59 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) 1 high risk | 59 | 18 | ₹6.06 Cr | 3 | 14.6 | Manoj Madhukar Waingankar 20% of spend · 16 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Narayan Tatu Rane RATNAGIRI-SINDHUDURG | 53 | ₹5.22 Cr | 0 |
| Sanjay Raut Sitting Rajya Sabha | 5 | ₹64.00 L | 2 |
| Anil Sukhdeorao Bonde Sitting Rajya Sabha | 1 | ₹20.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 42 | ₹4.23 Cr | 1 |
| Community Buildings | 5 | ₹49.88 L | 1 |
| Water | 4 | ₹32.99 L | 0 |
| Education | 3 | ₹47.00 L | 1 |
| Drainage & Sanitation | 2 | ₹20.00 L | 0 |
| Religious & Cultural | 1 | ₹20.00 L | 0 |
| Sports | 1 | ₹10.00 L | 0 |
| Street Lighting | 1 | ₹3.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| District Sindhudurg Taluka Sawantwadi, At Post Insuli Old Na ₹3,000,000 against a ₹954,305 median for Roads & Paving works in SINDHUDURG (214% above, 88 peer works) | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹30.00 L | 265 d | +214% | 72.5 | HIGH |
| District Sindhudurg Taluka Sawantwadi Mu.Insuli District Par 251 days beyond expected completion | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹2.00 L | 251 d | 0% | 55.3 | MEDIUM |
| Construction of community hall at talgaon, Malwan ₹2,000,000 against a ₹990,030 median for Community Buildings works in SINDHUDURG (102% above, 11 peer works) | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹20.00 L | — | +102% | 47.5 | MEDIUM |
| Gravel and asphalt the road from Ghodge Shri Dev Lingeshwar ₹1,500,000 against a ₹954,305 median for Roads & Paving works in SINDHUDURG (57% above, 88 peer works) | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹15.00 L | 166 d | +57% | 39.9 | LOW |
| Construction of classrooms for Mrs. Indirabai Dattatreya Var Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹35.00 L | 141 d | 0% | 38.8 | LOW |
| District Sindhudurg, Taluka, Village Anav, Form No. 23, Seri ₹1,500,000 against a ₹954,305 median for Roads & Paving works in SINDHUDURG (57% above, 88 peer works) | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹15.00 L | — | +57% | 36.8 | LOW |
| To develop the public park Oros Sulochananagar Balodyan in K 157 days beyond expected completion | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹10.00 L | 157 d | 0% | 32.9 | LOW |
| Paving and asphalting the road from Poip Naka to Vetal Mandi 141 days beyond expected completion | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹10.00 L | 141 d | +5% | 30.6 | LOW |
| Vadachapat Bouddhavadi Road gravelling and asphalting (Backw 141 days beyond expected completion | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹10.00 L | 141 d | +5% | 30.6 | LOW |
| Varad Shetyewadi to Shetyewadi and Madhliwadi Cemetery Road 157 days beyond expected completion | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹5.00 L | 157 d | -48% | 30.1 | LOW |
| To pave and asphalt the Kolamba Katwad cemetery road. Tal. M 141 days beyond expected completion | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹5.00 L | 141 d | -48% | 27.8 | LOW |
| Installation of street lights on the road leading to Bibavan 141 days beyond expected completion | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹3.00 L | 141 d | 0% | 27.8 | LOW |
| Construction of Road from Kumbharmath Ghumde Vastwadi to Sur ₹2,500,000 against a ₹954,305 median for Roads & Paving works in SINDHUDURG (162% above, 88 peer works) | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹25.00 L | — | +162% | 27.5 | LOW |
| District Sindhudurg Taluka Malvan, At Post. Kandalgaon Gram 100% similarity with another nearby work | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Completed | ₹7.00 L | — | -27% | 27.3 | LOW |
| Poip Viranwadi to Chambharwadi (Chavhanwadi) road gravelling 114 days beyond expected completion | SINDHUDURG(DISTRICT COLLECTOR SINDHUDURG_IDA) | Recommended | ₹10.00 L | 114 d | +5% | 26.5 | LOW |