| 1 | Construction of Paver Block road with GSB subgrade from Tors Roads & Paving — Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) - ₹8,245,381 against a ₹2,302,669 median for Roads & Paving works in COOCH BEHAR (258% above, 32 peer works)
- 188 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| COOCH BEHAR | ₹82.45 L | HIGH 77
cost 25delay 25duplication 20 | |
| 2 | Construction of Paver Block road with GSB subgrade from A Roads & Paving — Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) - ₹6,496,211 against a ₹2,302,669 median for Roads & Paving works in COOCH BEHAR (182% above, 32 peer works)
- 311 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| COOCH BEHAR | ₹64.96 L | HIGH 77
cost 25delay 25duplication 20 | |
| 3 | Construction of Paver Block road with GSB subgrade from Nat Roads & Paving — Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) - ₹8,617,886 against a ₹2,302,669 median for Roads & Paving works in COOCH BEHAR (274% above, 32 peer works)
- 311 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| COOCH BEHAR | ₹86.18 L | HIGH 77
cost 25delay 25duplication 20 | |
| 4 | 1 Installation of Solar Street Light 57 Nos at road site of Street Lighting — Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) - ₹2,843,160 against a ₹586,716 median for Street Lighting works in COOCH BEHAR (385% above, 155 peer works)
- 345 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| COOCH BEHAR | ₹28.43 L | HIGH 77
cost 25delay 25duplication 20 | |
| 5 | Installation of 9 no Mini High Mast Solar Street Light Syste Street Lighting — Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) - ₹5,280,444 against a ₹586,716 median for Street Lighting works in COOCH BEHAR (800% above, 155 peer works)
- 345 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| COOCH BEHAR | ₹52.80 L | HIGH 77
cost 25delay 25duplication 20 | |
| 6 | Construction of Paver Block road with GSB subgrade from Tors Roads & Paving — Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) - ₹8,245,381 against a ₹2,302,669 median for Roads & Paving works in COOCH BEHAR (258% above, 32 peer works)
- 188 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| COOCH BEHAR | ₹82.45 L | HIGH 77
cost 25delay 25duplication 20 | |
| 7 | Construction of Paver Block road with GSB subgrade from A Roads & Paving — Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) - ₹6,496,211 against a ₹2,302,669 median for Roads & Paving works in COOCH BEHAR (182% above, 32 peer works)
- 311 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| COOCH BEHAR | ₹64.96 L | HIGH 77
cost 25delay 25duplication 20 | |
| 8 | Construction of Paver Block road with GSB subgrade from Nat Roads & Paving — Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) - ₹8,617,886 against a ₹2,302,669 median for Roads & Paving works in COOCH BEHAR (274% above, 32 peer works)
- 311 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| COOCH BEHAR | ₹86.18 L | HIGH 77
cost 25delay 25duplication 20 | |
| 9 | 1 Installation of Solar Street Light 57 Nos at road site of Street Lighting — Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) - ₹2,843,160 against a ₹586,716 median for Street Lighting works in COOCH BEHAR (385% above, 155 peer works)
- 345 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| COOCH BEHAR | ₹28.43 L | HIGH 77
cost 25delay 25duplication 20 | |
| 10 | Installation of 9 no Mini High Mast Solar Street Light Syste Street Lighting — Cooch Behar(DISTRICT MAGISTRATE COOCHBEHAR_IDA) - ₹5,280,444 against a ₹586,716 median for Street Lighting works in COOCH BEHAR (800% above, 155 peer works)
- 345 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 48% delay rate across its projects
| COOCH BEHAR | ₹52.80 L | HIGH 77
cost 25delay 25duplication 20 | |
| 11 | Construction of P.C.C Open Mancha infront of Manikora Maa Ka Religious & Cultural — Malda(DISTRICT MAGISTRATE MALDA_IDA) - ₹823,000 against a ₹400,000 median for Religious & Cultural works in MALDA (106% above, 33 peer works)
- 578 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹8.23 L | HIGH 76
cost 25delay 25duplication 19 | |
| 12 | Construction of P.C.C Open Mancha infront of Manikora Maa Ka Religious & Cultural — Malda(DISTRICT MAGISTRATE MALDA_IDA) - ₹823,000 against a ₹400,000 median for Religious & Cultural works in MALDA (106% above, 33 peer works)
- 578 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹8.23 L | HIGH 76
cost 25delay 25duplication 19 | |
| 13 | Installation of Electric high mast light in front of bakha Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - ₹500,000 against a ₹200,000 median for Street Lighting works in MALDA (150% above, 436 peer works)
- 566 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 19 | |
| 14 | Installation of Electric high mast light in front of bakha Street Lighting — Malda(DISTRICT MAGISTRATE MALDA_IDA) - ₹500,000 against a ₹200,000 median for Street Lighting works in MALDA (150% above, 436 peer works)
- 566 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| MALDA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 19 | |
| 15 | CONSTRUCTION OF SCHOOL BUILDING OF ANJUMAN GIRLS PRIMARY SCH Education — KOLKATA(COMMISSIONER KOLKATA MUNICIPAL CORPORATION_IDA) - ₹2,500,000 against a ₹1,000,000 median for Education works in KOLKATA (150% above, 35 peer works)
- 250 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLKATA | ₹25.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 16 | DEVELOPMENT OF THE BHAWANIPUR GUJRATI EDUCATION SOCIETY. 5 L Education — KOLKATA(COMMISSIONER KOLKATA MUNICIPAL CORPORATION_IDA) - ₹5,000,000 against a ₹1,000,000 median for Education works in KOLKATA (400% above, 35 peer works)
- 258 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLKATA | ₹50.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 17 | CONSTRUCTION OF SCHOOL BUILDING OF ANJUMAN GIRLS PRIMARY SCH Education — KOLKATA(COMMISSIONER KOLKATA MUNICIPAL CORPORATION_IDA) - ₹2,500,000 against a ₹1,000,000 median for Education works in KOLKATA (150% above, 35 peer works)
- 250 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLKATA | ₹25.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 18 | DEVELOPMENT OF THE BHAWANIPUR GUJRATI EDUCATION SOCIETY. 5 L Education — KOLKATA(COMMISSIONER KOLKATA MUNICIPAL CORPORATION_IDA) - ₹5,000,000 against a ₹1,000,000 median for Education works in KOLKATA (400% above, 35 peer works)
- 258 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KOLKATA | ₹50.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 19 | Provision of an ambulance with advanced life support system( Roads & Paving — North 24 Parganas(DISTRICT MAGISTRATE NORTH TWENTY FOUR PARGANAS_IDA) - ₹3,075,000 against a ₹700,000 median for Roads & Paving works in NORTH 24 PARGANAS (339% above, 148 peer works)
- 236 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| NORTH 24 PARGANAS | ₹30.75 L | HIGH 75
cost 25delay 25duplication 20 | |
| 20 | Highmast light Street Lighting — North 24 Parganas(DISTRICT MAGISTRATE NORTH TWENTY FOUR PARGANAS_IDA) - ₹1,800,000 against a ₹840,000 median for Street Lighting works in NORTH 24 PARGANAS (114% above, 109 peer works)
- 827 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| NORTH 24 PARGANAS | ₹18.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 21 | Provision of an ambulance with advanced life support system( Roads & Paving — North 24 Parganas(DISTRICT MAGISTRATE NORTH TWENTY FOUR PARGANAS_IDA) - ₹3,075,000 against a ₹700,000 median for Roads & Paving works in NORTH 24 PARGANAS (339% above, 148 peer works)
- 236 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| NORTH 24 PARGANAS | ₹30.75 L | HIGH 75
cost 25delay 25duplication 20 | |
| 22 | Construction for Canteen at Ground Floor and modification of Community Buildings — North 24 Parganas(DISTRICT MAGISTRATE NORTH TWENTY FOUR PARGANAS_IDA) - ₹6,763,570 against a ₹2,000,000 median for Community Buildings works in NORTH 24 PARGANAS (238% above, 38 peer works)
- 177 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| NORTH 24 PARGANAS | ₹67.64 L | HIGH 75
cost 25delay 25duplication 20 | |
| 23 | Construction for Canteen at Ground Floor and modification of Community Buildings — North 24 Parganas(DISTRICT MAGISTRATE NORTH TWENTY FOUR PARGANAS_IDA) - ₹6,763,570 against a ₹2,000,000 median for Community Buildings works in NORTH 24 PARGANAS (238% above, 38 peer works)
- 177 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| NORTH 24 PARGANAS | ₹67.64 L | HIGH 75
cost 25delay 25duplication 20 | |
| 24 | Construction of New Community Hall Community Buildings — PASCHIM BARDHAMAN(DISTRICT MAGISTRATE PASCHIM BARDHAMAN_IDA) - ₹4,000,000 against a ₹1,299,985 median for Community Buildings works in PASCHIM BARDHAMAN (208% above, 26 peer works)
- 638 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PASCHIM BARDHAMAN | ₹40.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 25 | Installation of Ten (10) nos. Tube Well for Drinking water i Water — BANKURA(DISTRICT MAGISTRATE BANKURA_IDA) - ₹1,000,000 against a ₹500,000 median for Water works in BANKURA (100% above, 71 peer works)
- 600 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BANKURA | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |