136 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | 136 | 103 | ₹10.10 Cr | 11 | 15.5 | Dharwad Research and Technology Incubator Foundation 37% of spend · 91 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Pralhad Joshi DHARWAD | 130 | ₹6.53 Cr | 5 |
| Narayanasa K. Bhandage Sitting Rajya Sabha | 3 | ₹20.00 L | 3 |
| Nirmala Sitharaman Sitting Rajya Sabha | 1 | ₹3.19 Cr | 1 |
| Jaggesh Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
| G.C. Chandrashekhar Sitting Rajya Sabha | 1 | ₹8.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 107 | ₹5.25 Cr | 9 |
| Religious & Cultural | 18 | ₹86.71 L | 0 |
| Sports | 5 | ₹33.92 L | 0 |
| Education | 3 | ₹3.35 Cr | 2 |
| Equipment & Vehicles | 1 | ₹19.50 L | 0 |
| Boundary & Protection | 1 | ₹4.99 L | 0 |
| Roads & Paving | 1 | ₹4.99 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Development of Infrastructure for Skill Training Centre. Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹10.00 L | 558 d | 0% | 62.0 | MEDIUM |
| Construction of Community Hall. ₹750,000 against a ₹500,000 median for Community Buildings works in DHARWAD (50% above, 274 peer works) | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹7.50 L | 289 d | +50% | 61.9 | MEDIUM |
| Construction of Community Hall. ₹750,000 against a ₹500,000 median for Community Buildings works in DHARWAD (50% above, 274 peer works) | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹7.50 L | 289 d | +50% | 61.9 | MEDIUM |
| Construction of cultural Hall. 311 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹5.00 L | 311 d | 0% | 57.6 | MEDIUM |
| Construction of Community Hall (1st Floor) at Dharwad City , ₹1,000,000 against a ₹500,000 median for Community Buildings works in DHARWAD (100% above, 274 peer works) | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹10.00 L | 580 d | +100% | 54.4 | MEDIUM |
| Construction of cultural bhavan at Kundagol Tq Saunshi villa 548 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹5.00 L | 548 d | 0% | 50.3 | MEDIUM |
| SETTING UP OF BIONEST - BIO - INCUBATION CENTRE AT IIT DHARW ₹31,900,000 against a ₹1,000,000 median for Education works in DHARWAD (3090% above, 8 peer works) | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Completed | ₹3.19 Cr | — | +3090% | 49.4 | MEDIUM |
| construction of sabha bhavan at dharwad district,dharwad tal ₹800,000 against a ₹500,000 median for Community Buildings works in DHARWAD (60% above, 274 peer works) | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹8.00 L | 26 d | +60% | 43.0 | MEDIUM |
| Construction of Cultural Bhavan at Kundagol Tq, Gudgeri vil 617 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹5.00 L | 617 d | 0% | 40.4 | MEDIUM |
| Construction of Cultural Bhavan at Kundagol Tq Gudgeri Villa 617 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹5.00 L | 617 d | 0% | 40.4 | MEDIUM |
| Construction of cultural bhavan at Kundagol Tq BENAKANAHALLI 548 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹4.00 L | 548 d | -20% | 40.2 | MEDIUM |
| Construction of cultural bhavan at Kundagol Tq Yaliwala vill 548 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹4.00 L | 548 d | -20% | 38.0 | LOW |
| Construction of cultural bhavan at Kundagol Tq Kundagol city 548 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹4.00 L | 548 d | -20% | 38.0 | LOW |
| Construction of COMMUNITY bhavan at HUBBALLI Tq KOTGONDHUNAS 548 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹4.00 L | 548 d | -20% | 38.0 | LOW |
| Construction of Cultural bhavan at Hubli Tq Hebsur Village P 630 days beyond expected completion | DHARWAD(DEPUTY COMMISSIONER DHARWAR_IDA) | Recommended | ₹5.00 L | 630 d | 0% | 38.0 | LOW |