Ranked by how many works are waiting on verification, which is the queue a nodal authority actually has to clear. Open a district to see the agencies behind those works.
| # | District | Works | Completed | Agencies | Sanctioned | To verify | Flagged value | Avg score |
|---|---|---|---|---|---|---|---|---|
| 1 | KANNUR 28 high risk | 526 | 235 | 1 | ₹54.54 Cr | 158 | ₹28.86 Cr | 32.1 |
| 2 | MALAPPURAM 5 high risk | 619 | 409 | 1 | ₹42.89 Cr | 106 | ₹14.40 Cr | 23.1 |
| 3 | KOTTAYAM 9 high risk | 382 | 193 | 1 | ₹22.40 Cr | 105 | ₹10.50 Cr | 29.5 |
| 4 | KOZHIKODE 19 high risk | 374 | 265 | 1 | ₹28.04 Cr | 101 | ₹14.56 Cr | 25.5 |
| 5 | ERNAKULAM 4 high risk | 320 | 173 | 1 | ₹29.47 Cr | 85 | ₹15.67 Cr | 27.9 |
| 6 | THIRUVANANTHAPURAM 7 high risk | 592 | 465 | 1 | ₹30.70 Cr | 57 | ₹8.58 Cr | 17.4 |
| 7 | ALAPPUZHA | 142 | 62 | 1 | ₹15.00 Cr | 47 | ₹7.46 Cr | 29.2 |
| 8 | IDUKKI 4 high risk | 134 | 80 | 1 | ₹12.89 Cr | 35 | ₹6.59 Cr | 26.7 |
| 9 | PATHANAMTHITTA 3 high risk | 172 | 123 | 1 | ₹11.91 Cr | 33 | ₹5.52 Cr | 20.8 |
| 10 | PALAKKAD 2 high risk | 496 | 438 | 1 | ₹23.99 Cr | 28 | ₹8.46 Cr | 14.5 |
| 11 | KOLLAM 1 high risk | 152 | 102 | 1 | ₹12.12 Cr | 26 | ₹3.86 Cr | 23.4 |
| 12 | KASARAGOD | 270 | 239 | 1 | ₹10.29 Cr | 18 | ₹1.01 Cr | 17.1 |
| 13 | THRISSUR | 326 | 304 | 1 | ₹18.34 Cr | 15 | ₹2.84 Cr | 15.7 |
| 14 | WAYANAD 1 high risk | 67 | 33 | 1 | ₹8.18 Cr | 12 | ₹2.03 Cr | 28.9 |
Ordered by the share of allocation actually paid to vendors, lowest first — the members whose funds are moving slowest are the ones a nodal authority chases. “Committed” is money attached to a work but not yet paid; the portal publishes that figure under the name “utilisation”, which is why the two columns differ.
| Member | Allocated | Paid out | Committed | Never committed | To verify |
|---|---|---|---|---|---|
| C. Sadanandan Master Nominated Rajya Sabha · 55 works | ₹7.35 Cr | 0.0% | 62.1% | ₹2.78 Cr | 10 |
| V. Sivadasan Sitting Rajya Sabha · 63 works | ₹27.67 Cr | 9.0% | 69.0% | ₹8.57 Cr | 42 |
| Haris Beeran Sitting Rajya Sabha · 216 works | ₹12.25 Cr | 14.6% | 85.0% | ₹1.84 Cr | 90 |
| P. P. Suneer Sitting Rajya Sabha · 90 works | ₹12.25 Cr | 15.1% | 69.9% | ₹3.69 Cr | 27 |
| Jose K. Mani Sitting Rajya Sabha · 182 works | ₹12.25 Cr | 15.8% | 76.0% | ₹2.94 Cr | 86 |
| John Brittas Sitting Rajya Sabha · 144 works | ₹24.51 Cr | 23.5% | 87.6% | ₹3.04 Cr | 60 |
| Jebi Mather Hisham Sitting Rajya Sabha · 119 works | ₹22.06 Cr | 24.8% | 69.0% | ₹6.83 Cr | 67 |
| Sandosh Kumar P Sitting Rajya Sabha · 104 works | ₹22.06 Cr | 25.4% | 67.6% | ₹7.14 Cr | 45 |
| A. A. Rahim Sitting Rajya Sabha · 75 works | ₹22.06 Cr | 25.8% | 53.7% | ₹10.21 Cr | 24 |
| P. T. Usha Nominated Rajya Sabha · 121 works | ₹19.61 Cr | 28.2% | 70.7% | ₹5.74 Cr | 71 |
| Abdul Wahab Sitting Rajya Sabha · 368 works | ₹31.09 Cr | 30.2% | 88.3% | ₹3.63 Cr | 127 |
| Adv. A. M. Ariff ALAPPUZHA · 65 works | ₹9.81 Cr | 44.0% | 75.7% | ₹2.38 Cr | 17 |
| K Sudhakaran KANNUR · 139 works | ₹9.81 Cr | 58.5% | 72.4% | ₹2.70 Cr | 22 |
| K. Muraleedharan VADAKARA · 50 works | ₹9.81 Cr | 65.7% | 89.1% | ₹1.07 Cr | 10 |
| Benny Behanan CHALAKUDY · 69 works | ₹8.26 Cr | 66.9% | 96.5% | ₹28.86 L | 16 |
| Kodikunnil Suresh MAVELIKKARA · 95 works | ₹8.23 Cr | 70.4% | 95.9% | ₹33.49 L | 15 |
| M K Raghavan KOZHIKODE · 221 works | ₹9.81 Cr | 72.6% | 77.5% | ₹2.21 Cr | 6 |
| E T Mohammed Basheer PONNANI · 121 works | ₹9.97 Cr | 75.2% | 87.0% | ₹1.29 Cr | 7 |
| Anto Antony PATHANAMTHITTA · 166 works | ₹9.81 Cr | 76.2% | 87.8% | ₹1.20 Cr | 14 |
| N K Premachandran KOLLAM · 60 works | ₹4.99 Cr | 77.8% | 86.5% | ₹67.12 L | 5 |
| T.N. Prathapan THRISSUR · 91 works | ₹9.81 Cr | 78.0% | 82.2% | ₹1.75 Cr | 1 |
| V K Sreekandan PALAKKAD · 151 works | ₹8.60 Cr | 81.5% | 100.0% | ₹0 | 7 |
| Dean Kuriakose IDUKKI · 149 works | ₹9.81 Cr | 82.4% | 89.7% | ₹1.01 Cr | 7 |
| M P Abdussamad Samadani MALAPPURAM · 179 works | ₹9.77 Cr | 83.6% | 83.8% | ₹1.58 Cr | 1 |
| Thomas Chazhikadan KOTTAYAM · 194 works | ₹9.29 Cr | 83.9% | 94.0% | ₹56.15 L | 12 |
| Shashi Tharoor THIRUVANANTHAPURAM · 169 works | ₹9.81 Cr | 84.1% | 91.4% | ₹84.24 L | 16 |
| Hibi Eden ERNAKULAM · 40 works | ₹8.32 Cr | 84.1% | 97.4% | ₹21.29 L | 4 |
| Ramya Haridas ALATHUR · 419 works | ₹9.81 Cr | 87.3% | 87.8% | ₹1.20 Cr | 10 |
| Rahul Gandhi WAYANAD · 71 works | ₹9.81 Cr | 89.0% | 91.2% | ₹86.56 L | 3 |
| Adoor Prakash ATTINGAL · 300 works | ₹9.81 Cr | 92.9% | 95.8% | ₹41.31 L | 2 |
| Rajmohan Unnithan KASARAGOD · 286 works | ₹11.49 Cr | 97.4% | 98.0% | ₹22.75 L | 2 |
Sector is read from each work’s own description, because the portal’s category column says “Normal/Others” on almost every row.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 1,963 | ₹48.23 Cr | 203 |
| Roads & Paving | 1,395 | ₹106.35 Cr | 305 |
| Education | 542 | ₹88.53 Cr | 141 |
| Equipment & Vehicles | 153 | ₹6.51 Cr | 49 |
| Community Buildings | 153 | ₹23.58 Cr | 36 |
| Religious & Cultural | 108 | ₹5.87 Cr | 15 |
| Health | 103 | ₹21.70 Cr | 33 |
| Sports | 54 | ₹10.31 Cr | 19 |
| Water | 47 | ₹4.20 Cr | 17 |
| Boundary & Protection | 19 | ₹2.60 Cr | 5 |
Patterns across a whole agency or member, not a judgement on any one work — which is why none of these change a work’s score.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
The ten works least like their peers. A score is a reason to look, never a finding of wrongdoing.
| Work | District | Agency | Sanctioned | Score | Band |
|---|---|---|---|---|---|
| Installation of Solar High Mast LIght at Pookattupadi Juncti ₹449,000 against a ₹200,000 median for Street Lighting works in ERNAKULAM (124% above, 343 peer works) | ERNAKULAM | ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) | ₹4.49 L | 75.0 | HIGH |
| Construction Mutholapuram Pulingunnumala- Vettiyodi Drinking ₹2,500,000 against a ₹1,000,000 median for Water works in ERNAKULAM (150% above, 9 peer works) | ERNAKULAM | ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) | ₹25.00 L | 75.0 | HIGH |
| Construction of Artificial Football turf, Municipal Stadium ₹15,380,000 against a ₹2,291,551 median for Sports works in ERNAKULAM (571% above, 23 peer works) | ERNAKULAM | ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) | ₹1.54 Cr | 75.0 | HIGH |
| Construction of Mattakadu XIME College road or pathway, ward ₹1,500,000 against a ₹500,000 median for Roads & Paving works in ERNAKULAM (200% above, 192 peer works) | ERNAKULAM | ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) | ₹15.00 L | 74.8 | HIGH |
| Construction of School Building - Poovarany Kochukottaram LP ₹1,850,000 against a ₹500,000 median for Education works in KOTTAYAM (270% above, 148 peer works) | KOTTAYAM | KOTTAYAM(DISTRICT COLLECTOR KOTTAYAM_IDA) | ₹18.50 L | 74.7 | HIGH |
| Installation of Solar High Mast Light at Kottayam- Karappuzh ₹450,000 against a ₹200,000 median for Street Lighting works in KOTTAYAM (125% above, 331 peer works) | KOTTAYAM | KOTTAYAM(DISTRICT COLLECTOR KOTTAYAM_IDA) | ₹4.50 L | 74.7 | HIGH |
| Purchasing of School bus for M.M.M.U.M.UP School, Karakkad, ₹2,500,000 against a ₹500,000 median for Education works in KOTTAYAM (400% above, 148 peer works) | KOTTAYAM | KOTTAYAM(DISTRICT COLLECTOR KOTTAYAM_IDA) | ₹25.00 L | 74.7 | HIGH |
| Installation of Street main at Neeralakkode –Thoppil area
KS ₹620,000 against a ₹200,000 median for Street Lighting works in KOTTAYAM (210% above, 331 peer works) | KOTTAYAM | KOTTAYAM(DISTRICT COLLECTOR KOTTAYAM_IDA) | ₹6.20 L | 74.7 | HIGH |
| Construction of Vakkethara – Chettikkary Colony Road
(Cat: S ₹1,000,000 against a ₹500,000 median for Roads & Paving works in KOTTAYAM (100% above, 394 peer works) | KOTTAYAM | KOTTAYAM(DISTRICT COLLECTOR KOTTAYAM_IDA) | ₹10.00 L | 74.7 | HIGH |
| Construction of Cultural Centre at Laksham Veedu Colony Cat ₹1,850,000 against a ₹350,000 median for Religious & Cultural works in KOTTAYAM (429% above, 11 peer works) | KOTTAYAM | KOTTAYAM(DISTRICT COLLECTOR KOTTAYAM_IDA) | ₹18.50 L | 74.7 | HIGH |