345 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) 2 high risk | 345 | 0 | ₹6.46 Cr | 41 | 30.6 | District Engineer 100% of spend · 1 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Kali Charan Singh CHATRA | 343 | ₹6.24 Cr | 39 |
| Pradip Kumar Varma Sitting Rajya Sabha | 2 | ₹22.00 L | 2 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Water | 154 | ₹3.29 Cr | 12 |
| Community Buildings | 93 | ₹1.75 Cr | 10 |
| Religious & Cultural | 56 | ₹75.00 L | 16 |
| Roads & Paving | 31 | ₹47.00 L | 3 |
| Education | 9 | ₹18.00 L | 0 |
| Other | 1 | ₹1.00 L | 0 |
| Drainage & Sanitation | 1 | ₹1.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Renovation of the Chhotka Aahar in village Gerua of Panchaya ₹1,200,000 against a ₹200,000 median for Water works in CHATRA (500% above, 156 peer works) | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹12.00 L | 216 d | +500% | 85.0 | HIGH |
| Renovation of the Chhotka Aahar in village Bukru of Panchaya ₹1,000,000 against a ₹200,000 median for Water works in CHATRA (400% above, 156 peer works) | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹10.00 L | 216 d | +400% | 85.0 | HIGH |
| Repairing of Baherwa Ahar ₹300,000 against a ₹200,000 median for Water works in CHATRA (50% above, 156 peer works) | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹3.00 L | 128 d | +50% | 65.3 | MEDIUM |
| Repairing of Dumaria Ahar 115 days beyond expected completion | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹1.00 L | 115 d | -50% | 57.4 | MEDIUM |
| Construction of steps in Purainiya Talab ₹600,000 against a ₹200,000 median for Water works in CHATRA (200% above, 156 peer works) | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹6.00 L | 119 d | +200% | 56.5 | MEDIUM |
| Repairing of Baherwa Ahar 111 days beyond expected completion | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹1.50 L | 111 d | -25% | 56.0 | MEDIUM |
| Repairing of Dumaria Ahar 115 days beyond expected completion | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹2.00 L | 115 d | 0% | 56.0 | MEDIUM |
| Construction of Atal Ashmiriti Bhawan in Pathalgada ₹500,000 against a ₹200,000 median for Community Buildings works in CHATRA (150% above, 96 peer works) | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹5.00 L | 108 d | +150% | 55.0 | MEDIUM |
| Repairing of Guhi Ahar 119 days beyond expected completion | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹1.00 L | 119 d | -50% | 53.0 | MEDIUM |
| Repair of Guhi Ahar 119 days beyond expected completion | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹1.50 L | 119 d | -25% | 52.3 | MEDIUM |
| Retrofitting of Chandravanshi Bhawan (Block-Kanhachatti, Pan ₹400,000 against a ₹200,000 median for Community Buildings works in CHATRA (100% above, 96 peer works) | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹4.00 L | 88 d | +100% | 52.2 | MEDIUM |
| Construction of chabutra (Block-Kanhachatti, Panchayat-Kolha 88 days beyond expected completion | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹1.00 L | 88 d | -50% | 47.4 | MEDIUM |
| Construction of chabutra (Block-Kanhachatti, Panchayat-Kolha 88 days beyond expected completion | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹1.00 L | 88 d | -50% | 47.4 | MEDIUM |
| Construction of Chabutra near shiv mandir (Block-Kanhachatti 88 days beyond expected completion | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹1.00 L | 88 d | 0% | 46.2 | MEDIUM |
| Repair of Dhani Ahar ₹300,000 against a ₹200,000 median for Water works in CHATRA (50% above, 156 peer works) | CHATRA(DEPUTY COMMISSIONER CHATRA_IDA) | Recommended | ₹3.00 L | 124 d | +50% | 44.7 | MEDIUM |