 352 days beyond expected completion | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Recommended | ₹2.50 L | 352 d | -63% | 46.6 | MEDIUM |
| Construction of retaining wall and Volley Ball play ground a ₹1,500,000 against a ₹500,000 median for Boundary & Protection works in AIZAWL (200% above, 11 peer works) | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Recommended | ₹15.00 L | 57 d | +200% | 33.6 | LOW |
| Purchase of Books for BAR Association Library 164 days beyond expected completion | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Recommended | ₹50,000 | 164 d | -80% | 32.1 | LOW |
| Purchase of Bolero Pickup 4wd ps Ambulance Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹10.29 L | — | 0% | 30.9 | LOW |
| Purchase of Bolero Pickup 4wd ps Ambulance Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹10.29 L | — | 0% | 30.9 | LOW |
| Construction of Hall at Durtlang Cemetary ₹750,000 against a ₹250,000 median for Community Buildings works in AIZAWL (200% above, 12 peer works) | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Recommended | ₹7.50 L | 38 d | +200% | 30.9 | LOW |
| Construction of Information Centre cum Library Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹12.50 L | — | +400% | 30.1 | LOW |
| PCC flooring of Government Primary School, Lawipu Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹5.00 L | — | +100% | 30.1 | LOW |
| Construction of Committee Room at Govt. Aizawl College Completed work has no photographic documentation on record | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Completed | ₹15.00 L | — | +500% | 30.1 | LOW |
| Renovation of Aizawl Press Club Building ₹990,000 against a ₹250,000 median for Community Buildings works in AIZAWL (296% above, 12 peer works) | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Recommended | ₹9.90 L | 12 d | +296% | 27.3 | LOW |
| PCC pavement flooring. Approach road to Dardak Thingsulthlia ₹1,500,000 against a ₹675,000 median for Roads & Paving works in AIZAWL (122% above, 50 peer works) | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Recommended | ₹15.00 L | — | +122% | 25.6 | LOW |
| Construction of RCC of Transformer 500 KV Station, retaining ₹1,490,000 against a ₹675,000 median for Roads & Paving works in AIZAWL (121% above, 50 peer works) | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Recommended | ₹14.90 L | — | +121% | 25.6 | LOW |
| RCC Roof slabbing of Govt.Tuithiang Middle School ₹980,000 against a ₹250,000 median for Education works in AIZAWL (292% above, 30 peer works) | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Recommended | ₹9.80 L | — | +292% | 25.6 | LOW |
| Formation cutting, Construction of PCC Flooring at Lunghlu r ₹1,500,000 against a ₹675,000 median for Roads & Paving works in AIZAWL (122% above, 50 peer works) | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Recommended | ₹15.00 L | — | +122% | 25.6 | LOW |
| Construction of Recreation Centre at Aibawk, Aizawl District ₹1,500,000 against a ₹250,000 median for Community Buildings works in AIZAWL (500% above, 12 peer works) | AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) | Recommended | ₹15.00 L | — | +500% | 25.6 | LOW |