Protection Measure against erosion by the river Brahmaputra
Boundary & Protection
Assam / DHUBRI — DHUBRI(DEPUTY COMMISSIONER DHUBRI_IDA) · Badruddin Ajmal (DHUBRI)
Protection Measure against erosion by the river Brahmaputra at vill. Kushbari .
Overall risk score
55/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency33
Compliance0
Sanctioned
₹14.70 L
Delay
624d
Cost deviation
228%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,470,000 against a ₹448,832 median for Boundary & Protection works in DHUBRI (228% above, 57 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 624 days beyond expected completionPublished dates
Decision trail