| 1 | Construction of open sheds, benches, levees, gutters and foo Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹4,000,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (100% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹40.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 2 | Construction of open sheds, benches, levees, gutters and foo Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹4,000,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (100% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹40.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 3 | ruja Vasti to Khadak Vasti under Vill of Rui Pimpla in Vadaw Roads & Paving — BEED(DISTRICT COLLECTOR BEED_IDA) - ₹2,000,000 against a ₹998,300 median for Roads & Paving works in BEED (100% above, 83 peer works)
- 206 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| BEED | ₹20.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 4 | ruja Vasti to Khadak Vasti under Vill of Rui Pimpla in Vadaw Roads & Paving — BEED(DISTRICT COLLECTOR BEED_IDA) - ₹2,000,000 against a ₹998,300 median for Roads & Paving works in BEED (100% above, 83 peer works)
- 206 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| BEED | ₹20.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 5 | Road leading from Titwala (East), Manda, Anand Marg to Vinay Roads & Paving — THANE(DISTRICT COLLECTOR THANE_IDA) - ₹4,900,000 against a ₹500,000 median for Roads & Paving works in THANE (880% above, 135 peer works)
- 251 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| THANE | ₹49.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 6 | Concreting internal roads in the Titwala (E), Manda, Ward N Roads & Paving — THANE(DISTRICT COLLECTOR THANE_IDA) - ₹4,900,000 against a ₹500,000 median for Roads & Paving works in THANE (880% above, 135 peer works)
- 251 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| THANE | ₹49.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 7 | Road leading from Titwala (East), Manda, Anand Marg to Vinay Roads & Paving — THANE(DISTRICT COLLECTOR THANE_IDA) - ₹4,900,000 against a ₹500,000 median for Roads & Paving works in THANE (880% above, 135 peer works)
- 251 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| THANE | ₹49.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 8 | Concreting internal roads in the Titwala (E), Manda, Ward N Roads & Paving — THANE(DISTRICT COLLECTOR THANE_IDA) - ₹4,900,000 against a ₹500,000 median for Roads & Paving works in THANE (880% above, 135 peer works)
- 251 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| THANE | ₹49.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 9 | Construction of open sheds, lading, drains and footpaths at Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (75% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 10 | Section No. Construction of benches, levees, drains and foot Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (75% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 11 | Arrangement of levees, drains, footpaths and meeting places Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (75% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 12 | Construction of toilets, drains and footpaths at Kajare Chal Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (75% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 13 | Arrangement of imposition and meeting at Ward No 01, Kandarp Community Buildings — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Community Buildings works in MUMBAI SUBURBAN (75% above, 60 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 14 | Laying drains footpaths and meeting arrangements at Marol Pi Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (75% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 15 | Construction of open auditorium, lading and footpaths at Chh Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (75% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 16 | Construction of open sheds, lading, drains and footpaths at Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (75% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 17 | Section No. Construction of benches, levees, drains and foot Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (75% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 18 | Arrangement of levees, drains, footpaths and meeting places Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (75% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 19 | Construction of toilets, drains and footpaths at Kajare Chal Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (75% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 20 | Arrangement of imposition and meeting at Ward No 01, Kandarp Community Buildings — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Community Buildings works in MUMBAI SUBURBAN (75% above, 60 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 21 | Laying drains footpaths and meeting arrangements at Marol Pi Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (75% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 22 | Construction of open auditorium, lading and footpaths at Chh Roads & Paving — MUMBAI SUBURBAN(DISTRICT COLLECTOR MUMBAI SUBURBAN_IDA) - ₹3,500,000 against a ₹2,000,000 median for Roads & Paving works in MUMBAI SUBURBAN (75% above, 272 peer works)
- 216 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 61% delay rate across its projects
| MUMBAI SUBURBAN | ₹35.00 L | HIGH 73
delay 25duplication 20cost 19 | |
| 23 | District Sindhudurg Taluka Sawantwadi, At Post Insuli Old Na Roads & Paving — SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) - ₹3,000,000 against a ₹954,305 median for Roads & Paving works in SINDHUDURG (214% above, 88 peer works)
- 265 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SINDHUDURG | ₹30.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 24 | District Sindhudurg Taluka Sawantwadi, At Post Insuli Old Na Roads & Paving — SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) - ₹3,000,000 against a ₹954,305 median for Roads & Paving works in SINDHUDURG (214% above, 88 peer works)
- 265 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SINDHUDURG | ₹30.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 25 | Construction of a public hall at Mulashi Khurd, Pune Distric Community Buildings — PUNE(DISTRICT COLLECTOR PUNE_IDA) - ₹2,000,000 against a ₹1,000,000 median for Community Buildings works in PUNE (100% above, 255 peer works)
- 157 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| PUNE | ₹20.00 L | HIGH 72
cost 25delay 22duplication 20 | |