184 works across 1 implementing agency, recommended by 6 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | 184 | 24 | ₹12.14 Cr | 17 | 17.3 | Dharwad Research and Technology Incubator Foundation 67% of spend · 30 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Pralhad Joshi DHARWAD | 177 | ₹8.47 Cr | 10 |
| Narayanasa K. Bhandage Sitting Rajya Sabha | 3 | ₹20.00 L | 3 |
| Nirmala Sitharaman Sitting Rajya Sabha | 1 | ₹3.19 Cr | 1 |
| Ramesh Chandappa Jigajinagi BIJAPUR | 1 | ₹10.00 L | 1 |
| Jaggesh Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
| G.C. Chandrashekhar Sitting Rajya Sabha | 1 | ₹8.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 167 | ₹7.92 Cr | 12 |
| Religious & Cultural | 7 | ₹40.00 L | 0 |
| Education | 5 | ₹3.52 Cr | 4 |
| Other | 3 | ₹21.00 L | 0 |
| Roads & Paving | 1 | ₹5.00 L | 0 |
| Water | 1 | ₹4.50 L | 1 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Development of Infrastructure for Skill Training Centre. Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹10.00 L | 558 d | 0% | 68.1 | MEDIUM |
| Construction of Community Hall. ₹750,000 against a ₹500,000 median for Community Buildings works in DHARWAD (50% above, 274 peer works) | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹7.50 L | 289 d | +50% | 68.0 | MEDIUM |
| Construction of Community Hall. ₹750,000 against a ₹500,000 median for Community Buildings works in DHARWAD (50% above, 274 peer works) | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹7.50 L | 289 d | +50% | 68.0 | MEDIUM |
| Construction of cultural Hall. 311 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹5.00 L | 311 d | 0% | 63.7 | MEDIUM |
| SETTING UP OF BIONEST - BIO - INCUBATION CENTRE AT IIT DHARW ₹31,900,000 against a ₹1,000,000 median for Education works in DHARWAD (3090% above, 8 peer works) | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Completed | ₹3.19 Cr | — | +3090% | 55.5 | MEDIUM |
| construction of sabha bhavan at dharwad district,dharwad tal ₹800,000 against a ₹500,000 median for Community Buildings works in DHARWAD (60% above, 274 peer works) | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹8.00 L | 26 d | +60% | 49.2 | MEDIUM |
| Construction of Class Room For Under the Trust of Vanita Sev 197 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹10.00 L | 197 d | 0% | 45.0 | MEDIUM |
| Construction of Community Hall at Hosategur Village Near Shr 429 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹4.00 L | 429 d | -20% | 44.9 | MEDIUM |
| Construction of Community Bhavan of Veerashaiv Jangam Societ 430 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹4.50 L | 430 d | -10% | 44.8 | MEDIUM |
| Construction of College room of CBS Charitable Foudation at 430 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹5.00 L | 430 d | -50% | 44.6 | MEDIUM |
| Construction of Cultural Bhavan at Chabbi Village Near Vitho 429 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹2.50 L | 429 d | -50% | 44.1 | MEDIUM |
| Construction of Community Bhavan at Dharwad Taluk Kurubagatt 232 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹5.00 L | 232 d | 0% | 43.0 | MEDIUM |
| Construction of Cultural Bhavan at Dharwad Taluk Kotur Villa 232 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹5.00 L | 232 d | 0% | 43.0 | MEDIUM |
| Instalation of Drinking Water Plant at Hubli City Ward No 50 232 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹4.50 L | 232 d | 0% | 43.0 | MEDIUM |
| Construction Community Bhavan at Kalghatagi Taluk Dhulikopp 176 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹5.00 L | 176 d | 0% | 41.2 | MEDIUM |