| 1 | Electric Bus 14-Seater LeadAcid
14-Seater Sightseeing Electr Equipment & Vehicles — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - ₹1,400,000 against a ₹499,000 median for Equipment & Vehicles works in HYDERABAD (181% above, 18 peer works)
- 308 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 61% of this agency's ₹55,429,086 spend went to one vendor (SANTRIX CONSTRUCTIONS), across 8 vendors and 45 transactions
| HYDERABAD | ₹14.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 2 | Construction of Extra Floor on Existing Community Hall at So Community Buildings — ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in ADILABAD (100% above, 112 peer works)
- 325 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 54% delay rate across its projects
| ADILABAD | ₹10.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 3 | Construction of Extra Floor on Existing Community Hall at So Community Buildings — ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in ADILABAD (100% above, 112 peer works)
- 325 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 54% delay rate across its projects
| ADILABAD | ₹10.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 4 | C/o Comm Hall at Rajaka Colony near water plant at Thimmalak Water — RAJANNA SIRCILLA(DISTRICT COLLECTOR RAJANNA SIRCILLA_IDA) - ₹500,000 against a ₹200,000 median for Water works in RAJANNA SIRCILLA (150% above, 116 peer works)
- 323 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| RAJANNA SIRCILLA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 5 | C/o Comm Hall Hall at Mandala Reddy Colony beside Kummari Sa Community Buildings — RAJANNA SIRCILLA(DISTRICT COLLECTOR RAJANNA SIRCILLA_IDA) - ₹1,000,000 against a ₹485,106 median for Community Buildings works in RAJANNA SIRCILLA (106% above, 129 peer works)
- 323 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| RAJANNA SIRCILLA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 6 | C/o Comm Hall at Rajaka Colony near water plant at Thimmalak Water — RAJANNA SIRCILLA(DISTRICT COLLECTOR RAJANNA SIRCILLA_IDA) - ₹500,000 against a ₹200,000 median for Water works in RAJANNA SIRCILLA (150% above, 116 peer works)
- 323 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| RAJANNA SIRCILLA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 7 | C/o Comm Hall Hall at Mandala Reddy Colony beside Kummari Sa Community Buildings — RAJANNA SIRCILLA(DISTRICT COLLECTOR RAJANNA SIRCILLA_IDA) - ₹1,000,000 against a ₹485,106 median for Community Buildings works in RAJANNA SIRCILLA (106% above, 129 peer works)
- 323 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| RAJANNA SIRCILLA | ₹10.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 8 | Construction of community Hall at Arpanpally Village, Kesamu Community Buildings — MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) - ₹2,000,000 against a ₹499,000 median for Community Buildings works in MAHABUBABAD (301% above, 28 peer works)
- 370 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MAHABUBABAD | ₹20.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 9 | Construction of community Hall at Arpanpally Village, Kesamu Community Buildings — MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) - ₹2,000,000 against a ₹499,000 median for Community Buildings works in MAHABUBABAD (301% above, 28 peer works)
- 370 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MAHABUBABAD | ₹20.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 10 | C/o cultural building at Huzurabad club, Huzurabad Religious & Cultural — KARIMNAGAR(DISTRICT COLLECTOR KARIMNAGAR_IDA) - ₹3,500,000 against a ₹293,629 median for Religious & Cultural works in KARIMNAGAR (1092% above, 8 peer works)
- 561 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KARIMNAGAR | ₹35.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 11 | C/o cultural building at Huzurabad club, Huzurabad Religious & Cultural — KARIMNAGAR(DISTRICT COLLECTOR KARIMNAGAR_IDA) - ₹3,500,000 against a ₹293,629 median for Religious & Cultural works in KARIMNAGAR (1092% above, 8 peer works)
- 561 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| KARIMNAGAR | ₹35.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 12 | Electric Bus 14-Seater LeadAcid
14-Seater Sightseeing Electr Equipment & Vehicles — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - ₹1,400,000 against a ₹499,000 median for Equipment & Vehicles works in HYDERABAD (181% above, 18 peer works)
- 308 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HYDERABAD | ₹14.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 13 | Upgrading training facilities and equipment, Developing Mode Equipment & Vehicles — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - ₹1,500,000 against a ₹499,000 median for Equipment & Vehicles works in HYDERABAD (201% above, 18 peer works)
- 142 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 61% of this agency's ₹55,429,086 spend went to one vendor (SANTRIX CONSTRUCTIONS), across 8 vendors and 45 transactions
| HYDERABAD | ₹15.00 L | HIGH 74
cost 25duplication 20delay 20 | |
| 14 | Construction of Compound wall to ZPHS School in Chilvakodur Education — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹2,500,000 against a ₹500,000 median for Education works in JAGITIAL (400% above, 28 peer works)
- 303 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹25.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 15 | Construction of Community Hall at Korutla Town of Jagtial Di Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹5,000,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (1567% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹50.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 16 | C/o Library Hall at Buggaram (v) in Jagtial Dist Education — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹2,500,000 against a ₹500,000 median for Education works in JAGITIAL (400% above, 28 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹25.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 17 | C/o Culvert at Muddapally (v) Pegadapally (m) in Jagtial Dis Roads & Paving — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹1,000,000 against a ₹499,992 median for Roads & Paving works in JAGITIAL (100% above, 117 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 18 | Balance work of Amaraveerula Sthupam and Park, jagitial town Sports — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹1,000,000 against a ₹495,725 median for Sports works in JAGITIAL (102% above, 16 peer works)
- 561 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 19 | Construction of Compound wall to ZPHS School in Chilvakodur Education — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹2,500,000 against a ₹500,000 median for Education works in JAGITIAL (400% above, 28 peer works)
- 303 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹25.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 20 | Construction of Community Hall at Korutla Town of Jagtial Di Community Buildings — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹5,000,000 against a ₹300,000 median for Community Buildings works in JAGITIAL (1567% above, 276 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹50.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 21 | C/o Library Hall at Buggaram (v) in Jagtial Dist Education — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹2,500,000 against a ₹500,000 median for Education works in JAGITIAL (400% above, 28 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹25.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 22 | C/o Culvert at Muddapally (v) Pegadapally (m) in Jagtial Dis Roads & Paving — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹1,000,000 against a ₹499,992 median for Roads & Paving works in JAGITIAL (100% above, 117 peer works)
- 429 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 23 | Balance work of Amaraveerula Sthupam and Park, jagitial town Sports — Jagitial(DISTRICT COLLECTOR JAGTIAL_IDA) - ₹1,000,000 against a ₹495,725 median for Sports works in JAGITIAL (102% above, 16 peer works)
- 561 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JAGITIAL | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 24 | Laying of CC Road Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹500,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (300% above, 298 peer works)
- 548 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| VIKARABAD | ₹5.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 25 | Laying of CC Road Roads & Paving — VIKARABAD(DISTRICT COLLECTOR VIKARABAD_2) - ₹720,000 against a ₹125,000 median for Roads & Paving works in VIKARABAD (476% above, 298 peer works)
- 548 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| VIKARABAD | ₹7.20 L | HIGH 73
cost 25delay 25duplication 20 | |