Construction of Community Hall near Sootea Natya Bhawan
Community Buildings
Assam / BISWANATH — Biswanath(Deputy Commissioner Biswanath_IDA) · Ranjit Dutta (Sonitpur)
Overall risk score
42/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay43
Duplication0
Agency40
Compliance0
Sanctioned
₹10.00 L
Delay
77d
Cost deviation
100%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,000,000 against a ₹500,000 median for Community Buildings works in BISWANATH (100% above, 46 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 77 days beyond expected completionPublished dates
- Implementing agency has a 40% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.