| 1 | Open Gym Sports — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - ₹1,800,000 against a ₹1,142,945 median for Sports works in WEST TRIPURA (57% above, 16 peer works)
- 703 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| WEST TRIPURA | ₹18.00 L | MEDIUM 66
delay 25duplication 20cost 17 | |
| 2 | 01 No.-Open Gymnasium (12 Equipment ) including base and sh Community Buildings — Gomati(DM OFFICE GOMATI MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 558 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| GOMATI | ₹9.42 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 3 | 01 No.-Open Gymnasium (12 Equipment ) including base and sh Community Buildings — Gomati(DM OFFICE GOMATI MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 558 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| GOMATI | ₹9.42 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 4 | 1No - Open Gym (12 Equipment) { Air Bike, Air Walker, Arm Wh Community Buildings — Gomati(DM OFFICE GOMATI MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 618 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| GOMATI | ₹9.42 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 5 | 1No - Open Gym (12 Equipment) { Air Bike, Air Walker, Arm Wh Community Buildings — Gomati(DM OFFICE GOMATI MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 618 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| GOMATI | ₹9.42 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 6 | Beautification of Officetilla New Market Pond Water — Sepahijala(DISTRICT MAGISTRATE and COLLECTOR SIPAHIJALA_IDA) - ₹2,000,000 against a ₹390,000 median for Water works in SEPAHIJALA (413% above, 21 peer works)
- 703 days beyond expected completion
Read more (1 more)Show less- 54% of this agency's ₹29,518,467 spend went to one vendor (A TO Z TRADING COMPANY), across 9 vendors and 51 transactions
| SEPAHIJALA | ₹20.00 L | MEDIUM 57 | |
| 7 | Construction of Bus stop Community Buildings — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - 556 days beyond expected completion
- 100% similarity with another nearby work
| WEST TRIPURA | ₹3.03 L | MEDIUM 56
delay 25duplication 20cost 7 | |
| 8 | Construction of Bus stop Community Buildings — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - 556 days beyond expected completion
- 100% similarity with another nearby work
| WEST TRIPURA | ₹3.03 L | MEDIUM 56
delay 25duplication 20cost 7 | |
| 9 | Construction of Shed near Mehar Kali Bari Community Buildings — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - ₹5,000,000 against a ₹1,000,000 median for Community Buildings works in WEST TRIPURA (400% above, 32 peer works)
- 558 days beyond expected completion
| WEST TRIPURA | ₹50.00 L | MEDIUM 54 | |
| 10 | Construction of common work sheds/ common covered sitting ar Community Buildings — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - ₹3,000,000 against a ₹1,000,000 median for Community Buildings works in WEST TRIPURA (200% above, 32 peer works)
- 608 days beyond expected completion
| WEST TRIPURA | ₹30.00 L | MEDIUM 54 | |
| 11 | Procurement and Installation of 43 Nos of Branded Energy Eff Equipment & Vehicles — South Tripura(DISTRICT MAGISTRATE and COLLECTOR SOUTH TRIPURA DISTRICT_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 703 days beyond expected completion
| SOUTH TRIPURA | ₹22.15 L | MEDIUM 47 | |
| 12 | phase 1 - Construction of Kharanjan road (brick) for communi Roads & Paving — Gomati(DM OFFICE GOMATI MPLADS) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 608 days beyond expected completion
| GOMATI | ₹20.00 L | MEDIUM 47 | |
| 13 | Water RO with IRP Water — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - ₹665,000 against a ₹390,000 median for Water works in WEST TRIPURA (71% above, 38 peer works)
- 558 days beyond expected completion
| WEST TRIPURA | ₹6.65 L | MEDIUM 46 | |
| 14 | Modern Anganwadi Education — South Tripura(DISTRICT MAGISTRATE and COLLECTOR SOUTH TRIPURA DISTRICT_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 558 days beyond expected completion
| SOUTH TRIPURA | ₹15.00 L | MEDIUM 45 | |
| 15 | Installation of RO Water Purifier Water — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - ₹636,900 against a ₹390,000 median for Water works in WEST TRIPURA (63% above, 38 peer works)
- 703 days beyond expected completion
| WEST TRIPURA | ₹6.37 L | MEDIUM 45 | |
| 16 | Construction of Shed near Jagannath Bari Dhanpur, Kathalia B Community Buildings — Sepahijala(DISTRICT MAGISTRATE and COLLECTOR SIPAHIJALA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 608 days beyond expected completion
Read more (1 more)Show less- 54% of this agency's ₹29,518,467 spend went to one vendor (A TO Z TRADING COMPANY), across 9 vendors and 51 transactions
| SEPAHIJALA | ₹10.00 L | MEDIUM 44 | |
| 17 | Construction of Rooms/Shed Community Buildings — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - ₹1,500,000 against a ₹1,000,000 median for Community Buildings works in WEST TRIPURA (50% above, 32 peer works)
- 554 days beyond expected completion
| WEST TRIPURA | ₹15.00 L | MEDIUM 44 | |
| 18 | Public Shed with Toilet block Drainage & Sanitation — South Tripura(DISTRICT MAGISTRATE and COLLECTOR SOUTH TRIPURA DISTRICT_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 698 days beyond expected completion
| SOUTH TRIPURA | ₹10.00 L | MEDIUM 44 | |
| 19 | Construction of Shed & Toilet at Natt Bari Drainage & Sanitation — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 703 days beyond expected completion
| WEST TRIPURA | ₹11.27 L | MEDIUM 43 | |
| 20 | 1No - Open Gym (12 Equipment) { Air Bike, Air Walker, Arm Wh Community Buildings — South Tripura(DISTRICT MAGISTRATE and COLLECTOR SOUTH TRIPURA DISTRICT_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 618 days beyond expected completion
| SOUTH TRIPURA | ₹9.42 L | MEDIUM 42 | |
| 21 | Construction of Shed near Pitash Kali Bari Community Buildings — South Tripura(DISTRICT MAGISTRATE and COLLECTOR SOUTH TRIPURA DISTRICT_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 558 days beyond expected completion
| SOUTH TRIPURA | ₹10.00 L | MEDIUM 42 | |
| 22 | Extension of Library Building Education — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 556 days beyond expected completion
| WEST TRIPURA | ₹10.00 L | MEDIUM 41 | |
| 23 | Development of Galli with construction of new drain in/cl ot Drainage & Sanitation — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 584 days beyond expected completion
| WEST TRIPURA | ₹10.00 L | MEDIUM 41 | |
| 24 | Construction of Shed/room with toilet Drainage & Sanitation — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 550 days beyond expected completion
| WEST TRIPURA | ₹9.00 L | MEDIUM 41 | |
| 25 | Construction of Paver road from the house of Thakurchand Sar Roads & Paving — West Tripura(DISTRICT MAGISTRATE WEST TRIPURA_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 550 days beyond expected completion
| WEST TRIPURA | ₹8.00 L | MEDIUM 40 | |