Construction of Community Hall at Dakhin Dhingbori Chapari n
Community Buildings
Assam / NAGAON — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) · Gaurav Gogoi (Kaziranga)
Construction of Community Hall at Dakhin Dhingbori Chapari near Subahi Muktab, Dhingbori Chapari GP
Overall risk score
53/100
Blended from the five components below, each weighted as shown.
Risk components
Cost67
Delay100
Duplication0
Agency75
Compliance0
Sanctioned
₹5.00 L
Delay
656d
Cost deviation
67%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹500,000 against a ₹300,000 median for Community Buildings works in NAGAON (67% above, 101 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 656 days beyond expected completionPublished dates
- Implementing agency has a 75% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.