| 1 | Construction of drainage system near Government Sokey Junior Education — Namchi(IMPLEMENTING DISTRICT AGENCY, NAMCHI) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 737 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 44% delay rate across its projects
| NAMCHI | ₹40.00 L | MEDIUM 52 | |
| 2 | Site development and needed repair and renovation of Village Community Buildings — Namchi(IMPLEMENTING DISTRICT AGENCY, NAMCHI) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 735 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 44% delay rate across its projects
| NAMCHI | ₹10.00 L | MEDIUM 47 | |
| 3 | Railing work in needed location at Assangthang Government Se Water — Namchi(IMPLEMENTING DISTRICT AGENCY, NAMCHI) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 582 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 44% delay rate across its projects
| NAMCHI | ₹15.00 L | MEDIUM 47 | |
| 4 | Purchase and installation of PC system, electronic devices, Equipment & Vehicles — Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) - ₹2,500,000 against a ₹1,100,000 median for Equipment & Vehicles works in GANGTOK (127% above, 11 peer works)
- 100% similarity with another nearby work
| GANGTOK | ₹25.00 L | MEDIUM 46 | |
| 5 | School playground development and boundary fencing at Gitang Education — Gyalshing(DISTRICT COLLECTOR GYALSHING_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 731 days beyond expected completion
| GYALSHING | ₹25.00 L | MEDIUM 46 | |
| 6 | Supply and installation of PC system, printers ,copiers, ne Education — Gyalshing(DISTRICT COLLECTOR GYALSHING_IDA) - Completed work has no photographic documentation on record
- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
Read more (1 more)Show less- 100% similarity with another nearby work
| GYALSHING | ₹30.00 L | MEDIUM 44
duplication 20cost 18compliance 5 | |
| 7 | Supply and installation of PC system, printers, copiers, nee Education — Gyalshing(DISTRICT COLLECTOR GYALSHING_IDA) - Completed work has no photographic documentation on record
- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
Read more (1 more)Show less- 100% similarity with another nearby work
| GYALSHING | ₹30.00 L | MEDIUM 44
duplication 20cost 18compliance 5 | |
| 8 | Protective wall at needed locations below Indira Bye pass-He Roads & Paving — Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) - ₹3,000,000 against a ₹1,999,843 median for Roads & Paving works in GANGTOK (50% above, 11 peer works)
- 349 days beyond expected completion
| GANGTOK | ₹30.00 L | MEDIUM 44 | |
| 9 | supply and installation of PC system and other electronic de Education — Soreng(DISTRICT COLLECTOR SORENG_IDA) - Completed work has no photographic documentation on record
- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
Read more (1 more)Show less- 100% similarity with another nearby work
| SORENG | ₹34.93 L | MEDIUM 43
duplication 20cost 19compliance 5 | |
| 10 | Supply and installation of PC system and other electronic de Education — Soreng(DISTRICT COLLECTOR SORENG_IDA) - Completed work has no photographic documentation on record
- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
Read more (1 more)Show less- 100% similarity with another nearby work
| SORENG | ₹31.81 L | MEDIUM 43
duplication 20cost 18compliance 5 | |
| 11 | Construction of protective wall at Upper Kyangbari Boundary & Protection — Gyalshing(DISTRICT COLLECTOR GYALSHING_IDA) - ₹400,000 against a ₹250,000 median for Boundary & Protection works in GYALSHING (60% above, 41 peer works)
- 100% similarity with another nearby work
| GYALSHING | ₹4.00 L | MEDIUM 42
duplication 20cost 15delay 5 | |
| 12 | Construction of protective wall at Upper Kyangbari Boundary & Protection — Gyalshing(DISTRICT COLLECTOR GYALSHING_IDA) - ₹400,000 against a ₹250,000 median for Boundary & Protection works in GYALSHING (60% above, 41 peer works)
- 100% similarity with another nearby work
| GYALSHING | ₹4.00 L | MEDIUM 42
duplication 20cost 15delay 5 | |
| 13 | Purchase and installation of PC system electronic devices an Education — Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) - ₹2,000,000 against a ₹998,572 median for Education works in GANGTOK (100% above, 28 peer works)
- 99% similarity with another nearby work
| GANGTOK | ₹20.00 L | MEDIUM 42 | |