| 1 | Construction of three (3) classrooms. Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹4,008,840 against a ₹1,090,000 median for Education works in SOUTH GOA (268% above, 96 peer works)
- 573 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹40.09 L | HIGH 75
cost 25delay 25duplication 20 | |
| 2 | Construction of three (3) classrooms. Education — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - ₹4,008,840 against a ₹1,090,000 median for Education works in SOUTH GOA (268% above, 96 peer works)
- 573 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹40.09 L | HIGH 72
cost 25delay 25duplication 20 | |
| 3 | Wheelchair-Accessible School Bus for Anand Niketan Special S Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 337 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹30.18 L | HIGH 72
delay 25duplication 20cost 18 | |
| 4 | Wheelchair-Accessible School Bus for Anand Niketan Special S Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 337 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹30.18 L | HIGH 72
delay 25duplication 20cost 18 | |
| 5 | SCHOOL BUS for Dayanand High School, Chorao-Ilhas, North Goa Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 317 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹26.21 L | HIGH 71
delay 25duplication 20cost 16 | |
| 6 | SCHOOL BUS for Dayanand High School, Chorao-Ilhas, North Goa Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 317 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹26.21 L | HIGH 71
delay 25duplication 20cost 16 | |
| 7 | School Bus for Goa College of Physiotherapy, Naturopathy and Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 180 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹28.60 L | HIGH 70
delay 25duplication 20cost 16 | |
| 8 | School Bus for Tagore Educational Institute, Kothambi, Pale, Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 180 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹28.60 L | HIGH 70
delay 25duplication 20cost 16 | |
| 9 | School Bus for Goa College of Physiotherapy, Naturopathy and Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 180 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹28.60 L | HIGH 70
delay 25duplication 20cost 16 | |
| 10 | School Bus for Tagore Educational Institute, Kothambi, Pale, Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 180 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹28.60 L | HIGH 70
delay 25duplication 20cost 16 | |
| 11 | School Bus for Saraswat Vidyalaya, Telang Nagar, Khorlim, Ma Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 180 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹26.73 L | MEDIUM 69
delay 25duplication 20cost 15 | |
| 12 | School Bus for Saraswat Vidyalaya, Telang Nagar, Khorlim, Ma Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 180 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹26.73 L | MEDIUM 69
delay 25duplication 20cost 15 | |
| 13 | School Bus for Shree Bhagwati High School, Pernem, North Goa Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 148 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹31.62 L | MEDIUM 66
delay 21duplication 20cost 17 | |
| 14 | School Bus for Shree Bhagwati High School, Pernem, North Goa Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 148 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹31.62 L | MEDIUM 66
delay 21duplication 20cost 17 | |
| 15 | School Bus for Sateri Vidhya Mandir, Ibrampur, Pernem, P.O. Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 153 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹27.77 L | MEDIUM 66
delay 21duplication 20cost 15 | |
| 16 | School Bus for Sateri Vidhya Mandir, Ibrampur, Pernem, P.O. Education — NORTH GOA(DISTRICT COLLECTOR NORTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 153 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 62% delay rate across its projects
| NORTH GOA | ₹27.77 L | MEDIUM 66
delay 21duplication 20cost 15 | |
| 17 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹20.00 L | MEDIUM 66
delay 25duplication 20cost 18 | |
| 18 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹20.00 L | MEDIUM 66
delay 25duplication 20cost 18 | |
| 19 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 20 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 21 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 22 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 23 | Covering of roadside drainages by installing RCC Slabs. Drainage & Sanitation — SOUTH GOA(DISTRICT COLLECTOR SOUTH GOA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 757 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH GOA | ₹15.00 L | MEDIUM 65
delay 25duplication 20cost 17 | |
| 24 | INSTALLATION OF 20 CM LED HIGH MAST POLES WITH SIX LIGHTS EA Street Lighting — SHAHJAHANPUR(DISTRICT MAGISTRAE SHAHJAHANAPUR_IDA) - ₹4,860,000 against a ₹243,000 median for Street Lighting works in SHAHJAHANPUR (1900% above, 1015 peer works)
- 127 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SHAHJAHANPUR | ₹48.60 L | MEDIUM 64
cost 25duplication 20delay 18 | |
| 25 | INSTALLATION OF 20 CM LED HIGH MAST POLES WITH SIX LIGHTS EA Street Lighting — SHAHJAHANPUR(DISTRICT MAGISTRAE SHAHJAHANAPUR_IDA) - ₹4,860,000 against a ₹243,000 median for Street Lighting works in SHAHJAHANPUR (1900% above, 1015 peer works)
- 127 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SHAHJAHANPUR | ₹48.60 L | MEDIUM 64
cost 25duplication 20delay 18 | |