| 1 | CC ROAD FROM SC MOHALLE TO COMMUNITY BUILDING IN GRAM PANCHA Roads & Paving — Khargone (West Nimar)(DISTRICT COLLECTOR KHARGONE_IDA) - ₹1,300,000 against a ₹500,000 median for Roads & Paving works in KHARGONE (160% above, 19 peer works)
- 370 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 454 days
| KHARGONE | ₹13.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 2 | Shri Reva bhagirath Desi Gauraksha Shala Samiti Gram Ramgarh Community Buildings — Khargone (West Nimar)(DISTRICT COLLECTOR KHARGONE_IDA) - ₹2,100,000 against a ₹500,000 median for Community Buildings works in KHARGONE (320% above, 140 peer works)
- 556 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 1 payment still in progress, oldest 454 days
| KHARGONE | ₹21.00 L | HIGH 79
cost 25delay 25duplication 20 | |
| 3 | CC ROAD FROM SC MOHALLE TO COMMUNITY BUILDING IN GRAM PANCHA Roads & Paving — Khargone (West Nimar)(DISTRICT COLLECTOR KHARGONE_IDA) - ₹1,300,000 against a ₹500,000 median for Roads & Paving works in KHARGONE (160% above, 19 peer works)
- 370 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 55% delay rate across its projects
| KHARGONE | ₹13.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 4 | Shri Reva bhagirath Desi Gauraksha Shala Samiti Gram Ramgarh Community Buildings — Khargone (West Nimar)(DISTRICT COLLECTOR KHARGONE_IDA) - ₹2,100,000 against a ₹500,000 median for Community Buildings works in KHARGONE (320% above, 140 peer works)
- 556 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 55% delay rate across its projects
| KHARGONE | ₹21.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 5 | wharf construction (Ghat Nirman) in Pond of Karodiya for Pu Water — BHOPAL(DISTRICT COLLECTOR BHOPAL_IDA) - ₹2,000,000 against a ₹750,000 median for Water works in BHOPAL (167% above, 8 peer works)
- 575 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BHOPAL | ₹20.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 6 | wharf construction (Ghat Nirman) in Pond of Karodiya for Pu Water — BHOPAL(DISTRICT COLLECTOR BHOPAL_IDA) - ₹2,000,000 against a ₹750,000 median for Water works in BHOPAL (167% above, 8 peer works)
- 575 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BHOPAL | ₹20.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 7 | CC Road from NABARD road to Karondiya connecting road in GP Roads & Paving — VIDISHA(District Collector Vidisha_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in VIDISHA (100% above, 164 peer works)
- 173 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| VIDISHA | ₹10.00 L | HIGH 74
cost 25delay 24duplication 20 | |
| 8 | CC Road from NABARD road to Karondiya connecting road in GP Roads & Paving — VIDISHA(District Collector Vidisha_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in VIDISHA (100% above, 164 peer works)
- 173 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| VIDISHA | ₹10.00 L | HIGH 74
cost 25delay 24duplication 20 | |
| 9 | Construction of Community Building in PALTA Gram Vidhansabh Community Buildings — CHHATARPUR(District Collector Chhatarpur_IDA) - ₹2,000,000 against a ₹399,773 median for Community Buildings works in CHHATARPUR (400% above, 223 peer works)
- 703 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| CHHATARPUR | ₹20.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 10 | Construction of Community Building in PALTA Gram Vidhansabh Community Buildings — CHHATARPUR(District Collector Chhatarpur_IDA) - ₹2,000,000 against a ₹399,773 median for Community Buildings works in CHHATARPUR (400% above, 223 peer works)
- 703 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| CHHATARPUR | ₹20.00 L | HIGH 73
cost 25delay 25duplication 20 | |
| 11 | Construction of Common Work Tin Shed in Shankar Lakshman Community Buildings — INDORE(DISTRICT COLLECTOR INDORE_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in INDORE (100% above, 46 peer works)
- 185 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| INDORE | ₹10.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 12 | Const. Work of Samudayik bhawan at Ward NO 01 Manpur Community Buildings — INDORE(DISTRICT COLLECTOR INDORE_IDA) - ₹1,148,700 against a ₹500,000 median for Community Buildings works in INDORE (130% above, 46 peer works)
- 705 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| INDORE | ₹11.49 L | HIGH 72
cost 25delay 25duplication 20 | |
| 13 | Construction of Common Work Tin Shed in Shankar Lakshman Community Buildings — INDORE(DISTRICT COLLECTOR INDORE_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in INDORE (100% above, 46 peer works)
- 185 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| INDORE | ₹10.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 14 | Const. Work of Samudayik bhawan at Ward NO 01 Manpur Community Buildings — INDORE(DISTRICT COLLECTOR INDORE_IDA) - ₹1,148,700 against a ₹500,000 median for Community Buildings works in INDORE (130% above, 46 peer works)
- 705 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| INDORE | ₹11.49 L | HIGH 72
cost 25delay 25duplication 20 | |
| 15 | Approach Road From Gram Gondi pura To kakad Roads & Paving — BHOPAL(DISTRICT COLLECTOR BHOPAL_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 715 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BHOPAL | ₹10.00 L | MEDIUM 64
delay 25duplication 20cost 14 | |
| 16 | Approach Road From Gram Gondi pura To kakad Roads & Paving — BHOPAL(DISTRICT COLLECTOR BHOPAL_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 715 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BHOPAL | ₹10.00 L | MEDIUM 64
delay 25duplication 20cost 14 | |
| 17 | Construction of Room in Sewa Bharti Sewa Nyas sansthan for p Community Buildings — Agar-Malwa(District Collector Agar Malwa_IDA) - ₹1,500,000 against a ₹750,000 median for Community Buildings works in AGAR-MALWA (100% above, 14 peer works)
- 79 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 44% of this agency's ₹8,007,000 spend went to one vendor (CEO JANPAD PANCHAYAT BADOD), across 5 vendors and 178 transactions
| AGAR-MALWA | ₹15.00 L | MEDIUM 62
cost 25duplication 20delay 11 | |
| 18 | Installation Of Fixed Garden OPEN GYM Equipment in Gram Panc Sports — DINDORI(District Collector Dindori_IDA) - 173 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| DINDORI | ₹8.55 L | MEDIUM 61
delay 24duplication 20cost 9 | |
| 19 | Installation Of Fixed Garden OPEN GYM Equipment in Gram Panc Sports — DINDORI(District Collector Dindori_IDA) - 173 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| DINDORI | ₹8.55 L | MEDIUM 61
delay 24duplication 20cost 9 | |
| 20 | Installation Of Fixed Garden OPEN GYM Equipment in Gram Panc Sports — DINDORI(District Collector Dindori_IDA) - 173 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| DINDORI | ₹8.55 L | MEDIUM 61
delay 24duplication 20cost 9 | |
| 21 | Installation Of Fixed Garden OPEN GYM Equipment in Gram Panc Sports — DINDORI(District Collector Dindori_IDA) - 173 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| DINDORI | ₹8.55 L | MEDIUM 61
delay 24duplication 20cost 9 | |
| 22 | Installation Of Fixed OPEN GYM Equipment in Gram Panchayat Sports — DINDORI(District Collector Dindori_IDA) - 173 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| DINDORI | ₹8.55 L | MEDIUM 61
delay 24duplication 20cost 9 | |
| 23 | Installation Of Fixed Garden OPEN GYM Equipment in Gram Panc Sports — DINDORI(District Collector Dindori_IDA) - 173 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| DINDORI | ₹8.55 L | MEDIUM 61
delay 24duplication 20cost 9 | |
| 24 | Installation Of Fixed Garden OPEN GYM Equipment in Gram Panc Sports — DINDORI(District Collector Dindori_IDA) - 173 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| DINDORI | ₹8.55 L | MEDIUM 61
delay 24duplication 20cost 9 | |
| 25 | Installation Of Fixed Garden OPEN GYM Equipment in Gram Panc Sports — DINDORI(District Collector Dindori_IDA) - 173 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| DINDORI | ₹8.55 L | MEDIUM 61
delay 24duplication 20cost 9 | |