10 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BISHNUPUR(Deputy Commissioner Bishnupur_ida) | 10 | 0 | ₹1.73 Cr | 4 | 33.1 | Murphy Thumrah 90% of spend · 2 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Angomcha Bimol Akoijam INNER MANIPUR | 6 | ₹1.18 Cr | 3 |
| Adhikarimayum Sharda Devi Sitting Rajya Sabha | 3 | ₹45.00 L | 1 |
| Alfred Kanngam S Arthur OUTER MANIPUR | 1 | ₹10.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 3 | ₹90.86 L | 2 |
| Roads & Paving | 3 | ₹21.00 L | 0 |
| Sports | 3 | ₹46.00 L | 1 |
| Street Lighting | 1 | ₹15.00 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Development of the Kumbi Kangjeibung (ground) and earth fill Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BISHNUPUR(Deputy Commissioner Bishnupur_ida) | Recommended | ₹26.00 L | 191 d | 0% | 58.5 | MEDIUM |
| A RCC market shed at Leimapokpam Bazar, Leimapokpam Mayai Le Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BISHNUPUR(Deputy Commissioner Bishnupur_ida) | Recommended | ₹49.00 L | 251 d | 0% | 51.6 | MEDIUM |
| Lighting the street around the Kumbi Kangjeibung Playground. Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BISHNUPUR(Deputy Commissioner Bishnupur_ida) | Recommended | ₹15.00 L | 191 d | 0% | 43.9 | MEDIUM |
| Civic Amenity Programme for Yumnam Khunou Maning Leikai Comm Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BISHNUPUR(Deputy Commissioner Bishnupur_ida) | Recommended | ₹30.00 L | — | 0% | 40.6 | MEDIUM |
| Development of Lashal playground 152 days beyond expected completion | BISHNUPUR(Deputy Commissioner Bishnupur_ida) | Recommended | ₹10.00 L | 152 d | 0% | 36.8 | LOW |
| Development and upgradation work of Salam Road (IVR), Nachou 100% similarity with another nearby work | BISHNUPUR(Deputy Commissioner Bishnupur_ida) | Recommended | ₹7.50 L | — | 0% | 29.5 | LOW |
| Development and upgradration work of Khongnang Karak Road, K 100% similarity with another nearby work | BISHNUPUR(Deputy Commissioner Bishnupur_ida) | Recommended | ₹7.50 L | — | 0% | 29.5 | LOW |
| Second Phase of Development of the Kumbi Kangjeibung Ground 97% similarity with another nearby work | BISHNUPUR(Deputy Commissioner Bishnupur_ida) | Recommended | ₹10.00 L | — | 0% | 21.0 | LOW |
| Renovation of Relief Camp at Santhong Community Hall, Kwakta Implementing agency has a 47% delay rate across its projects | BISHNUPUR(Deputy Commissioner Bishnupur_ida) | Recommended | ₹11.86 L | — | 0% | 10.8 | LOW |
| Construction of Culvert at Kumbi Kangjeibung. Implementing agency has a 47% delay rate across its projects | BISHNUPUR(Deputy Commissioner Bishnupur_ida) | Recommended | ₹6.00 L | — | 0% | 8.4 | LOW |