Construction of Public Utility Community Centre at Chawngkhu
Community Buildings
Mizoram / AIZAWL — AIZAWL(DEPUTY COMMISSIONER AIZAWL_IDA) · C. Lalrosanga (MIZORAM)
Construction of Public Utility Community Centre at Chawngkhupa Inhmun tlang, Sailam, Aizawl
Overall risk score
30/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay0
Duplication0
Agency4
Compliance30
Sanctioned
₹10.00 L
Delay
0d
Cost deviation
300%
Work status
Completed
AI powered · gemini-flash-liteWhy was this flagged?
- Completed work has no photographic documentation on recordStated compliance rule
- ₹1,000,000 against a ₹250,000 median for Community Buildings works in AIZAWL (300% above, 12 peer works)Peer comparison · sector labelled by Gemini Flash Lite
Decision trail
Nobody has recorded a decision on this work yet.