| 1 | Construction of Hiyangthang community hall at Hiyangthang Community Buildings — IMPHAL WEST(Deputy Commissioner Imphal West MPLADS_IDA) - ₹2,500,000 against a ₹1,500,000 median for Community Buildings works in IMPHAL WEST (67% above, 10 peer works)
- 565 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹25,013,448 spend went to one vendor (PS ENTERPRISES), across 1 vendor and 24 transactions
| IMPHAL WEST | ₹25.00 L | MEDIUM 57 | |
| 2 | Construction of Waiting Shed Community Buildings — IMPHAL WEST(Deputy Commissioner Imphal West MPLADS_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 554 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹25,013,448 spend went to one vendor (PS ENTERPRISES), across 1 vendor and 24 transactions
| IMPHAL WEST | ₹20.00 L | MEDIUM 57 | |
| 3 | Construction of Public park at Lilong chajing, Imphal West Sports — IMPHAL WEST(Deputy Commissioner Imphal West MPLADS_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 547 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹25,013,448 spend went to one vendor (PS ENTERPRISES), across 1 vendor and 24 transactions
| IMPHAL WEST | ₹15.00 L | MEDIUM 55 | |
| 4 | Construction of market Shed at Khonghampat Awang Leikai Community Buildings — IMPHAL WEST(Deputy Commissioner Imphal West MPLADS_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 547 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹25,013,448 spend went to one vendor (PS ENTERPRISES), across 1 vendor and 24 transactions
| IMPHAL WEST | ₹10.00 L | MEDIUM 53 | |
| 5 | Construction of Moirang Khunou Community Hall with Kitchen S Community Buildings — BISHNUPUR(Deputy Commissioner Bishnupur_ida) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 561 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 47% delay rate across its projects
| BISHNUPUR | ₹48.00 L | MEDIUM 52 | |
| 6 | Construction of Multipurpose hall at Thanga Karang Community Buildings — BISHNUPUR(Deputy Commissioner Bishnupur_ida) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 547 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 47% delay rate across its projects
| BISHNUPUR | ₹35.00 L | MEDIUM 51 | |
| 7 | Renovation and beautification of Ningthoukhong Awang Mamang Religious & Cultural — BISHNUPUR(Deputy Commissioner Bishnupur_ida) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 545 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 47% delay rate across its projects
| BISHNUPUR | ₹12.54 L | MEDIUM 46 | |
| 8 | Renovation of Crematorium with one room shad at Khoikhoi Lei Religious & Cultural — BISHNUPUR(Deputy Commissioner Bishnupur_ida) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 549 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 47% delay rate across its projects
| BISHNUPUR | ₹10.00 L | MEDIUM 45 | |
| 9 | Donation of Medical Ambulance to District Hospitals under In Health — IMPHAL EAST(Deputy Commissioner Imphal East_IDA) - Completed work has no photographic documentation on record
- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
Read more (1 more)Show less- 91% of this agency's ₹59,595,962 spend went to one vendor (PS ENTERPRISES), across 2 vendors and 38 transactions
| IMPHAL EAST | ₹1.00 Cr | MEDIUM 42
cost 23agency 15compliance 5 | |
| 10 | Installation of Solar Street light under AJAY Phase II Street Lighting — IMPHAL EAST(Deputy Commissioner Imphal East_IDA) - Completed work has no photographic documentation on record
- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
Read more (1 more)Show less- 91% of this agency's ₹59,595,962 spend went to one vendor (PS ENTERPRISES), across 2 vendors and 38 transactions
| IMPHAL EAST | ₹53.96 L | MEDIUM 41
cost 21agency 15compliance 5 | |