57 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) 1 high risk | 57 | 38 | ₹3.07 Cr | 4 | 21.4 | LND Dvnt Nayeralga Med Clg Nayeralga 7% of spend · 53 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Badruddin Ajmal DHUBRI | 55 | ₹2.87 Cr | 2 |
| Rwngwra Narzary Sitting Rajya Sabha | 2 | ₹20.00 L | 2 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 23 | ₹1.26 Cr | 0 |
| Education | 18 | ₹1.04 Cr | 3 |
| Boundary & Protection | 11 | ₹51.81 L | 1 |
| Community Buildings | 4 | ₹22.07 L | 0 |
| Water | 1 | ₹2.88 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Purchase of furniture for auditorium hall of Sapatgram colle ₹1,500,000 against a ₹401,800 median for Education works in DHUBRI (273% above, 29 peer works) | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹15.00 L | 199 d | +273% | 74.9 | HIGH |
| Purchase of Furniture of Ratnapith College, Chapar. 199 days beyond expected completion | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹5.00 L | 199 d | +24% | 56.7 | MEDIUM |
| Const. of Community Hall cum library of Alomganj Bazar (Ph – ₹2,304,960 against a ₹401,800 median for Education works in DHUBRI (474% above, 29 peer works) | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹23.05 L | 612 d | +474% | 54.9 | MEDIUM |
| Protection Measure against erosion by the river Brahmaputra ₹1,470,000 against a ₹448,832 median for Boundary & Protection works in DHUBRI (228% above, 57 peer works) | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹14.70 L | 624 d | +228% | 54.9 | MEDIUM |
| Const. of Guard wall near RCC Culvert at vill Dalsingeralga 625 days beyond expected completion | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹5.76 L | 625 d | +20% | 39.5 | LOW |
| Const. of RCC culvert with approach near Hazipara-Bhuddhari 631 days beyond expected completion | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹5.57 L | 631 d | +16% | 39.4 | LOW |
| Const. of Bolder Guard wall near Tipkai river at Jhaleralga 628 days beyond expected completion | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹4.80 L | 628 d | +7% | 38.5 | LOW |
| Const of Market shed at Balajan bazaar (Ph-II) 577 days beyond expected completion | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹4.80 L | 577 d | -4% | 38.2 | LOW |
| Const. of Iron Gate of Durahati Model High School (Ph-I) 612 days beyond expected completion | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹4.80 L | 612 d | +20% | 38.0 | LOW |
| Construction of Road from Subas Ch. Ray house to Azad Ali Mo 628 days beyond expected completion | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹3.84 L | 628 d | -20% | 37.9 | LOW |
| Construction of RCC Box Culvert at village Bhamondanga Pt-II 628 days beyond expected completion | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹3.84 L | 628 d | -20% | 37.9 | LOW |
| Construction of waiting shed nearby 17th No National High wa 628 days beyond expected completion | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹3.84 L | 628 d | -23% | 37.9 | LOW |
| Const. of road with Send Gravelling from Kadom Ali house to 631 days beyond expected completion | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹3.84 L | 631 d | -20% | 37.9 | LOW |
| Const. of Road from PWD road to Anowar Hussain house at vill 631 days beyond expected completion | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹2.40 L | 631 d | -50% | 37.5 | LOW |
| Construction of Market shed at Sonahat Bazar at vill- Dhafar 612 days beyond expected completion | DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) | Recommended | ₹3.82 L | 612 d | -24% | 37.4 | LOW |