50 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | RAMBAN(Deputy Commissioner Ramban_IDA) | 50 | 16 | ₹2.02 Cr | 13 | 23.0 | Vikram Enterprises 67% of spend · 15 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Jitendra Singh UDHAMPUR | 50 | ₹2.02 Cr | 13 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 12 | ₹33.79 L | 6 |
| Drainage & Sanitation | 12 | ₹31.79 L | 0 |
| Boundary & Protection | 11 | ₹23.51 L | 4 |
| Religious & Cultural | 7 | ₹15.58 L | 1 |
| Water | 2 | ₹5.00 L | 1 |
| Education | 2 | ₹4.60 L | 1 |
| Health | 1 | ₹2.50 L | 0 |
| Equipment & Vehicles | 1 | ₹78.50 L | 0 |
| Sports | 1 | ₹4.00 L | 0 |
| Community Buildings | 1 | ₹2.50 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Protection Wall near house to Sh. Parkash S ₹300,000 against a ₹163,000 median for Boundary & Protection works in RAMBAN (84% above, 17 peer works) | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹3.00 L | 324 d | +84% | 56.8 | MEDIUM |
| Construction of Tile Work ₹400,000 against a ₹200,000 median for Roads & Paving works in RAMBAN (100% above, 19 peer works) | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹4.00 L | — | +100% | 55.8 | MEDIUM |
| Construction of Tile Work ₹400,000 against a ₹200,000 median for Roads & Paving works in RAMBAN (100% above, 19 peer works) | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹4.00 L | — | +100% | 55.8 | MEDIUM |
| Construction of Protection Wall ₹300,000 against a ₹163,000 median for Boundary & Protection works in RAMBAN (84% above, 17 peer works) | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹3.00 L | — | +84% | 51.8 | MEDIUM |
| Construction of Protection Wall ₹300,000 against a ₹163,000 median for Boundary & Protection works in RAMBAN (84% above, 17 peer works) | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹3.00 L | — | +84% | 51.8 | MEDIUM |
| Construction of protection wall near Old Neelna Khandar Kund ₹250,000 against a ₹163,000 median for Boundary & Protection works in RAMBAN (53% above, 17 peer works) | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹2.50 L | 189 d | +53% | 49.2 | MEDIUM |
| Construction of Pacca Path from Mohalla – Manshal, Ward no. 324 days beyond expected completion | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹3.00 L | 324 d | 0% | 43.9 | MEDIUM |
| New installation of hand pump near the house of Abdul Gani , 266 days beyond expected completion | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹2.00 L | 266 d | 0% | 43.8 | MEDIUM |
| Construction of tile work From Nagni Mandir to Akhmul Devta 266 days beyond expected completion | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹3.00 L | 266 d | 0% | 43.6 | MEDIUM |
| Construction of Tile Work ₹300,000 against a ₹200,000 median for Roads & Paving works in RAMBAN (50% above, 19 peer works) | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹3.00 L | — | +50% | 43.3 | MEDIUM |
| Construction of Tile work ₹300,000 against a ₹200,000 median for Roads & Paving works in RAMBAN (50% above, 19 peer works) | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹3.00 L | — | +50% | 43.3 | MEDIUM |
| Construction of tile work ₹300,000 against a ₹200,000 median for Roads & Paving works in RAMBAN (50% above, 19 peer works) | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹3.00 L | — | +50% | 43.3 | MEDIUM |
| Construction of tile work from National Highway to the house 189 days beyond expected completion | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹2.00 L | 189 d | 0% | 42.3 | MEDIUM |
| Purchase of one (1) Critical Care Mobile Medical Van to Dist Completed work has no photographic documentation on record | RAMBAN(Deputy Commissioner Ramban_IDA) | Completed | ₹78.50 L | — | 0% | 37.6 | LOW |
| Construction of P path from the house of Ashraf to the hous ₹350,000 against a ₹200,000 median for Roads & Paving works in RAMBAN (75% above, 19 peer works) | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹3.50 L | — | +75% | 29.6 | LOW |