| 1 | High mask solar light at the intersection of Dilip Nishad in Street Lighting — PRAYAGRAJ(DISTRICT MAGISTRAE ALLAHABAD_IDA) - ₹150,000 against a ₹21,109 median for Street Lighting works in PRAYAGRAJ (611% above, 1120 peer works)
- 606 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 60% delay rate across its projects
| PRAYAGRAJ | ₹1.50 L | HIGH 79
cost 25delay 25duplication 20 | |
| 2 | High mask solar light at the intersection of Dilip Nishad in Street Lighting — PRAYAGRAJ(DISTRICT MAGISTRAE ALLAHABAD_IDA) - ₹150,000 against a ₹21,109 median for Street Lighting works in PRAYAGRAJ (611% above, 1120 peer works)
- 606 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 60% delay rate across its projects
| PRAYAGRAJ | ₹1.50 L | HIGH 79
cost 25delay 25duplication 20 | |
| 3 | Work of solar light and solar pump at public place near Shri Street Lighting — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - ₹3,000,000 against a ₹119,950 median for Street Lighting works in MIRZAPUR (2401% above, 95 peer works)
- 606 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹30.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 4 | Work of solar light and solar pump at public place near Shri Street Lighting — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - ₹3,000,000 against a ₹119,950 median for Street Lighting works in MIRZAPUR (2401% above, 95 peer works)
- 606 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹30.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 5 | New Construction of Panchayat House of village Pitovas under Community Buildings — BULANDSHAHR(DISTRICT MAGISTRATE BULANDSHAHR_IDA) - ₹2,000,000 against a ₹281,100 median for Community Buildings works in BULANDSHAHR (611% above, 19 peer works)
- 360 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BULANDSHAHR | ₹20.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 6 | New Construction of Panchayat House of village Pitovas under Community Buildings — BULANDSHAHR(DISTRICT MAGISTRATE BULANDSHAHR_IDA) - ₹2,000,000 against a ₹281,100 median for Community Buildings works in BULANDSHAHR (611% above, 19 peer works)
- 360 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BULANDSHAHR | ₹20.00 L | HIGH 71
cost 25delay 25duplication 20 | |
| 7 | Chaff warehouse and boundary construction work for public de Boundary & Protection — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - ₹4,600,000 against a ₹3,000,000 median for Boundary & Protection works in MIRZAPUR (53% above, 20 peer works)
- 606 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹46.00 L | HIGH 70
delay 25cost 21duplication 20 | |
| 8 | Chaff warehouse and boundary construction work for public de Boundary & Protection — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - ₹4,600,000 against a ₹3,000,000 median for Boundary & Protection works in MIRZAPUR (53% above, 20 peer works)
- 606 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹46.00 L | HIGH 70
delay 25cost 21duplication 20 | |
| 9 | Construction of public Panchayat building at Karondia in Gra Community Buildings — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 360 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹48.00 L | MEDIUM 70
delay 25cost 20duplication 20 | |
| 10 | Construction of public Panchayat building at Karondia in Gra Community Buildings — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 360 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹48.00 L | MEDIUM 70
delay 25cost 20duplication 20 | |
| 11 | Construction of culvert on village panchayat Songadha block Roads & Paving — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - ₹4,500,000 against a ₹3,000,000 median for Roads & Paving works in MIRZAPUR (50% above, 45 peer works)
- 360 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹45.00 L | MEDIUM 69
delay 25duplication 20cost 20 | |
| 12 | Construction of Sabri Ashram night shelter in Village Pancha Community Buildings — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 360 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹45.00 L | MEDIUM 69
delay 25duplication 20cost 20 | |
| 13 | Construction of culvert on village panchayat Songadha block Roads & Paving — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - ₹4,500,000 against a ₹3,000,000 median for Roads & Paving works in MIRZAPUR (50% above, 45 peer works)
- 360 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹45.00 L | MEDIUM 69
delay 25duplication 20cost 20 | |
| 14 | Construction of Sabri Ashram night shelter in Village Pancha Community Buildings — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 360 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹45.00 L | MEDIUM 69
delay 25duplication 20cost 20 | |
| 15 | Beautification work of Amrit Sarovar Pond Water — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 606 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹40.00 L | MEDIUM 69
delay 25duplication 20cost 19 | |
| 16 | Construction work of night shelter at public place near Kano Community Buildings — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 606 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹40.00 L | MEDIUM 69
delay 25duplication 20cost 19 | |
| 17 | Construction of Amrit Sarovar Pond in Gram Panchayat Baidha Water — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 606 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹40.00 L | MEDIUM 69
delay 25duplication 20cost 19 | |
| 18 | Beautification work of Amrit Sarovar Pond Water — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 606 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹40.00 L | MEDIUM 69
delay 25duplication 20cost 19 | |
| 19 | Construction work of night shelter at public place near Kano Community Buildings — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 606 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹40.00 L | MEDIUM 69
delay 25duplication 20cost 19 | |
| 20 | Construction of Amrit Sarovar Pond in Gram Panchayat Baidha Water — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 606 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹40.00 L | MEDIUM 69
delay 25duplication 20cost 19 | |
| 21 | construction of community toilets. Drainage & Sanitation — PRAYAGRAJ(DISTRICT MAGISTRAE ALLAHABAD_IDA) - ₹1,500,000 against a ₹1,000,000 median for Drainage & Sanitation works in PRAYAGRAJ (50% above, 9 peer works)
- 606 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 60% delay rate across its projects
| PRAYAGRAJ | ₹15.00 L | MEDIUM 69
delay 25duplication 20cost 15 | |
| 22 | construction of community toilets. Drainage & Sanitation — PRAYAGRAJ(DISTRICT MAGISTRAE ALLAHABAD_IDA) - ₹1,500,000 against a ₹1,000,000 median for Drainage & Sanitation works in PRAYAGRAJ (50% above, 9 peer works)
- 606 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 60% delay rate across its projects
| PRAYAGRAJ | ₹15.00 L | MEDIUM 69
delay 25duplication 20cost 15 | |
| 23 | Construction of public waiting room at Upper Primary Health Community Buildings — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 360 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹40.00 L | MEDIUM 69
delay 25duplication 20cost 19 | |
| 24 | Construction of public waiting room at Upper Primary Health Community Buildings — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 360 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹40.00 L | MEDIUM 69
delay 25duplication 20cost 19 | |
| 25 | Construction of C.C. road from village panchayat Belvan, Blo Roads & Paving — MIRZAPUR(DISTRICT MAGISTRATE MIRZAPUR_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 360 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MIRZAPUR | ₹35.00 L | MEDIUM 68
delay 25duplication 20cost 19 | |