Open this link on a larger screen to see the verification queue.
90 works across 1 implementing agency, recommended by 6 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | DINDORI(District Collector Dindori_IDA) | 90 | 0 | ₹4.01 Cr | 28 | 25.8 | MP STATE AGRO 40% of spend · 24 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Faggan Singh Kulaste MANDLA | 67 | ₹2.12 Cr | 12 |
| Kavita Patidar Sitting Rajya Sabha | 12 | ₹79.34 L | 11 |
| Vivek K. Tankha Sitting Rajya Sabha | 8 | ₹30.32 L | 3 |
| L. Murugan Sitting Rajya Sabha | 1 | ₹50.00 L | 1 |
| Sumitra Balmik Sitting Rajya Sabha | 1 | ₹5.00 L | 1 |
| Vishnu Datt Sharma KHAJURAHO | 1 | ₹25.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Water | 35 | ₹61.44 L | 5 |
| Roads & Paving | 18 | ₹87.00 L | 8 |
| Community Buildings | 15 | ₹67.73 L | 6 |
| Street Lighting | 11 | ₹49.01 L | 0 |
| Sports | 6 | ₹51.30 L | 6 |
| Education | 3 | ₹75.00 L | 2 |
| Drainage & Sanitation | 1 | ₹5.00 L | 0 |
| Boundary & Protection | 1 | ₹5.00 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Contrution work of Boundary wall in PG college Dindori 544 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹5.00 L | 544 d | 0% | 60.9 | MEDIUM |
| Shaskiya Chandra Vijay Snakottar Mahavidyalaya ward no.1 mai 553 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹5.00 L | 553 d | 0% | 60.6 | MEDIUM |
| Installation Of Fixed Garden OPEN GYM Equipment in Gram Panc 173 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹8.55 L | 173 d | 0% | 60.5 | MEDIUM |
| Installation Of Fixed Garden OPEN GYM Equipment in Gram Panc 173 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹8.55 L | 173 d | 0% | 60.5 | MEDIUM |
| Installation Of Fixed Garden OPEN GYM Equipment in Gram Panc 173 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹8.55 L | 173 d | 0% | 60.5 | MEDIUM |
| Installation Of Fixed Garden OPEN GYM Equipment in Gram Panc 173 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹8.55 L | 173 d | 0% | 60.5 | MEDIUM |
| Installation Of Fixed OPEN GYM Equipment in Gram Panchayat 173 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹8.55 L | 173 d | 0% | 60.5 | MEDIUM |
| Installation Of Fixed Garden OPEN GYM Equipment in Gram Panc 173 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹8.55 L | 173 d | 0% | 60.5 | MEDIUM |
| Gram Panchayat Deora Hansnagar, janpad Panchayat Dindori Bha 569 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹3.00 L | 569 d | -40% | 59.5 | MEDIUM |
| Providing GI Water tanker Capacity 5500 Liter Tyre 900X16 in 173 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹1.61 L | 173 d | -10% | 57.9 | MEDIUM |
| Providing GI Water tanker Capacity 5500 Liter Tyre 900X16 in 173 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹1.61 L | 173 d | -10% | 57.9 | MEDIUM |
| Providing GI Water tanker Capacity 5500 Liter Tyre 900X16 in 173 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹1.61 L | 173 d | -10% | 57.9 | MEDIUM |
| Providing GI Water tanker Capacity 5500 Liter Tyre 900X16 in 173 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹1.61 L | 173 d | -10% | 57.9 | MEDIUM |
| Providing GI Water tanker Capacity 5500 Liter Tyre 900X16 in 173 days beyond expected completion | DINDORI(District Collector Dindori_IDA) | Recommended | ₹1.61 L | 173 d | -10% | 57.9 | MEDIUM |
| Auditorium hall collectrate parisar me atirikt kaksha ka n ₹1,000,000 against a ₹499,500 median for Community Buildings works in DINDORI (100% above, 24 peer works) | DINDORI(District Collector Dindori_IDA) | Recommended | ₹10.00 L | 248 d | +100% | 57.3 | MEDIUM |