| 1 | Construction of a Museum at 2 No. Tupsinga Gaon, Sadiya, Tin Community Buildings — TINSUKIA(DC Tinsukia) - ₹999,998 against a ₹500,000 median for Community Buildings works in TINSUKIA (100% above, 61 peer works)
- 120 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹10.00 L | HIGH 72
cost 25duplication 20delay 17 | |
| 2 | Development of Switch Gate at Meleng Embankment, Barhoipam, Boundary & Protection — JORHAT(DEPUTY COMMISSIONER JORHAT_IDA) - ₹500,000 against a ₹250,000 median for Boundary & Protection works in JORHAT (100% above, 25 peer works)
- 185 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 46% delay rate across its projects
| JORHAT | ₹5.00 L | MEDIUM 57 | |
| 3 | Construction of a Museum at 2 No. Tupsinga Gaon, Sadiya, Tin Community Buildings — TINSUKIA(DC Tinsukia) - ₹999,998 against a ₹500,000 median for Community Buildings works in TINSUKIA (100% above, 61 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹10.00 L | MEDIUM 56
cost 25duplication 20agency 11 | |
| 4 | Development of Jaiguru High School at Amrakanda, Gorajan GP Education — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - ₹500,000 against a ₹300,000 median for Education works in NAGAON (67% above, 49 peer works)
- 656 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹5.00 L | MEDIUM 53 | |
| 5 | Construction of Community Hall at Kadomoni Pather near Saleh Community Buildings — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in NAGAON (67% above, 101 peer works)
- 656 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹5.00 L | MEDIUM 53 | |
| 6 | Construction of Community Hall at Dakhin Dhingbori Chapari n Community Buildings — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in NAGAON (67% above, 101 peer works)
- 656 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹5.00 L | MEDIUM 53 | |
| 7 | Construction of Community Hall Boundary Wall, Earth Filling Community Buildings — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in NAGAON (67% above, 101 peer works)
- 661 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹5.00 L | MEDIUM 53 | |
| 8 | Construction of Community Hall at Geruamukh 7 No. Ward, Khat Community Buildings — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - 645 days beyond expected completion
- 96% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹2.00 L | MEDIUM 53
delay 25agency 11duplication 8 | |
| 9 | Purchase of Ambulance for Bechamari Mini PHC, Bechamari GP Health — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 659 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹9.00 L | MEDIUM 49 | |
| 10 | Development of Jajari Anchalik Kaborsthan, Dolongghat Blok, Religious & Cultural — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹1.00 L | MEDIUM 47 | |
| 11 | Construction of Waiting Shed at Samaguri Grant, Bajiagaon Bl Community Buildings — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹1.00 L | MEDIUM 47 | |
| 12 | Development of Community Hall near at Borma Islamiya Madrass Community Buildings — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹1.00 L | MEDIUM 47 | |
| 13 | Construction of Community Hall at Dakhin Bhagamur, Bajiagaon Community Buildings — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹1.00 L | MEDIUM 47 | |
| 14 | Construction of Community Hall at Garumara near Adarsh Vidya Education — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹1.00 L | MEDIUM 47 | |
| 15 | Construction of Community Hall at Akalabya Jr. College, Bhel Education — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹1.00 L | MEDIUM 47 | |
| 16 | Construction of Boundary Wall at Gotonga near Eidgha, Bajiag Boundary & Protection — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹1.00 L | MEDIUM 47 | |
| 17 | Development of 48 no AWC at Kuhumtoli, Bajiagaon Block, Kuhu Education — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹1.00 L | MEDIUM 47 | |
| 18 | Development of Krishti Bikas Sangha at Bharaguri, Bajiagaon Religious & Cultural — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹1.00 L | MEDIUM 47 | |
| 19 | Development of Borachuk Namghar at Puranigudam, Bajiagaon GP Religious & Cultural — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹1.00 L | MEDIUM 47 | |
| 20 | Construction of Community Hall near at Dakhin Kawaimari Hali Community Buildings — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹1.00 L | MEDIUM 47 | |
| 21 | Construction of Boundary Wall at Kawaimari Rajhuwa Kabarstha Boundary & Protection — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹1.00 L | MEDIUM 47 | |
| 22 | Development of Community Hall at Kathpara Bazar, Laokhowa Bl Community Buildings — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 712 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹1.00 L | MEDIUM 47 | |
| 23 | Construction of a Canteen of the Institute of Tai Studies an Community Buildings — CHARAIDEO(Deputy Commissioner Charaideo_IDA) - ₹400,000 against a ₹200,000 median for Community Buildings works in CHARAIDEO (100% above, 26 peer works)
- 79 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 72% delay rate across its projects
| CHARAIDEO | ₹4.00 L | MEDIUM 47 | |
| 24 | Construction of Boundary Wall at Singari Bazar Anchalik Buri Boundary & Protection — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - 722 days beyond expected completion
- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹3.00 L | MEDIUM 46 | |
| 25 | Construction of Boundary Wall at Chatian Birat Bazar Anchali Boundary & Protection — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - 722 days beyond expected completion
- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹3.00 L | MEDIUM 46 | |