| 1 | Construction of Boundary Wall of Community Hall Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in GANJAM (67% above, 445 peer works)
- 166 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹5.00 L | MEDIUM 68
delay 23duplication 20cost 17 | |
| 2 | Construction of Community Hall Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in GANJAM (67% above, 445 peer works)
- 166 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹5.00 L | MEDIUM 68
delay 23duplication 20cost 17 | |
| 3 | Construction of Community Hall for Cultural Activity Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹500,000 against a ₹300,000 median for Community Buildings works in GANJAM (67% above, 445 peer works)
- 165 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹5.00 L | MEDIUM 68
delay 23duplication 20cost 17 | |
| 4 | Construction of Kalyani Mandap Religious & Cultural — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹700,000 against a ₹300,000 median for Religious & Cultural works in GANJAM (133% above, 112 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹7.00 L | MEDIUM 61
cost 25duplication 20agency 9 | |
| 5 | Construction of Pandara Samaja Community Hall Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 166 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹4.00 L | MEDIUM 60
delay 23duplication 20agency 9 | |
| 6 | Construction of Community Hall Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 166 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹4.00 L | MEDIUM 60
delay 23duplication 20agency 9 | |
| 7 | Construction of Community Hall Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 186 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹2.00 L | MEDIUM 60
delay 25duplication 20agency 9 | |
| 8 | Construction of Kalyan Mandap Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 165 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹4.00 L | MEDIUM 60
delay 23duplication 20agency 9 | |
| 9 | Construction of community Hall for Cultural Activity Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 165 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹4.00 L | MEDIUM 60
delay 23duplication 20agency 9 | |
| 10 | Construction of Kalyan Mandap near Sidhheswar Mandir Religious & Cultural — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹1,000,000 against a ₹300,000 median for Religious & Cultural works in GANJAM (233% above, 112 peer works)
- 186 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹10.00 L | MEDIUM 59 | |
| 11 | Construction of Community Hall for Cultural Activity Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 166 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹3.00 L | MEDIUM 58
delay 23duplication 20agency 9 | |
| 12 | Construction of Community Hall Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 166 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹3.00 L | MEDIUM 58
delay 23duplication 20agency 9 | |
| 13 | Construction of Community Hall for Cultural Activity Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 166 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹2.00 L | MEDIUM 58
delay 23duplication 20agency 9 | |
| 14 | Construction of Community Hall Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 166 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹2.00 L | MEDIUM 58
delay 23duplication 20agency 9 | |
| 15 | Construction of Kalyan Mandap Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 166 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹2.00 L | MEDIUM 58
delay 23duplication 20agency 9 | |
| 16 | Construction of Kalyan mandap Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 165 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹3.00 L | MEDIUM 58
delay 23duplication 20agency 9 | |
| 17 | Construction of Community Hall for Cultural Activity Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 165 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹3.00 L | MEDIUM 58
delay 23duplication 20agency 9 | |
| 18 | Construction of Community Hall for Cultural Activity Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 165 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹2.00 L | MEDIUM 58
delay 23duplication 20agency 9 | |
| 19 | Development of park near Dhanei Dam Sports — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹1,000,000 against a ₹300,000 median for Sports works in GANJAM (233% above, 19 peer works)
- 170 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹10.00 L | MEDIUM 57 | |
| 20 | Construction of Library with computer facility Education — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in GANJAM (100% above, 48 peer works)
- 170 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹10.00 L | MEDIUM 57 | |
| 21 | Construction of Paver road Roads & Paving — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹700,000 against a ₹300,000 median for Roads & Paving works in GANJAM (133% above, 122 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹7.00 L | MEDIUM 54
cost 25duplication 20agency 9 | |
| 22 | Construction of Kalyan Mandap Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 133 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹3.00 L | MEDIUM 53
duplication 20delay 18agency 9 | |
| 23 | Construction of rooms of Sishu Mandir School Education — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in GANJAM (100% above, 48 peer works)
- 133 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹10.00 L | MEDIUM 52 | |
| 24 | Construction of Kalyani Mandap Religious & Cultural — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - ₹500,000 against a ₹300,000 median for Religious & Cultural works in GANJAM (67% above, 112 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹5.00 L | MEDIUM 47
duplication 20cost 17agency 9 | |
| 25 | Construction of Community Hall of Aliya Khandayat Samaja, L Community Buildings — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) - 166 days beyond expected completion
- 96% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 57% delay rate across its projects
| GANJAM | ₹3.00 L | MEDIUM 46
delay 23agency 9duplication 8 | |