152 works across 1 implementing agency, recommended by 10 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) 1 high risk | 152 | 102 | ₹12.12 Cr | 26 | 23.4 | Bharanikkavu Labour Contract Society 6% of spend · 74 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| N K Premachandran KOLLAM | 60 | ₹4.28 Cr | 5 |
| Kodikunnil Suresh MAVELIKKARA | 38 | ₹3.22 Cr | 5 |
| Adv. A. M. Ariff ALAPPUZHA | 15 | ₹1.55 Cr | 4 |
| Abdul Wahab Sitting Rajya Sabha | 13 | ₹41.62 L | 3 |
| Haris Beeran Sitting Rajya Sabha | 11 | ₹48.45 L | 0 |
| Sandosh Kumar P Sitting Rajya Sabha | 5 | ₹86.78 L | 2 |
| P. P. Suneer Sitting Rajya Sabha | 4 | ₹83.50 L | 4 |
| Jose K. Mani Sitting Rajya Sabha | 3 | ₹6.00 L | 1 |
| P. T. Usha Nominated Rajya Sabha | 2 | ₹30.00 L | 2 |
| Jebi Mather Hisham Sitting Rajya Sabha | 1 | ₹10.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 60 | ₹5.02 Cr | 5 |
| Street Lighting | 38 | ₹1.12 Cr | 6 |
| Education | 27 | ₹3.57 Cr | 10 |
| Equipment & Vehicles | 6 | ₹21.84 L | 0 |
| Community Buildings | 6 | ₹67.63 L | 3 |
| Religious & Cultural | 5 | ₹34.46 L | 0 |
| Drainage & Sanitation | 4 | ₹24.94 L | 0 |
| Boundary & Protection | 2 | ₹7.63 L | 0 |
| Health | 2 | ₹72.41 L | 1 |
| Sports | 1 | ₹9.16 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| CONSTRUCTION OF SULTHANSHA GRANDHASAA BUILDING ₹2,500,000 against a ₹521,500 median for Community Buildings works in KOLLAM (379% above, 14 peer works) | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹25.00 L | 177 d | +379% | 72.5 | HIGH |
| Installation of Solar HighMast Light near Gandhi Bhavan ,War ₹450,000 against a ₹250,000 median for Street Lighting works in KOLLAM (80% above, 139 peer works) | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹4.50 L | 249 d | +80% | 67.9 | MEDIUM |
| CONSTRUCTION O FLIBRARY BIULDING ₹2,100,000 against a ₹1,383,320 median for Education works in KOLLAM (52% above, 83 peer works) | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹21.00 L | 171 d | +52% | 60.5 | MEDIUM |
| Construction of Kulatharaman Foot bridge, Ward No. 20, Pirav 183 days beyond expected completion | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹7.00 L | 183 d | +17% | 56.3 | MEDIUM |
| Solar Mini Mast Light Installation at Junction infront of Ka 249 days beyond expected completion | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹3.00 L | 249 d | +20% | 55.5 | MEDIUM |
| Setting up of mini mast light at Kunnoothara Mukku, Ward no. 212 days beyond expected completion | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹2.96 L | 212 d | +18% | 54.8 | MEDIUM |
| Setting up of Mini Mast light at Chekkanazhak junction, Ward 183 days beyond expected completion | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹3.00 L | 183 d | +20% | 54.3 | MEDIUM |
| Construction of Kalathivila -Kanjirakuttivila Canal Road con ₹1,000,000 against a ₹600,000 median for Roads & Paving works in KOLLAM (67% above, 197 peer works) | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹10.00 L | 99 d | +67% | 53.3 | MEDIUM |
| Concreting of Kaithapuzha Bridge Pathinambara Colony Road at ₹2,000,000 against a ₹600,000 median for Roads & Paving works in KOLLAM (233% above, 197 peer works) | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹20.00 L | 544 d | +233% | 52.9 | MEDIUM |
| Self supported tressless roofing to Open Air Auditorium to ₹1,500,000 against a ₹521,500 median for Community Buildings works in KOLLAM (188% above, 14 peer works) | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹15.00 L | 545 d | +188% | 52.9 | MEDIUM |
| Construction of Building for C R Madhu Sabdika Grandhasala, ₹1,500,000 against a ₹521,500 median for Community Buildings works in KOLLAM (188% above, 14 peer works) | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹15.00 L | 546 d | +188% | 52.9 | MEDIUM |
| New Building Construction for new class rooms of Mukhathala ₹5,000,000 against a ₹1,383,320 median for Education works in KOLLAM (261% above, 83 peer works) | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹50.00 L | — | +261% | 47.9 | MEDIUM |
| Installation of Minimast light (motorized) at Manjappara Pav ₹450,000 against a ₹250,000 median for Street Lighting works in KOLLAM (80% above, 139 peer works) | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹4.50 L | 544 d | +80% | 47.9 | MEDIUM |
| Construction of Sub-Centre for PHC in Thodiyoor Gram Panchay Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹40.00 L | 546 d | 0% | 47.3 | MEDIUM |
| Construction of Building for Anganwadi No. 3 in Gandhinagar Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) | Recommended | ₹15.00 L | 940 d | +8% | 46.6 | MEDIUM |