206 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) 1 high risk | 206 | 70 | ₹8.72 Cr | 50 | 27.3 | BHOJYA GUGULOTH 13% of spend · 36 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Balram Naik Porika MAHABUBABAD | 130 | ₹4.72 Cr | 15 |
| Ravi Chandra Vaddiraju Sitting Rajya Sabha | 68 | ₹3.55 Cr | 34 |
| Kadiyam Kavya WARANGEL | 5 | ₹15.90 L | 0 |
| Renuka Chowdhury Sitting Rajya Sabha | 2 | ₹10.00 L | 0 |
| Anil Kumar Yadav Mandadi Sitting Rajya Sabha | 1 | ₹20.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 97 | ₹4.95 Cr | 23 |
| Street Lighting | 75 | ₹1.61 Cr | 13 |
| Community Buildings | 12 | ₹84.90 L | 7 |
| Water | 9 | ₹27.51 L | 1 |
| Education | 3 | ₹59.98 L | 3 |
| Other | 3 | ₹12.14 L | 1 |
| Sports | 2 | ₹9.97 L | 2 |
| Drainage & Sanitation | 2 | ₹9.97 L | 0 |
| Health | 1 | ₹4.99 L | 0 |
| Equipment & Vehicles | 1 | ₹3.07 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of community Hall at Arpanpally Village, Kesamu ₹2,000,000 against a ₹499,000 median for Community Buildings works in MAHABUBABAD (301% above, 28 peer works) | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹20.00 L | 370 d | +301% | 76.0 | HIGH |
| at Ward No.7, Kesamudram station (V) Kesamudram (M), Mahabub Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹10.00 L | 311 d | 0% | 62.3 | MEDIUM |
| Construction of Community Hall At Sy.No.503/1, 9th Ward, I 372 days beyond expected completion | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹4.98 L | 372 d | -0% | 59.6 | MEDIUM |
| Construction of Community Hall Near Ramalingeshwara Swamy Te 328 days beyond expected completion | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹4.99 L | 328 d | 0% | 59.5 | MEDIUM |
| Installation of fixed garden gym equipment AT Kalwala(V), Ke 325 days beyond expected completion | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹4.99 L | 325 d | 0% | 59.4 | MEDIUM |
| Construction of Toilet and providing Water Facility at Prim ₹499,000 against a ₹313,333 median for Water works in MAHABUBABAD (59% above, 10 peer works) | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹4.99 L | 133 d | +59% | 59.3 | MEDIUM |
| Installation of Fixed Garden Gym Equipment at Ward No.2, Kes 311 days beyond expected completion | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹4.98 L | 311 d | 0% | 59.1 | MEDIUM |
| Installation of LED Street lights at Shanigapuram ward no.9t ₹500,000 against a ₹229,549 median for Street Lighting works in MAHABUBABAD (118% above, 193 peer works) | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹5.00 L | 310 d | +118% | 56.0 | MEDIUM |
| Installation of Street lights at Edulapusapally Ward No.1 of ₹500,000 against a ₹229,549 median for Street Lighting works in MAHABUBABAD (118% above, 193 peer works) | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹5.00 L | 310 d | +118% | 56.0 | MEDIUM |
| Installation of Street Lights at Jamandlapally, Ward No.2 & ₹500,000 against a ₹229,549 median for Street Lighting works in MAHABUBABAD (118% above, 193 peer works) | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹5.00 L | 310 d | +118% | 56.0 | MEDIUM |
| Construction of Community Hall Beside SBI Bank Gumdoor in Wa ₹999,000 against a ₹499,000 median for Community Buildings works in MAHABUBABAD (100% above, 28 peer works) | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹9.99 L | 161 d | +100% | 53.3 | MEDIUM |
| Laying of CC Road from Badavath Kamili(H) to Badavath Santos 150 days beyond expected completion | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹4.99 L | 150 d | +0% | 52.7 | MEDIUM |
| Construction of Community Hall at Ward No.08, Kesamudram Mun ₹1,000,000 against a ₹499,000 median for Community Buildings works in MAHABUBABAD (100% above, 28 peer works) | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹10.00 L | — | +100% | 51.0 | MEDIUM |
| Construction of compund wall at road side at NTR Stadium, Ma ₹1,980,000 against a ₹498,402 median for Roads & Paving works in MAHABUBABAD (297% above, 187 peer works) | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹19.80 L | 115 d | +297% | 47.0 | MEDIUM |
| Construction of Community Hall at Ward No.4 in Inugurthy 109 days beyond expected completion | MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) | Recommended | ₹4.99 L | 109 d | 0% | 46.4 | MEDIUM |