26 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | RAMBAN(Deputy Commissioner Ramban_IDA) | 26 | 16 | ₹1.04 Cr | 4 | 19.6 | Sh Rattan Singh So Lakhpat Singh Ro Beeranbass Hochak Pogal District Ramban Contractor 28% of spend · 18 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Jitendra Singh UDHAMPUR | 26 | ₹1.04 Cr | 4 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 7 | ₹11.62 L | 0 |
| Boundary & Protection | 6 | ₹9.49 L | 0 |
| Drainage & Sanitation | 5 | ₹29.97 L | 2 |
| Community Buildings | 4 | ₹45.62 L | 2 |
| Sports | 2 | ₹5.00 L | 0 |
| Education | 1 | ₹1.64 L | 0 |
| Other | 1 | ₹82,400 | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Toilet Complex/Bathroom at Village Neera nea ₹1,000,000 against a ₹300,000 median for Drainage & Sanitation works in RAMBAN (233% above, 17 peer works) | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹10.00 L | 567 d | +233% | 53.2 | MEDIUM |
| Toilet Block at Neera ₹1,500,000 against a ₹300,000 median for Drainage & Sanitation works in RAMBAN (400% above, 17 peer works) | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹15.00 L | 567 d | +400% | 53.2 | MEDIUM |
| Yatri Shed near Chamunda Mata Mandir, Sarvadhar, Block Ukhra Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹22.60 L | 565 d | 0% | 44.9 | MEDIUM |
| Construction of Community Hall near Ramleela Ground Maitra w Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹19.60 L | 567 d | 0% | 44.6 | MEDIUM |
| Construction of P/path from Gadhi Nalla to Gadhi Grath, ward 565 days beyond expected completion | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹2.00 L | 565 d | 0% | 35.5 | LOW |
| Construction of tractor road from Sawni Bus stand to Patiswa 565 days beyond expected completion | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹2.00 L | 565 d | 0% | 35.5 | LOW |
| P/path Chuni Lal Mohalla Lower Marlab, Pyt. Hochak, Ukhral R 565 days beyond expected completion | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹2.00 L | 565 d | 0% | 35.5 | LOW |
| Construction of shed near Shiv Mandir Bowli Bazar Ramban, Bl 565 days beyond expected completion | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹2.00 L | 565 d | 0% | 35.5 | LOW |
| Construction of Ground levelling & Tile work at pyt. Demote 565 days beyond expected completion | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹2.50 L | 565 d | 0% | 35.3 | LOW |
| Construction of park at Pyt Seri, Ward no. 3, Kundi near Jag 565 days beyond expected completion | RAMBAN(Deputy Commissioner Ramban_IDA) | Recommended | ₹2.50 L | 565 d | 0% | 35.3 | LOW |
| Protection wall near house to Shri Parkash Singh to Shri Bha | RAMBAN(Deputy Commissioner Ramban_IDA) | Completed | ₹2.13 L | — | +30% | 10.8 | LOW |
| Protection work, ward no. 2, Pyt. Khari Lower B, Block Khari Completed work has no photographic documentation on record | RAMBAN(Deputy Commissioner Ramban_IDA) | Completed | ₹1.37 L | — | -16% | 10.3 | LOW |
| Protection wall near house to Shri Sunit Singh to Shri Umesh | RAMBAN(Deputy Commissioner Ramban_IDA) | Completed | ₹1.98 L | — | +22% | 8.6 | LOW |
| Land leveling at Narad Mohalla, Ward no. 5, Village Phagmull | RAMBAN(Deputy Commissioner Ramban_IDA) | Completed | ₹82,400 | — | 0% | 7.2 | LOW |
| P/path at Jaggi Mohalla ward no. 7, Pyt. Neera, Block Ramban | RAMBAN(Deputy Commissioner Ramban_IDA) | Completed | ₹1.21 L | — | -40% | 6.3 | LOW |