| 1 | Regarding the installation of High Mast light at Sita Kund D Street Lighting — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹1,296,194 against a ₹563,000 median for Street Lighting works in SULTANPUR (130% above, 44 peer works)
- 158 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹12.96 L | HIGH 73
cost 25delay 22duplication 20 | |
| 2 | Regarding the installation of High Mast light at Sita Kund D Street Lighting — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹1,296,194 against a ₹563,000 median for Street Lighting works in SULTANPUR (130% above, 44 peer works)
- 158 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹12.96 L | HIGH 73
cost 25delay 22duplication 20 | |
| 3 | Recommendation for Installation of Various Lighting Arrangem Street Lighting — SOUTH(COMMISSIONER SOUTH) - ₹3,726,112 against a ₹968,970 median for Street Lighting works in SOUTH (285% above, 119 peer works)
- 114 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH | ₹37.26 L | MEDIUM 62
cost 25duplication 20delay 16 | |
| 4 | Recommendation for Installation of Various Lighting Arrangem Street Lighting — SOUTH(COMMISSIONER SOUTH) - ₹3,726,112 against a ₹968,970 median for Street Lighting works in SOUTH (285% above, 119 peer works)
- 114 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| SOUTH | ₹37.26 L | MEDIUM 62
cost 25duplication 20delay 16 | |
| 5 | Recommendation for Installation of Two Water Coolers at Pant Water — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹744,780 against a ₹372,390 median for Water works in SULTANPUR (100% above, 11 peer works)
- 78 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹7.45 L | MEDIUM 62
cost 25duplication 20delay 11 | |
| 6 | Recommendation for Installation of Two Water Coolers at Pant Water — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹744,780 against a ₹372,390 median for Water works in SULTANPUR (100% above, 11 peer works)
- 78 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹7.45 L | MEDIUM 62
cost 25duplication 20delay 11 | |
| 7 | Recommendation for the installation of 15 Solar Lights Street Lighting — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - 114 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 42 payments still in progress, oldest 686 days
| MUZAFFARNAGAR | ₹2.30 L | MEDIUM 58
duplication 20delay 16agency 14 | |
| 8 | Provision of lighting arrangements with 4m decorative poles Street Lighting — CENTRAL(COMMISSIONER MCD (CENTRAL DISTRICT)) - ₹1,690,420 against a ₹717,502 median for Street Lighting works in CENTRAL (136% above, 63 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 54% of this agency's ₹41,296,762 spend went to one vendor (Central Electronics Limited), across 17 vendors and 31 transactions
| CENTRAL | ₹16.90 L | MEDIUM 51
cost 25duplication 20agency 6 | |
| 9 | Construction of a Cement Concrete CC Road at Vikas Khand Dub Roads & Paving — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹2,600,000 against a ₹820,890 median for Roads & Paving works in SULTANPUR (217% above, 60 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹26.00 L | MEDIUM 51
cost 25duplication 20agency 6 | |
| 10 | Construction of a Cement Concrete CC Road at Vikas Khand Dub Roads & Paving — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹2,600,000 against a ₹820,890 median for Roads & Paving works in SULTANPUR (217% above, 60 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹26.00 L | MEDIUM 51
cost 25duplication 20agency 6 | |
| 11 | Recommendation of construction of a Park at Village Chhanna Sports — PATIALA(DEPUTY COMMISSIONER PATIALA_IDA) - ₹1,500,000 against a ₹299,934 median for Sports works in PATIALA (400% above, 27 peer works)
- 100% similarity with another nearby work
| PATIALA | ₹15.00 L | MEDIUM 50
cost 25duplication 20agency 5 | |
| 12 | Recommendation for the installation of 15 Solar Lights Street Lighting — MUZAFFARNAGAR(DISTRICT MAGISTRATE MUZAFFARNAGAR_IDA) - 114 days beyond expected completion
- 100% similarity with another nearby work
| MUZAFFARNAGAR | ₹2.30 L | MEDIUM 50
duplication 20delay 16cost 8 | |
| 13 | Recommendation of construction of a Park at Village Chhanna Sports — PATIALA(DEPUTY COMMISSIONER PATIALA_IDA) - ₹1,500,000 against a ₹299,934 median for Sports works in PATIALA (400% above, 27 peer works)
- 100% similarity with another nearby work
| PATIALA | ₹15.00 L | MEDIUM 49
cost 25duplication 20agency 4 | |
| 14 | Installation of two RO Water Coolers at Ward 7 Civil Lines D Water — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹700,000 against a ₹372,390 median for Water works in SULTANPUR (88% above, 11 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹7.00 L | MEDIUM 48
cost 22duplication 20agency 6 | |
| 15 | Installation of two RO Water Coolers at Ward 7 Civil Lines D Water — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - ₹700,000 against a ₹372,390 median for Water works in SULTANPUR (88% above, 11 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹7.00 L | MEDIUM 48
cost 22duplication 20agency 6 | |
| 16 | Installation of 50 Water ATMs based on RO Plant and Water Co Water — CENTRAL(COMMISSIONER MCD (CENTRAL DISTRICT)) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 100% similarity with another nearby work
Read more (1 more)Show less- 54% of this agency's ₹41,296,762 spend went to one vendor (Central Electronics Limited), across 17 vendors and 31 transactions
| CENTRAL | ₹2.25 Cr | MEDIUM 48
cost 22duplication 20agency 6 | |
| 17 | Provision of lighting arrangements with 4m decorative poles Street Lighting — CENTRAL(COMMISSIONER MCD (CENTRAL DISTRICT)) - ₹1,690,420 against a ₹717,502 median for Street Lighting works in CENTRAL (136% above, 63 peer works)
- 100% similarity with another nearby work
| CENTRAL | ₹16.90 L | MEDIUM 48
cost 25duplication 20agency 3 | |
| 18 | Conversio n of existing TPDDL overhead power line into under Street Lighting — NORTH(COMMISSIONER MCD NORTH_IDA) - ₹1,597,834 against a ₹523,829 median for Street Lighting works in NORTH (205% above, 112 peer works)
- 100% similarity with another nearby work
| NORTH | ₹15.98 L | MEDIUM 47
cost 25duplication 20agency 2 | |
| 19 | Conversio n of existing TPDDL overhead power line into under Street Lighting — NORTH(COMMISSIONER MCD NORTH_IDA) - ₹1,597,834 against a ₹523,829 median for Street Lighting works in NORTH (205% above, 112 peer works)
- 100% similarity with another nearby work
| NORTH | ₹15.98 L | MEDIUM 47
cost 25duplication 20agency 2 | |
| 20 | Recommendation for Installation of Two High Mass light at Pa Sports — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - 78 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹13.00 L | MEDIUM 47
duplication 20delay 11cost 10 | |
| 21 | Recommendation for Installation of Two High Mass light at Pa Sports — SULTANPUR(DISTRICT MAGISTRATE SULTANPUR_IDA) - 78 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| SULTANPUR | ₹13.00 L | MEDIUM 47
duplication 20delay 11cost 10 | |
| 22 | Provision of Street Light Poles with LED Fitting at Madangir Street Lighting — SOUTH(COMMISSIONER SOUTH) - ₹2,434,004 against a ₹968,970 median for Street Lighting works in SOUTH (151% above, 119 peer works)
- 100% similarity with another nearby work
| SOUTH | ₹24.34 L | MEDIUM 47
cost 25duplication 20agency 2 | |
| 23 | Recommendation for Fixing of Stainless Steel and Victorian B Equipment & Vehicles — SOUTH(COMMISSIONER SOUTH) - ₹945,061 against a ₹449,770 median for Equipment & Vehicles works in SOUTH (110% above, 49 peer works)
- 100% similarity with another nearby work
| SOUTH | ₹9.45 L | MEDIUM 47
cost 25duplication 20agency 2 | |
| 24 | Provision of Street Light Poles with LED Fitting at Madangir Street Lighting — SOUTH(COMMISSIONER SOUTH) - ₹2,434,004 against a ₹968,970 median for Street Lighting works in SOUTH (151% above, 119 peer works)
- 100% similarity with another nearby work
| SOUTH | ₹24.34 L | MEDIUM 47
cost 25duplication 20agency 2 | |
| 25 | Recommendation for Fixing of Stainless Steel and Victorian B Equipment & Vehicles — SOUTH(COMMISSIONER SOUTH) - ₹945,061 against a ₹449,770 median for Equipment & Vehicles works in SOUTH (110% above, 49 peer works)
- 100% similarity with another nearby work
| SOUTH | ₹9.45 L | MEDIUM 47
cost 25duplication 20agency 2 | |