60 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | 60 | 24 | ₹10.95 Cr | 10 | 21.7 | SHIV SHAKTI FURNITURE 12% of spend · 23 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Indra Hang Subba SIKKIM | 44 | ₹8.14 Cr | 3 |
| Dorjee Tshering Lepcha Sitting Rajya Sabha | 16 | ₹2.81 Cr | 7 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 21 | ₹3.81 Cr | 1 |
| Boundary & Protection | 15 | ₹3.15 Cr | 5 |
| Equipment & Vehicles | 11 | ₹1.81 Cr | 1 |
| Roads & Paving | 8 | ₹1.73 Cr | 2 |
| Community Buildings | 2 | ₹15.00 L | 1 |
| Drainage & Sanitation | 1 | ₹5.00 L | 0 |
| Other | 1 | ₹10.00 L | 0 |
| Street Lighting | 1 | ₹15.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of protection wall at land slides zone along th Completed work has no photographic documentation on record | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Completed | ₹45.00 L | — | +125% | 50.4 | MEDIUM |
| Protective wall to Alternative Highway Adampool to Sichey Completed work has no photographic documentation on record | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Completed | ₹40.00 L | — | +100% | 50.4 | MEDIUM |
| construction of protection Wall at end Point of Adampool Rao Completed work has no photographic documentation on record | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Completed | ₹45.00 L | — | +125% | 50.4 | MEDIUM |
| Flood Control Embankments along riverbank roadside at Adampo ₹4,000,000 against a ₹1,999,838 median for Boundary & Protection works in GANGTOK (100% above, 22 peer works) | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Recommended | ₹40.00 L | — | +100% | 45.9 | MEDIUM |
| Flood Control Embankments along riverbank roadside at Adampo ₹4,000,000 against a ₹1,999,838 median for Boundary & Protection works in GANGTOK (100% above, 22 peer works) | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Recommended | ₹40.00 L | — | +100% | 45.9 | MEDIUM |
| Purchase and installation of PC system, electronic devices, ₹2,500,000 against a ₹1,100,000 median for Equipment & Vehicles works in GANGTOK (127% above, 11 peer works) | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Recommended | ₹25.00 L | — | +127% | 45.9 | MEDIUM |
| Protective wall at needed locations below Indira Bye pass-He ₹3,000,000 against a ₹1,999,843 median for Roads & Paving works in GANGTOK (50% above, 11 peer works) | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Recommended | ₹30.00 L | 349 d | +50% | 43.7 | MEDIUM |
| Construction of Flood Control Embankments at Akchu Khola at 118 days beyond expected completion | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Recommended | ₹5.00 L | 118 d | -75% | 42.8 | MEDIUM |
| Purchase and installation of PC system electronic devices an ₹2,000,000 against a ₹998,572 median for Education works in GANGTOK (100% above, 28 peer works) | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Recommended | ₹20.00 L | — | +100% | 41.7 | MEDIUM |
| Construction of Public Libraries and reading room 98 days beyond expected completion | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Recommended | ₹5.00 L | 98 d | 0% | 40.1 | MEDIUM |
| Supply and installation of interactive digital board at vari ₹5,000,000 against a ₹998,572 median for Education works in GANGTOK (401% above, 28 peer works) | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Recommended | ₹50.00 L | 37 d | +401% | 31.0 | LOW |
| Supply and installation of interactive digital board through Completed work has no photographic documentation on record | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Completed | ₹50.00 L | — | +401% | 30.4 | LOW |
| Supply and installation of needed furnitures at newly shifte Completed work has no photographic documentation on record | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Completed | ₹27.45 L | — | +150% | 30.4 | LOW |
| supply and installation of pc system and other electronic de Completed work has no photographic documentation on record | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Completed | ₹25.00 L | — | +150% | 30.4 | LOW |
| Supply and installation of PC system and other electronic de Completed work has no photographic documentation on record | Gangtok(DISTRICT COLLECTOR EAST DISTRICT_IDA) | Completed | ₹25.00 L | — | +150% | 30.4 | LOW |