Development of park near Dhanei Dam
Sports
Odisha / GANJAM — GANJAM(DISTRICT COLLECTOR GANJAM_IDA) · Anita Subhadarshini (ASKA)
Overall risk score
57/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay94
Duplication0
Agency57
Compliance0
Sanctioned
₹10.00 L
Delay
170d
Cost deviation
233%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,000,000 against a ₹300,000 median for Sports works in GANJAM (233% above, 19 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 170 days beyond expected completionPublished dates
- Implementing agency has a 57% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.