CONSTRUCTION OF SCHOOL BUILDING OF ANJUMAN GIRLS PRIMARY SCH

Education

West Bengal / KOLKATA — KOLKATA(COMMISSIONER KOLKATA MUNICIPAL CORPORATION_IDA) · Mohammed Nadimul Haque (Sitting Rajya Sabha)

CONSTRUCTION OF SCHOOL BUILDING OF ANJUMAN GIRLS PRIMARY SCHOOL OF 35 Mofidul Islam Lane KOLKATA 700014 WARD 54 BR VI

Overall risk score
75/100
Blended from the five components below, each weighted as shown.
HIGH

Risk components

Cost100
Delay100
Duplication100
Agency35
Compliance0
Sanctioned
₹25.00 L
Delay
250d
Cost deviation
150%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹2,500,000 against a ₹1,000,000 median for Education works in KOLKATA (150% above, 35 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 250 days beyond expected completionPublished dates
  • 100% similarity with another nearby workAI · Sentence-BERT embeddings (all-MiniLM-L6-v2)

Decision trail

Nobody has recorded a decision on this work yet.

Reads as a near-duplicate of work #52233 (sentence-embedding similarity 1.00, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)