73 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) 1 high risk | 73 | 23 | ₹13.60 Cr | 17 | 30.0 | Mousumi Banik 15% of spend · 29 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Rajib Bhattacharjee Sitting Rajya Sabha | 47 | ₹6.46 Cr | 13 |
| Biplab Kumar Deb TRIPURA WEST | 26 | ₹7.14 Cr | 4 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 17 | ₹3.14 Cr | 3 |
| Roads & Paving | 15 | ₹2.76 Cr | 4 |
| Health | 13 | ₹1.80 Cr | 0 |
| Community Buildings | 9 | ₹3.06 Cr | 4 |
| Sports | 8 | ₹1.24 Cr | 1 |
| Equipment & Vehicles | 4 | ₹9.98 L | 3 |
| Religious & Cultural | 4 | ₹94.67 L | 0 |
| Drainage & Sanitation | 2 | ₹47.00 L | 1 |
| Water | 1 | ₹9.00 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Const. of Single Storey RCC Library Building at Ramkrishna M ₹4,500,000 against a ₹1,417,827 median for Roads & Paving works in WEST TRIPURA (217% above, 23 peer works) | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Recommended | ₹45.00 L | 301 d | +217% | 71.7 | HIGH |
| Construction of single Class Room with staircase at Sishu Ti Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Recommended | ₹22.00 L | 301 d | +15% | 62.0 | MEDIUM |
| Construction of Community Cultural Hall at Yogi Vishav Kalya ₹2,000,000 against a ₹1,000,000 median for Community Buildings works in WEST TRIPURA (100% above, 32 peer works) | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Recommended | ₹20.00 L | 72 d | +100% | 56.7 | MEDIUM |
| Additional fund for providing one Mahindra Bolero Pioneer Yo 203 days beyond expected completion | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Recommended | ₹48,500 | 203 d | -76% | 56.0 | MEDIUM |
| Construction of toilet block in the school premises of Kshud 202 days beyond expected completion | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Recommended | ₹1.50 L | 202 d | -89% | 54.1 | MEDIUM |
| Construction of community guest house at Sri Sri Santikali S ₹6,683,300 against a ₹1,000,000 median for Community Buildings works in WEST TRIPURA (568% above, 32 peer works) | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Recommended | ₹66.83 L | 184 d | +568% | 51.7 | MEDIUM |
| Construction of Community Hall at Chandrapur near Tata Kalib ₹3,348,643 against a ₹1,417,827 median for Roads & Paving works in WEST TRIPURA (136% above, 23 peer works) | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Recommended | ₹33.49 L | 198 d | +136% | 51.7 | MEDIUM |
| Construction of RCC road beside Pragati School, Ward No.18, ₹4,602,150 against a ₹1,417,827 median for Roads & Paving works in WEST TRIPURA (225% above, 23 peer works) | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Recommended | ₹46.02 L | 246 d | +225% | 51.7 | MEDIUM |
| Construction of RCC Double storied Art Gallery cum Library B ₹5,000,000 against a ₹1,913,500 median for Education works in WEST TRIPURA (161% above, 30 peer works) | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Recommended | ₹50.00 L | — | +161% | 46.7 | MEDIUM |
| Construction of RCC Drain in the west lane of Gedumia Masjid ₹3,500,000 against a ₹1,127,450 median for Drainage & Sanitation works in WEST TRIPURA (210% above, 9 peer works) | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Recommended | ₹35.00 L | — | +210% | 46.7 | MEDIUM |
| Community hall near the house of Samar Chakraborty, Jagahari ₹2,000,000 against a ₹1,000,000 median for Community Buildings works in WEST TRIPURA (100% above, 32 peer works) | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Recommended | ₹20.00 L | — | +100% | 46.7 | MEDIUM |
| Water fountain and electrification work at Rabindra Kanan Am ₹900,000 against a ₹390,000 median for Water works in WEST TRIPURA (131% above, 38 peer works) | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Recommended | ₹9.00 L | — | +131% | 46.7 | MEDIUM |
| Providing of Hand Roller and Grass Cutter machine for the cr ₹499,050 against a ₹205,000 median for Equipment & Vehicles works in WEST TRIPURA (143% above, 59 peer works) | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Completed | ₹4.99 L | — | +143% | 46.7 | MEDIUM |
| Installation of CCTV surveillance system at Netaji Subhash V ₹430,000 against a ₹205,000 median for Equipment & Vehicles works in WEST TRIPURA (110% above, 59 peer works) | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Completed | ₹4.30 L | — | +110% | 46.7 | MEDIUM |
| Construction of Boundary Wall and Gates of MGM Class XII Sch Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) | Recommended | ₹25.00 L | 72 d | +31% | 45.7 | MEDIUM |