264 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) 1 high risk | 264 | 21 | ₹7.18 Cr | 89 | 28.3 | KPR Constructions 23% of spend · 27 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Godam Nagesh ADILABAD | 173 | ₹5.54 Cr | 3 |
| Damodar Rao Divakonda Sitting Rajya Sabha | 52 | ₹62.40 L | 52 |
| Ravi Chandra Vaddiraju Sitting Rajya Sabha | 25 | ₹55.97 L | 23 |
| Renuka Chowdhury Sitting Rajya Sabha | 14 | ₹46.50 L | 11 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 97 | ₹1.76 Cr | 82 |
| Water | 60 | ₹1.02 Cr | 1 |
| Community Buildings | 58 | ₹2.64 Cr | 6 |
| Roads & Paving | 21 | ₹73.00 L | 0 |
| Boundary & Protection | 7 | ₹29.99 L | 0 |
| Education | 7 | ₹24.00 L | 0 |
| Drainage & Sanitation | 6 | ₹21.99 L | 0 |
| Religious & Cultural | 3 | ₹10.00 L | 0 |
| Sports | 2 | ₹10.00 L | 0 |
| Other | 1 | ₹1.50 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Extra Floor on Existing Community Hall at So ₹1,000,000 against a ₹500,000 median for Community Buildings works in ADILABAD (100% above, 112 peer works) | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹10.00 L | 325 d | +100% | 78.1 | HIGH |
| Erection of LED High mast lights near Hanuman Temple at Tej 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |
| Erection of LED High mast light in DevulaThanda, Rolmamada 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |
| Erection of LED High mast lights near Gandhi Chowk in Nera 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |
| Erection of LED High mast lights in Kistapur (V), Neradigon 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |
| Erection of LED High mast lights in Buddikonda (V), Neradig 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |
| Erection of LED High mast lights in Venkatapur (V), Neradigo 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |
| Erection of LED High mast lights in Chinnabuggaram (V), Nera 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |
| Erection of LED High mast lights in Nandyanaik thanda (V), N 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |
| Erection of LED High mast lights in Dhannur (V), Neradigonda 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |
| Erection of LED High mast lights in Wagdhari (V), Neradigond 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |
| Erection of LED High mast lights in Tharnam B (V), Neradigon 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |
| Erection of LED High mast lights in Shankarapur (V), Neradig 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |
| Erection of LED Three High mast lights in Boregaon(V), Nerad 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |
| Erection of LED one High mast lights in Dhannur D(V), Neradi 332 days beyond expected completion | ADILABAD(DISTRICT COLLECTOR ADILABAD_IDA) | Recommended | ₹1.50 L | 332 d | +25% | 61.8 | MEDIUM |