| 1 | Construction of Community centres and Community Hall Community Buildings — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Community Buildings works in SHIMLA (150% above, 221 peer works)
- 284 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 2 | Construction of Link Road and pathways Roads & Paving — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in SHIMLA (150% above, 330 peer works)
- 284 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 3 | C/o Boundary Wall behind the house of Sh. Bhim Singh S/o Dur Boundary & Protection — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Boundary & Protection works in SHIMLA (150% above, 39 peer works)
- 332 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 4 | Installation of Hand Pump with electric motor at village Kar Water — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹300,000 against a ₹150,000 median for Water works in SHIMLA (100% above, 23 peer works)
- 339 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹3.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 5 | C/o L/R and ambulance road from National Highway 205 upto Sh Roads & Paving — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹1,000,000 against a ₹200,000 median for Roads & Paving works in SHIMLA (400% above, 330 peer works)
- 574 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹10.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 6 | c/o L/R from Nature Park to Village Sharai G.P. Mashobra Dev Sports — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹1,000,000 against a ₹150,000 median for Sports works in SHIMLA (567% above, 85 peer works)
- 747 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹10.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 7 | Construction of Community centres and Community Hall Community Buildings — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Community Buildings works in SHIMLA (150% above, 221 peer works)
- 284 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 8 | Construction of Link Road and pathways Roads & Paving — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in SHIMLA (150% above, 330 peer works)
- 284 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 9 | C/o Boundary Wall behind the house of Sh. Bhim Singh S/o Dur Boundary & Protection — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹500,000 against a ₹200,000 median for Boundary & Protection works in SHIMLA (150% above, 39 peer works)
- 332 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹5.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 10 | Installation of Hand Pump with electric motor at village Kar Water — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹300,000 against a ₹150,000 median for Water works in SHIMLA (100% above, 23 peer works)
- 339 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹3.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 11 | C/o L/R and ambulance road from National Highway 205 upto Sh Roads & Paving — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹1,000,000 against a ₹200,000 median for Roads & Paving works in SHIMLA (400% above, 330 peer works)
- 574 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹10.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 12 | c/o L/R from Nature Park to Village Sharai G.P. Mashobra Dev Sports — SHIMLA(DEPUTY COMMISSIONER SHIMLA_IDA) - ₹1,000,000 against a ₹150,000 median for Sports works in SHIMLA (567% above, 85 peer works)
- 747 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| SHIMLA | ₹10.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 13 | C/o Community Centre in G.P. Bhatoli, Ward No. 02, Dev. Bloc Community Buildings — UNA(DEPUTY COMMISSIOENR UNA_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in UNA (100% above, 36 peer works)
- 656 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 47% delay rate across its projects
| UNA | ₹4.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 14 | C/o Community Centre, G.P. Raipur Sahoran, Ward No. 07, Dev. Community Buildings — UNA(DEPUTY COMMISSIOENR UNA_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in UNA (100% above, 36 peer works)
- 656 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 47% delay rate across its projects
| UNA | ₹4.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 15 | C/o Community Hall/Centre Building at Harijan Basti Village Community Buildings — UNA(DEPUTY COMMISSIOENR UNA_IDA) - ₹1,000,000 against a ₹200,000 median for Community Buildings works in UNA (400% above, 36 peer works)
- 747 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 47% delay rate across its projects
| UNA | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 16 | C/o Community Centre in G.P. Bhatoli, Ward No. 02, Dev. Bloc Community Buildings — UNA(DEPUTY COMMISSIOENR UNA_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in UNA (100% above, 36 peer works)
- 656 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 47% delay rate across its projects
| UNA | ₹4.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 17 | C/o Community Centre, G.P. Raipur Sahoran, Ward No. 07, Dev. Community Buildings — UNA(DEPUTY COMMISSIOENR UNA_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in UNA (100% above, 36 peer works)
- 656 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 47% delay rate across its projects
| UNA | ₹4.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 18 | C/o Community Hall/Centre Building at Harijan Basti Village Community Buildings — UNA(DEPUTY COMMISSIOENR UNA_IDA) - ₹1,000,000 against a ₹200,000 median for Community Buildings works in UNA (400% above, 36 peer works)
- 747 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 47% delay rate across its projects
| UNA | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 19 | Construction of water tank at Village Borar Lani near the ho Water — SIRMAUR(DEPUTY COMMISSIONER SIRMOUR_IDA) - ₹300,000 against a ₹150,000 median for Water works in SIRMAUR (100% above, 52 peer works)
- 183 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SIRMAUR | ₹3.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 20 | Construction of water tank at Village Borar Lani near the ho Water — SIRMAUR(DEPUTY COMMISSIONER SIRMOUR_IDA) - ₹300,000 against a ₹150,000 median for Water works in SIRMAUR (100% above, 52 peer works)
- 183 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SIRMAUR | ₹3.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 21 | C/o additional rooms in GHS Phindru, VPO Phindru, Dev. Block Education — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹500,000 against a ₹250,000 median for Education works in CHAMBA (100% above, 23 peer works)
- 324 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 22 | Construction of Concrete Road Adarsh Nagar Hardaspura Ward p Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (150% above, 339 peer works)
- 373 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 23 | Construction of ambulance road soling conc. With drain main Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (100% above, 339 peer works)
- 412 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 24 | Pucca path from Chalang to Shamshan Ghat GP Chil Bangla Dev. Religious & Cultural — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Religious & Cultural works in CHAMBA (100% above, 38 peer works)
- 413 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 25 | Jeep Road from Khalotu to Bairi GP Chil Bangla Dev. Block Ch Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (100% above, 339 peer works)
- 413 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |