| 1 | Regarding the installation of High Mast light at Sita Kund D Street Lighting — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹1,296,194 against a ₹563,000 median for Street Lighting works in SULTANPUR (130% above, 44 peer works)
- 158 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹12.96 L | HIGH 73
cost 25delay 22duplication 20 | |
| 2 | Regarding the installation of High Mast light at Sita Kund D Street Lighting — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹1,296,194 against a ₹563,000 median for Street Lighting works in SULTANPUR (130% above, 44 peer works)
- 158 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹12.96 L | HIGH 73
cost 25delay 22duplication 20 | |
| 3 | Supply Installation Testing & Commissioning of CCTV Surveill Equipment & Vehicles — EAST(COMMISSIONER EAST) - ₹1,800,000 against a ₹788,200 median for Equipment & Vehicles works in EAST (128% above, 36 peer works)
- 550 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| EAST | ₹18.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 4 | Supply Installation Testing & Commissioning of CCTV Surveill Equipment & Vehicles — EAST(COMMISSIONER EAST) - ₹5,000,000 against a ₹788,200 median for Equipment & Vehicles works in EAST (534% above, 36 peer works)
- 550 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| EAST | ₹50.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 5 | Supply Installation Testing & Commissioning of CCTV Surveill Equipment & Vehicles — EAST(COMMISSIONER EAST) - ₹2,500,000 against a ₹788,200 median for Equipment & Vehicles works in EAST (217% above, 36 peer works)
- 550 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| EAST | ₹25.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 6 | Supply Installation Testing & Commissioning of CCTV Surveill Equipment & Vehicles — EAST(COMMISSIONER EAST) - ₹1,700,000 against a ₹788,200 median for Equipment & Vehicles works in EAST (116% above, 36 peer works)
- 550 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| EAST | ₹17.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 7 | Supply Installation Testing & Commissioning of CCTV Surveill Equipment & Vehicles — EAST(COMMISSIONER EAST) - ₹1,500,000 against a ₹788,200 median for Equipment & Vehicles works in EAST (90% above, 36 peer works)
- 550 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| EAST | ₹15.00 L | MEDIUM 69
delay 25cost 23duplication 20 | |
| 8 | Construction of 400 Mtr Track in Stadium Sports — SONIPAT(DEPUTY COMMISSIONER SONEPAT_IDA) - ₹1,467,000 against a ₹537,000 median for Sports works in SONIPAT (173% above, 19 peer works)
- 113 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SONIPAT | ₹14.67 L | MEDIUM 65
cost 25duplication 20delay 16 | |
| 9 | Construction of 400 Mtr Track in Stadium Sports — SONIPAT(DEPUTY COMMISSIONER SONEPAT_IDA) - ₹1,467,000 against a ₹537,000 median for Sports works in SONIPAT (173% above, 19 peer works)
- 113 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SONIPAT | ₹14.67 L | MEDIUM 65
cost 25duplication 20delay 16 | |
| 10 | Provision of Semi High Mast Lights (12 Mtr) in under the Sou Street Lighting — SOUTH WEST(COMMISSIONER MCD SOUTH WEST) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 593 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| SOUTH WEST | ₹17.02 L | MEDIUM 63
delay 25duplication 18cost 16 | |
| 11 | Provision of Semi High Mast Lights (12 Mtr) in under the Sou Street Lighting — SOUTH WEST(COMMISSIONER MCD SOUTH WEST) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 593 days beyond expected completion
Read more (1 more)Show less- 99% similarity with another nearby work
| SOUTH WEST | ₹17.14 L | MEDIUM 63
delay 25duplication 18cost 16 | |
| 12 | Supply Installation Testing and Commissioning of cctv Survei Equipment & Vehicles — CENTRAL(COMMISSIONER MCD (CENTRAL DISTRICT)) - ₹4,779,933 against a ₹318,720 median for Equipment & Vehicles works in CENTRAL (1400% above, 29 peer works)
- 81 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 54% of this agency's ₹41,296,762 spend went to one vendor (Central Electronics Limited), across 17 vendors and 31 transactions
| CENTRAL | ₹47.80 L | MEDIUM 63
cost 25duplication 20delay 11 | |
| 13 | Supply Installation Testing and Commissioning of cctv Survei Equipment & Vehicles — CENTRAL(COMMISSIONER MCD (CENTRAL DISTRICT)) - ₹25,217,575 against a ₹318,720 median for Equipment & Vehicles works in CENTRAL (7812% above, 29 peer works)
- 81 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 54% of this agency's ₹41,296,762 spend went to one vendor (Central Electronics Limited), across 17 vendors and 31 transactions
| CENTRAL | ₹2.52 Cr | MEDIUM 63
cost 25duplication 20delay 11 | |
| 14 | Recommendation for Installation of Various Lighting Arrangem Street Lighting — SOUTH(COMMISSIONER SOUTH) - ₹3,726,112 against a ₹968,970 median for Street Lighting works in SOUTH (285% above, 119 peer works)
- 114 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH | ₹37.26 L | MEDIUM 62
cost 25duplication 20delay 16 | |
| 15 | Recommendation for Installation of Various Lighting Arrangem Street Lighting — SOUTH(COMMISSIONER SOUTH) - ₹3,726,112 against a ₹968,970 median for Street Lighting works in SOUTH (285% above, 119 peer works)
- 114 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH | ₹37.26 L | MEDIUM 62
cost 25duplication 20delay 16 | |
| 16 | Recommendation for Installation of Two Water Coolers at Pant Water — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹744,780 against a ₹372,390 median for Water works in SULTANPUR (100% above, 11 peer works)
- 78 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹7.45 L | MEDIUM 62
cost 25duplication 20delay 11 | |
| 17 | Recommendation for Installation of Two Water Coolers at Pant Water — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹744,780 against a ₹372,390 median for Water works in SULTANPUR (100% above, 11 peer works)
- 78 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹7.45 L | MEDIUM 62
cost 25duplication 20delay 11 | |
| 18 | Providing or fixing of Open Air Gym Equipment Sports — EAST(COMMISSIONER EAST) - ₹1,467,121 against a ₹426,472 median for Sports works in EAST (244% above, 70 peer works)
- 79 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| EAST | ₹14.67 L | MEDIUM 61
cost 25duplication 20delay 11 | |
| 19 | Installation of Childrens Play Equipment Equipment & Vehicles — CENTRAL(COMMISSIONER MCD (CENTRAL DISTRICT)) - ₹1,000,000 against a ₹318,720 median for Equipment & Vehicles works in CENTRAL (214% above, 29 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 54% of this agency's ₹41,296,762 spend went to one vendor (Central Electronics Limited), across 17 vendors and 31 transactions
| CENTRAL | ₹10.00 L | MEDIUM 61
cost 25duplication 20delay 9 | |
| 20 | Construction of Basket Ball Court in Stadium Sports — SONIPAT(DEPUTY COMMISSIONER SONEPAT_IDA) - ₹964,000 against a ₹537,000 median for Sports works in SONIPAT (80% above, 19 peer works)
- 113 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SONIPAT | ₹9.64 L | MEDIUM 60
duplication 20cost 20delay 16 | |
| 21 | Construction of Basket Ball Court in Stadium Sports — SONIPAT(DEPUTY COMMISSIONER SONEPAT_IDA) - ₹964,000 against a ₹537,000 median for Sports works in SONIPAT (80% above, 19 peer works)
- 113 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SONIPAT | ₹9.64 L | MEDIUM 60
duplication 20cost 20delay 16 | |
| 22 | Provision of Semi High mast lights (12 Mtr) in under the Sou Street Lighting — SOUTH(COMMISSIONER SOUTH) - ₹1,710,617 against a ₹968,970 median for Street Lighting works in SOUTH (77% above, 119 peer works)
- 593 days beyond expected completion
Read more (1 more)Show less- 98% similarity with another nearby work
| SOUTH | ₹17.11 L | MEDIUM 59
delay 25cost 19duplication 13 | |
| 23 | Provision of Semi High mast lights (12 Mtr) in under the Sou Street Lighting — SOUTH(COMMISSIONER SOUTH) - ₹1,710,617 against a ₹968,970 median for Street Lighting works in SOUTH (77% above, 119 peer works)
- 595 days beyond expected completion
Read more (1 more)Show less- 98% similarity with another nearby work
| SOUTH | ₹17.11 L | MEDIUM 59
delay 25cost 19duplication 13 | |
| 24 | TPD Aerobic Drum Compost Plant along with Sieving Trommel, S Drainage & Sanitation — EAST(COMMISSIONER EAST) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 2117 days beyond expected completion
Read more (1 more)Show less- 97% similarity with another nearby work
| EAST | ₹15.44 L | MEDIUM 59
delay 25cost 20duplication 12 | |
| 25 | TPD Aerobic Drum Compost Plant along with Sieving Trommel, S Drainage & Sanitation — EAST(COMMISSIONER EAST) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 2117 days beyond expected completion
Read more (1 more)Show less- 97% similarity with another nearby work
| EAST | ₹15.44 L | MEDIUM 59
delay 25cost 20duplication 12 | |