| 1 | Const. of Single Storey RCC Library Building at Ramkrishna M Roads & Paving — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - ₹4,500,000 against a ₹1,417,827 median for Roads & Paving works in WEST TRIPURA (217% above, 23 peer works)
- 301 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| WEST TRIPURA | ₹45.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 2 | Supply & Installation of Swing & Slide Sports — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 833 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| DHALAI | ₹75.00 L | HIGH 74
delay 25cost 23duplication 20 | |
| 3 | Const. of Single Storey RCC Library Building at Ramkrishna M Roads & Paving — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - ₹4,500,000 against a ₹1,417,827 median for Roads & Paving works in WEST TRIPURA (217% above, 23 peer works)
- 301 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| WEST TRIPURA | ₹45.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 4 | Open Gym Sports — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - ₹1,800,000 against a ₹1,142,945 median for Sports works in WEST TRIPURA (57% above, 16 peer works)
- 703 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| WEST TRIPURA | ₹18.00 L | MEDIUM 66
delay 25duplication 20cost 17 | |
| 5 | Construction of new School Building at Sabroom English Mediu Education — South Tripura(DISTRICT MAGISTRATE and COLLECTOR SOUTH TRIPURA DISTRICT_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 203 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH TRIPURA | ₹25.00 L | MEDIUM 65
delay 25duplication 20cost 15 | |
| 6 | Construction of new School Building at Sabroom English Mediu Education — South Tripura(DISTRICT MAGISTRATE and COLLECTOR SOUTH TRIPURA DISTRICT_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 203 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH TRIPURA | ₹25.00 L | MEDIUM 65
delay 25duplication 20cost 15 | |
| 7 | Construction of single Class Room with staircase at Sishu Ti Education — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 301 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| WEST TRIPURA | ₹22.00 L | MEDIUM 64
delay 25duplication 20cost 15 | |
| 8 | 01 No.-Open Gymnasium (12 Equipment ) including base and sh Community Buildings — Gomati(DM OFFICE GOMATI MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 558 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| GOMATI | ₹9.42 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 9 | 01 No.-Open Gymnasium (12 Equipment ) including base and sh Community Buildings — Gomati(DM OFFICE GOMATI MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 558 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| GOMATI | ₹9.42 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 10 | 1No - Open Gym (12 Equipment) { Air Bike, Air Walker, Arm Wh Community Buildings — Gomati(DM OFFICE GOMATI MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 618 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| GOMATI | ₹9.42 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 11 | 1No - Open Gym (12 Equipment) { Air Bike, Air Walker, Arm Wh Community Buildings — Gomati(DM OFFICE GOMATI MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 618 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| GOMATI | ₹9.42 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 12 | Construction of single Class Room with staircase at Sishu Ti Education — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 301 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| WEST TRIPURA | ₹22.00 L | MEDIUM 62
delay 25duplication 20cost 15 | |
| 13 | Construction of Community Cultural Hall at Yogi Vishav Kalya Community Buildings — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - ₹2,000,000 against a ₹1,000,000 median for Community Buildings works in WEST TRIPURA (100% above, 32 peer works)
- 100% similarity with another nearby work
| WEST TRIPURA | ₹20.00 L | MEDIUM 59
cost 25duplication 20delay 10 | |
| 14 | Additional fund for providing one Mahindra Bolero Pioneer Yo Equipment & Vehicles — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - 203 days beyond expected completion
- 100% similarity with another nearby work
| WEST TRIPURA | ₹48,500 | MEDIUM 58
delay 25duplication 20cost 9 | |
| 15 | Beautification of Officetilla New Market Pond Water — Sepahijala(DISTRICT MAGISTRATE and COLLECTOR SIPAHIJALA_IDA) - ₹2,000,000 against a ₹390,000 median for Water works in SEPAHIJALA (413% above, 21 peer works)
- 703 days beyond expected completion
Read more (1 more)Show less- 54% of this agency's ₹29,518,467 spend went to one vendor (A TO Z TRADING COMPANY), across 9 vendors and 51 transactions
| SEPAHIJALA | ₹20.00 L | MEDIUM 57 | |
| 16 | Construction of Community Cultural Hall at Yogi Vishav Kalya Community Buildings — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - ₹2,000,000 against a ₹1,000,000 median for Community Buildings works in WEST TRIPURA (100% above, 32 peer works)
- 100% similarity with another nearby work
| WEST TRIPURA | ₹20.00 L | MEDIUM 57
cost 25duplication 20delay 10 | |
| 17 | Construction of Bus stop Community Buildings — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - 556 days beyond expected completion
- 100% similarity with another nearby work
| WEST TRIPURA | ₹3.03 L | MEDIUM 56
delay 25duplication 20cost 7 | |
| 18 | Construction of Bus stop Community Buildings — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - 556 days beyond expected completion
- 100% similarity with another nearby work
| WEST TRIPURA | ₹3.03 L | MEDIUM 56
delay 25duplication 20cost 7 | |
| 19 | Construction of toilet block in the school premises of Kshud Roads & Paving — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - 202 days beyond expected completion
- 100% similarity with another nearby work
| WEST TRIPURA | ₹1.50 L | MEDIUM 56
delay 25duplication 20cost 7 | |
| 20 | Additional fund for providing one Mahindra Bolero Pioneer Yo Equipment & Vehicles — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - 203 days beyond expected completion
- 100% similarity with another nearby work
| WEST TRIPURA | ₹48,500 | MEDIUM 56
delay 25duplication 20cost 9 | |
| 21 | Supply & Installation of Stainless Steel Water Tank- G304 wi Water — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 833 days beyond expected completion
| DHALAI | ₹1.05 Cr | MEDIUM 55 | |
| 22 | Construction of toilet block in the school premises of Kshud Roads & Paving — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - 202 days beyond expected completion
- 100% similarity with another nearby work
| WEST TRIPURA | ₹1.50 L | MEDIUM 54
delay 25duplication 20cost 7 | |
| 23 | Construction of Shed near Mehar Kali Bari Community Buildings — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - ₹5,000,000 against a ₹1,000,000 median for Community Buildings works in WEST TRIPURA (400% above, 32 peer works)
- 558 days beyond expected completion
| WEST TRIPURA | ₹50.00 L | MEDIUM 54 | |
| 24 | Construction of common work sheds/ common covered sitting ar Community Buildings — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - ₹3,000,000 against a ₹1,000,000 median for Community Buildings works in WEST TRIPURA (200% above, 32 peer works)
- 608 days beyond expected completion
| WEST TRIPURA | ₹30.00 L | MEDIUM 54 | |
| 25 | Development of community water harvesting pond, Routhkalla G Water — Sepahijala(DISTRICT MAGISTRATE and COLLECTOR SIPAHIJALA_IDA) - ₹3,500,000 against a ₹390,000 median for Water works in SEPAHIJALA (797% above, 21 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 54% of this agency's ₹29,518,467 spend went to one vendor (A TO Z TRADING COMPANY), across 9 vendors and 51 transactions
| SEPAHIJALA | ₹35.00 L | MEDIUM 52
cost 25duplication 20agency 7 | |