60 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | UNA(DEPUTY COMMISSIOENR UNA_IDA) 3 high risk | 60 | 22 | ₹2.35 Cr | 27 | 38.2 | RIYA ENTERPRISES 15% of spend · 54 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Anurag Singh Thakur HAMIRPUR | 23 | ₹44.99 L | 1 |
| Harsh Mahajan Sitting Rajya Sabha | 20 | ₹24.34 L | 11 |
| Sikander Kumar Sitting Rajya Sabha | 17 | ₹1.65 Cr | 15 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 26 | ₹40.29 L | 7 |
| Street Lighting | 10 | ₹9.74 L | 5 |
| Education | 8 | ₹1.18 Cr | 7 |
| Community Buildings | 5 | ₹23.00 L | 3 |
| Religious & Cultural | 4 | ₹9.50 L | 1 |
| Boundary & Protection | 3 | ₹5.20 L | 1 |
| Sports | 2 | ₹6.05 L | 1 |
| Drainage & Sanitation | 1 | ₹2.50 L | 1 |
| Water | 1 | ₹20.00 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| C/o Community Centre in G.P. Bhatoli, Ward No. 02, Dev. Bloc ₹400,000 against a ₹200,000 median for Community Buildings works in UNA (100% above, 36 peer works) | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹4.00 L | 656 d | +100% | 77.0 | HIGH |
| C/o Community Centre, G.P. Raipur Sahoran, Ward No. 07, Dev. ₹400,000 against a ₹200,000 median for Community Buildings works in UNA (100% above, 36 peer works) | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹4.00 L | 656 d | +100% | 77.0 | HIGH |
| C/o Community Hall/Centre Building at Harijan Basti Village ₹1,000,000 against a ₹200,000 median for Community Buildings works in UNA (400% above, 36 peer works) | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹10.00 L | 747 d | +400% | 77.0 | HIGH |
| construction work of Link Road 333 days beyond expected completion | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹1.00 L | 333 d | -33% | 61.8 | MEDIUM |
| construction work of Link Road 333 days beyond expected completion | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹1.00 L | 333 d | -33% | 61.8 | MEDIUM |
| C/o Pakka Path from the house of Sh. Dhani Ram to main road 676 days beyond expected completion | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹2.00 L | 676 d | +33% | 60.9 | MEDIUM |
| construction work of Link Road 333 days beyond expected completion | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹1.50 L | 333 d | 0% | 60.8 | MEDIUM |
| construction work of Link Road 333 days beyond expected completion | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹1.50 L | 333 d | 0% | 60.8 | MEDIUM |
| Construction of Link Road & pathways 284 days beyond expected completion | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹1.50 L | 284 d | 0% | 60.2 | MEDIUM |
| Development of public park’s 284 days beyond expected completion | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹5.00 L | 284 d | 0% | 60.0 | MEDIUM |
| Construction of Community Centre at Village and Gram Panchay Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹20.00 L | 127 d | 0% | 57.4 | MEDIUM |
| Purchase of books for Schools and Public Library in District Completed work has no photographic documentation on record | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Completed | ₹19.97 L | — | +150% | 56.5 | MEDIUM |
| Number of 6, Solar Light, GP Babehar, Dev. Block Gagret 153 days beyond expected completion | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹93,000 | 153 d | 0% | 55.6 | MEDIUM |
| Number of 6, Solar Light, GP Kuneran, Dev. Block Gagret 153 days beyond expected completion | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹93,000 | 153 d | 0% | 55.6 | MEDIUM |
| Number of 6, Solar Light, GP Ghanari, Dev. Block Gagret 153 days beyond expected completion | UNA(DEPUTY COMMISSIOENR UNA_IDA) | Recommended | ₹93,000 | 153 d | 0% | 55.6 | MEDIUM |