| 1 | Construction of Room/Hall Community Buildings — Kasganj(DISTRICT MAGISTRATE KASGANJ KANSHIRAMNAGAR_IDA) - ₹1,000,000 against a ₹538,471 median for Community Buildings works in KASGANJ (86% above, 57 peer works)
- 706 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 68% of this agency's ₹53,548,054 spend went to one vendor (SOMYA CONSTRUCTION), across 3 vendors and 368 transactions
| KASGANJ | ₹10.00 L | HIGH 80
delay 25cost 21duplication 20 | |
| 2 | Construction of Room/Hall Community Buildings — Kasganj(DISTRICT MAGISTRATE KASGANJ KANSHIRAMNAGAR_IDA) - ₹1,000,000 against a ₹538,471 median for Community Buildings works in KASGANJ (86% above, 57 peer works)
- 706 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 63% of this agency's ₹58,374,364 spend went to one vendor (SUPER AGRO), across 2 vendors and 147 transactions
| KASGANJ | ₹10.00 L | HIGH 79
delay 25cost 21duplication 20 | |
| 3 | Amar Shaheed Virangna Raani Avantibai Lodhi Sansthan, Near B Roads & Paving — LUCKNOW(DISTRICT MAGISTRAE LUCKNOW_IDA) - ₹2,000,000 against a ₹993,000 median for Roads & Paving works in LUCKNOW (101% above, 401 peer works)
- 612 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| LUCKNOW | ₹20.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 4 | Amar Shaheed Virangna Raani Avantibai Lodhi Sansthan, Near B Roads & Paving — LUCKNOW(DISTRICT MAGISTRAE LUCKNOW_IDA) - ₹2,000,000 against a ₹993,000 median for Roads & Paving works in LUCKNOW (101% above, 401 peer works)
- 612 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| LUCKNOW | ₹20.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 5 | construction of a room in Santosh Kumari Shravan Kumar Agarw Education — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in BUDAUN (100% above, 29 peer works)
- 344 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 6 | construction of rooms in Asharfi Devi Girls Inter College, U Education — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in BUDAUN (100% above, 29 peer works)
- 344 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹10.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 7 | RCC Spectator Gallery Teen Shed in College Playgrond Education — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹2,917,618 against a ₹500,000 median for Education works in BUDAUN (484% above, 29 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹29.18 L | HIGH 74
cost 25delay 25duplication 20 | |
| 8 | High Mast LED Light (30 mtrs MS Pole with 16 LED Light 350 W Street Lighting — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹950,000 against a ₹163,273 median for Street Lighting works in BUDAUN (482% above, 716 peer works)
- 631 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹9.50 L | HIGH 74
cost 25delay 25duplication 20 | |
| 9 | Civil Work - Community Hall in Majra Parwala Community Buildings — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹2,500,000 against a ₹850,000 median for Community Buildings works in BUDAUN (194% above, 25 peer works)
- 706 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹25.00 L | HIGH 74
cost 25delay 25duplication 20 | |
| 10 | Community Hall in Shri Radha Krishna Saraswati Vidya Mandir Education — JALAUN(DISTRICT MAGISTRATE JALAUN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 612 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 81% of this agency's ₹70,485,857 spend went to one vendor (PITAMBRA CONSTRUCTION), across 5 vendors and 175 transactions
| JALAUN | ₹10.00 L | HIGH 72
delay 25duplication 20agency 15 | |
| 11 | Civil work of Library Room in School Education — Kasganj(DISTRICT MAGISTRATE KASGANJ KANSHIRAMNAGAR_IDA) - ₹1,000,000 against a ₹711,000 median for Education works in KASGANJ (41% above, 14 peer works)
- 706 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 68% of this agency's ₹53,548,054 spend went to one vendor (SOMYA CONSTRUCTION), across 3 vendors and 368 transactions
| KASGANJ | ₹10.00 L | HIGH 72
delay 25duplication 20cost 14 | |
| 12 | construction of a room in Santosh Kumari Shravan Kumar Agarw Education — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in BUDAUN (100% above, 29 peer works)
- 344 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹10.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 13 | construction of rooms in Asharfi Devi Girls Inter College, U Education — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹1,000,000 against a ₹500,000 median for Education works in BUDAUN (100% above, 29 peer works)
- 344 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹10.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 14 | RCC Spectator Gallery Teen Shed in College Playgrond Education — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹2,917,618 against a ₹500,000 median for Education works in BUDAUN (484% above, 29 peer works)
- 590 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹29.18 L | HIGH 72
cost 25delay 25duplication 20 | |
| 15 | High Mast LED Light (30 mtrs MS Pole with 16 LED Light 350 W Street Lighting — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹950,000 against a ₹163,273 median for Street Lighting works in BUDAUN (482% above, 716 peer works)
- 631 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹9.50 L | HIGH 72
cost 25delay 25duplication 20 | |
| 16 | Civil Work - Community Hall in Majra Parwala Community Buildings — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹2,500,000 against a ₹850,000 median for Community Buildings works in BUDAUN (194% above, 25 peer works)
- 706 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹25.00 L | HIGH 72
cost 25delay 25duplication 20 | |
| 17 | Civil work of Library Room in School Education — Kasganj(DISTRICT MAGISTRATE KASGANJ KANSHIRAMNAGAR_IDA) - ₹1,000,000 against a ₹711,000 median for Education works in KASGANJ (41% above, 14 peer works)
- 706 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 63% of this agency's ₹58,374,364 spend went to one vendor (SUPER AGRO), across 2 vendors and 147 transactions
| KASGANJ | ₹10.00 L | HIGH 72
delay 25duplication 20cost 14 | |
| 18 | Concreate core sand with cement interlocking bricks work Roads & Paving — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹1,716,000 against a ₹964,300 median for Roads & Paving works in BUDAUN (78% above, 106 peer works)
- 706 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹17.16 L | MEDIUM 68
delay 25duplication 20cost 19 | |
| 19 | Community Hall Civil Work - In Village Jyora Community Buildings — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹1,495,600 against a ₹850,000 median for Community Buildings works in BUDAUN (76% above, 25 peer works)
- 706 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹14.96 L | MEDIUM 68
delay 25duplication 20cost 19 | |
| 20 | Concreate core sand with cement interlocking bricks work Roads & Paving — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹1,716,000 against a ₹964,300 median for Roads & Paving works in BUDAUN (78% above, 106 peer works)
- 706 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹17.16 L | MEDIUM 67
delay 25duplication 20cost 19 | |
| 21 | Community Hall Civil Work - In Village Jyora Community Buildings — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹1,495,600 against a ₹850,000 median for Community Buildings works in BUDAUN (76% above, 25 peer works)
- 706 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹14.96 L | MEDIUM 66
delay 25duplication 20cost 19 | |
| 22 | Community Hall in Shri Radha Krishna Saraswati Vidya Mandir Education — JALAUN(DISTRICT MAGISTRATE JALAUN_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 612 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 54% delay rate across its projects
| JALAUN | ₹10.00 L | MEDIUM 66
delay 25duplication 20cost 12 | |
| 23 | Concreate core sand with cement interlocking bricks work Roads & Paving — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹1,532,300 against a ₹964,300 median for Roads & Paving works in BUDAUN (59% above, 106 peer works)
- 706 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹15.32 L | MEDIUM 65
delay 25duplication 20cost 16 | |
| 24 | Concreate core sand with cement interlocking bricks work Roads & Paving — BUDAUN(DISTRICT MAGISTRATE BUDAUN_IDA) - ₹1,532,300 against a ₹964,300 median for Roads & Paving works in BUDAUN (59% above, 106 peer works)
- 706 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| BUDAUN | ₹15.32 L | MEDIUM 63
delay 25duplication 20cost 16 | |
| 25 | construction of community hall
and Beautification of viranga Community Buildings — JHANSI(DISTRICT MAGISTRAE JHANSI_IDA) - ₹996,000 against a ₹597,900 median for Community Buildings works in JHANSI (67% above, 11 peer works)
- 271 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| JHANSI | ₹9.96 L | MEDIUM 62
delay 25duplication 20cost 17 | |