| 1 | Construction of two class rooms in Bhagwat Jha Azad Degree C Education — JAMTARA(Deputy Commissioner Jamtara_IDA) - ₹1,000,000 against a ₹249,745 median for Education works in JAMTARA (300% above, 46 peer works)
- 430 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 97% of this agency's ₹28,850,000 spend went to one vendor (PRAHLAD MANDAL), across 2 vendors and 108 transactions
| JAMTARA | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 2 | Renovation of the Chhotka Aahar in village Gerua of Panchaya Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹1,200,000 against a ₹200,000 median for Water works in CHATRA (500% above, 156 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹12.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 3 | Renovation of the Chhotka Aahar in village Bukru of Panchaya Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹1,000,000 against a ₹200,000 median for Water works in CHATRA (400% above, 156 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 100% of this agency's ₹28,661,363 spend went to one vendor (District Engineer), across 1 vendor and 148 transactions
| CHATRA | ₹10.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 4 | Construction of community hall in sahilong in dumargadi pan Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,200,000 against a ₹500,000 median for Community Buildings works in KHUNTI (140% above, 30 peer works)
- 805 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 74% of this agency's ₹40,768,520 spend went to one vendor (ASSISTANT ENGINEER ZILA PARISHAD KHUNTI), across 3 vendors and 103 transactions
| KHUNTI | ₹12.00 L | HIGH 85
cost 25delay 25duplication 20 | |
| 5 | Panchayat Kundalwadah Village Jhitri Pond construction near Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹299,570 median for Water works in GIRIDIH (234% above, 168 peer works)
- 186 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹10.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 6 | Panchayat Kundalwadah, Village Kundalwadah Pond constructio Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹299,570 median for Water works in GIRIDIH (234% above, 168 peer works)
- 186 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹10.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 7 | Construction of pond in Panchayat Chapuadih, Village-Phucho Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹299,570 median for Water works in GIRIDIH (234% above, 168 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹10.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 8 | Panchayat Jhalakdiha, Village Tikalto, Tola Ganganpur - Cons Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,500,000 against a ₹299,570 median for Water works in GIRIDIH (401% above, 168 peer works)
- 199 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹15.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 9 | Construction of Guest House at Radha Krishan Thakur Bari Sev Community Buildings — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in GIRIDIH (233% above, 90 peer works)
- 562 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 65% of this agency's ₹110,464,562 spend went to one vendor (Executive engineer), across 2 vendors and 335 transactions
| GIRIDIH | ₹10.00 L | HIGH 83
cost 25delay 25duplication 20 | |
| 10 | Construction of Paver Block path from jhumri pond towards pa Roads & Paving — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - ₹1,000,000 against a ₹299,932 median for Roads & Paving works in KODERMA (233% above, 112 peer works)
- 166 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 88% of this agency's ₹18,356,889 spend went to one vendor (JE SATYENDRA KUMAR), across 3 vendors and 59 transactions
| KODERMA | ₹10.00 L | HIGH 83
cost 25delay 23duplication 20 | |
| 11 | Panchayat Kundalwadah Village Jhitri Pond construction near Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹299,570 median for Water works in GIRIDIH (234% above, 168 peer works)
- 186 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹10.00 L | HIGH 82
cost 25delay 25duplication 20 | |
| 12 | Panchayat Kundalwadah, Village Kundalwadah Pond constructio Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹299,570 median for Water works in GIRIDIH (234% above, 168 peer works)
- 186 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹10.00 L | HIGH 82
cost 25delay 25duplication 20 | |
| 13 | Construction of pond in Panchayat Chapuadih, Village-Phucho Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹299,570 median for Water works in GIRIDIH (234% above, 168 peer works)
- 195 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹10.00 L | HIGH 82
cost 25delay 25duplication 20 | |
| 14 | Panchayat Jhalakdiha, Village Tikalto, Tola Ganganpur - Cons Water — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,500,000 against a ₹299,570 median for Water works in GIRIDIH (401% above, 168 peer works)
- 199 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹15.00 L | HIGH 82
cost 25delay 25duplication 20 | |
| 15 | Construction of Guest House at Radha Krishan Thakur Bari Sev Community Buildings — GIRIDIH(Deputy Commissioner Giridh_IDA) - ₹1,000,000 against a ₹300,000 median for Community Buildings works in GIRIDIH (233% above, 90 peer works)
- 562 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 57% of this agency's ₹126,197,671 spend went to one vendor (Executive engineer), across 2 vendors and 380 transactions
| GIRIDIH | ₹10.00 L | HIGH 82
cost 25delay 25duplication 20 | |
| 16 | Construction of multipurpose hall in M.B.D. college kauria, Education — BOKARO(DEPUTY COMMISSIONER BOKARO_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in BOKARO (100% above, 15 peer works)
- 805 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| BOKARO | ₹10.00 L | HIGH 81
cost 25delay 25duplication 20 | |
| 17 | Construction of multipurpose hall in M.B.D. college kauria, Education — BOKARO(DEPUTY COMMISSIONER BOKARO_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in BOKARO (100% above, 15 peer works)
- 805 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| BOKARO | ₹10.00 L | HIGH 81
cost 25delay 25duplication 20 | |
| 18 | Construction of PCC road from kusum vihar phase-2 main road Roads & Paving — DHANBAD(DEPUTY COMMISSIONER DHANBAD_IDA) - ₹1,000,000 against a ₹300,000 median for Roads & Paving works in DHANBAD (233% above, 344 peer works)
- 774 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 61% of this agency's ₹72,550,145 spend went to one vendor (BIRENDRA KUMAR MAHATO), across 6 vendors and 408 transactions
| DHANBAD | ₹10.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 19 | Construction of community hall in sahilong in dumargadi pan Community Buildings — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) - ₹1,200,000 against a ₹500,000 median for Community Buildings works in KHUNTI (140% above, 30 peer works)
- 805 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactions
| KHUNTI | ₹12.00 L | HIGH 80
cost 25delay 25duplication 20 | |
| 20 | Construction of Paver Block path from jhumri pond towards pa Roads & Paving — KODERMA(DEPUTY COMMISSIONER KODARMA_IDA) - ₹1,000,000 against a ₹299,932 median for Roads & Paving works in KODERMA (233% above, 112 peer works)
- 166 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 63% of this agency's ₹19,120,071 spend went to one vendor (JE SATYENDRA KUMAR), across 5 vendors and 72 transactions
| KODERMA | ₹10.00 L | HIGH 79
cost 25delay 23duplication 20 | |
| 21 | Construction of PCC road from kusum vihar phase-2 main road Roads & Paving — DHANBAD(DEPUTY COMMISSIONER DHANBAD_IDA) - ₹1,000,000 against a ₹300,000 median for Roads & Paving works in DHANBAD (233% above, 344 peer works)
- 774 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 43% of this agency's ₹79,555,681 spend went to one vendor (BHAGAT KUMAR RAY), across 5 vendors and 537 transactions
| DHANBAD | ₹10.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 22 | Construction of two class rooms in Bhagwat Jha Azad Degree C Education — JAMTARA(Deputy Commissioner Jamtara_IDA) - ₹1,000,000 against a ₹249,745 median for Education works in JAMTARA (300% above, 46 peer works)
- 430 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 46% of this agency's ₹28,689,800 spend went to one vendor (SANTOSH KUMAR MONDAL), across 3 vendors and 104 transactions
| JAMTARA | ₹10.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 23 | Renovation of the Chhotka Aahar in village Gerua of Panchaya Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹1,200,000 against a ₹200,000 median for Water works in CHATRA (500% above, 156 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| CHATRA | ₹12.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 24 | Renovation of the Chhotka Aahar in village Bukru of Panchaya Water — CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) - ₹1,000,000 against a ₹200,000 median for Water works in CHATRA (400% above, 156 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| CHATRA | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 25 | Installation of solar street light in durgapur panchayat:
1) Street Lighting — BOKARO(DEPUTY COMMISSIONER BOKARO_IDA) - ₹220,000 against a ₹22,000 median for Street Lighting works in BOKARO (900% above, 443 peer works)
- 363 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 73% delay rate across its projects
| BOKARO | ₹2.20 L | HIGH 77
cost 25delay 25duplication 16 | |