Construction of Community Hall at Hosategur Village Near Shr

Community Buildings

Karnataka / DHARWAD — DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) · Pralhad Joshi (DHARWAD)

Construction of Community Hall at Hosategur Village Near Shri Girimalleshwar Math Pry No 518 Continue work

Overall risk score
45/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost38
Delay100
Duplication0
Agency70
Compliance0
Sanctioned
₹4.00 L
Delay
429d
Cost deviation
-20%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 429 days beyond expected completionPublished dates
  • 67% of this agency's ₹47,709,751 spend went to one vendor (Dharwad Research and Technology Incubator Foundation), across 30 vendors and 37 transactionsStatistics · Herfindahl-Hirschman index

Decision trail

Nobody has recorded a decision on this work yet.