| 1 | Construction of Indoor Sports Stadium at Bengali Boy’s Schoo Education — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - ₹5,000,000 against a ₹300,000 median for Education works in NAGAON (1567% above, 49 peer works)
- 254 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹50.00 L | HIGH 81
cost 25delay 25duplication 20 | |
| 2 | Construction of Guest House at Mahapurush Srimanta Sankardev Community Buildings — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - ₹5,000,000 against a ₹300,000 median for Community Buildings works in NAGAON (1567% above, 101 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹50.00 L | HIGH 81
cost 25delay 25duplication 20 | |
| 3 | Construction of Indoor Sports Stadium at Bengali Boy’s Schoo Education — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - ₹5,000,000 against a ₹300,000 median for Education works in NAGAON (1567% above, 49 peer works)
- 254 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹50.00 L | HIGH 81
cost 25delay 25duplication 20 | |
| 4 | Construction of Guest House at Mahapurush Srimanta Sankardev Community Buildings — NAGAON(DEPUTY COMMISSIONER NOWGONG_IDA) - ₹5,000,000 against a ₹300,000 median for Community Buildings works in NAGAON (1567% above, 101 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 75% delay rate across its projects
| NAGAON | ₹50.00 L | HIGH 81
cost 25delay 25duplication 20 | |
| 5 | Construction of Stage at Lashit Yovak Sangha at 2 No. Kohalg Religious & Cultural — MAJULI(District Commissioner, Majuli) - ₹2,000,000 against a ₹200,000 median for Religious & Cultural works in MAJULI (900% above, 13 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 76% delay rate across its projects
| MAJULI | ₹20.00 L | HIGH 81
cost 25delay 25duplication 20 | |
| 6 | Construction of Stage at Lashit Yovak Sangha at 2 No. Kohalg Religious & Cultural — MAJULI(District Commissioner, Majuli) - ₹2,000,000 against a ₹200,000 median for Religious & Cultural works in MAJULI (900% above, 13 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 76% delay rate across its projects
| MAJULI | ₹20.00 L | HIGH 81
cost 25delay 25duplication 20 | |
| 7 | Construction of Assam Type Guest House at Rangagora Amlokhi Community Buildings — CHARAIDEO(Deputy Commissioner Charaideo_IDA) - ₹2,500,000 against a ₹200,000 median for Community Buildings works in CHARAIDEO (1150% above, 26 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 72% delay rate across its projects
| CHARAIDEO | ₹25.00 L | HIGH 81
cost 25delay 25duplication 20 | |
| 8 | Construction of Assam Type Guest House at Rangagora Amlokhi Community Buildings — CHARAIDEO(Deputy Commissioner Charaideo_IDA) - ₹2,500,000 against a ₹200,000 median for Community Buildings works in CHARAIDEO (1150% above, 26 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 72% delay rate across its projects
| CHARAIDEO | ₹25.00 L | HIGH 81
cost 25delay 25duplication 20 | |
| 9 | Construction of Gorkha Sanskritik Kala Kristi Knedra at Free Religious & Cultural — TINSUKIA(DC Tinsukia) - ₹5,000,000 against a ₹500,000 median for Religious & Cultural works in TINSUKIA (900% above, 26 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹50.00 L | HIGH 81
cost 25delay 25duplication 20 | |
| 10 | Construction of Gorkha Sanskritik Kala Kristi Knedra at Free Religious & Cultural — TINSUKIA(DC Tinsukia) - ₹5,000,000 against a ₹500,000 median for Religious & Cultural works in TINSUKIA (900% above, 26 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 71% delay rate across its projects
| TINSUKIA | ₹50.00 L | HIGH 81
cost 25delay 25duplication 20 | |
| 11 | Construction of protective sheds for preservation of Bhomora Roads & Paving — SONITPUR(Deputy Commissioner Sonitpur, Tezpur) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 231 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 77% of this agency's ₹39,850,751 spend went to one vendor (MAHAMAYA CONSTRUCTION), across 6 vendors and 302 transactions
| SONITPUR | ₹45.00 L | HIGH 79
delay 25duplication 20cost 19 | |
| 12 | Construction of Open Stage at Jorhat Theatre Hall, Ward No. Community Buildings — JORHAT(DEPUTY COMMISSIONER JORHAT_IDA) - ₹2,500,000 against a ₹250,000 median for Community Buildings works in JORHAT (900% above, 110 peer works)
- 275 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| JORHAT | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 13 | Construction of Community Hall at Bir Pangrao Khetra, Lalimc Community Buildings — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹2,500,000 against a ₹299,995 median for Community Buildings works in SIVASAGAR (733% above, 73 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 14 | Construction of Open Stage at Jorhat Theatre Hall, Ward No. Community Buildings — JORHAT(DEPUTY COMMISSIONER JORHAT_IDA) - ₹2,500,000 against a ₹250,000 median for Community Buildings works in JORHAT (900% above, 110 peer works)
- 275 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| JORHAT | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 15 | Construction of Community Hall at Bir Pangrao Khetra, Lalimc Community Buildings — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹2,500,000 against a ₹299,995 median for Community Buildings works in SIVASAGAR (733% above, 73 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 16 | Construction of Ganeshguri Krira Aru Sanskritik Yuva Mancha, Religious & Cultural — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹2,500,000 against a ₹697,000 median for Religious & Cultural works in KAMRUP METRO (259% above, 20 peer works)
- 254 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 17 | Construction of New Stage and Green Room at Cheng Ren Campus Religious & Cultural — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹3,000,000 against a ₹697,000 median for Religious & Cultural works in KAMRUP METRO (330% above, 20 peer works)
- 275 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹30.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 18 | Construction of Gym Hall at Abhiruchi Institute of Physical Community Buildings — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹1,500,000 against a ₹600,000 median for Community Buildings works in KAMRUP METRO (150% above, 47 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹15.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 19 | Construction of Ganeshguri Krira Aru Sanskritik Yuva Mancha, Religious & Cultural — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹2,500,000 against a ₹697,000 median for Religious & Cultural works in KAMRUP METRO (259% above, 20 peer works)
- 254 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹25.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 20 | Construction of New Stage and Green Room at Cheng Ren Campus Religious & Cultural — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹3,000,000 against a ₹697,000 median for Religious & Cultural works in KAMRUP METRO (330% above, 20 peer works)
- 275 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹30.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 21 | Construction of Gym Hall at Abhiruchi Institute of Physical Community Buildings — KAMRUP METRO(DEPUTY COMMISSIONER KAMRUP METROPOLITAN_IDA) - ₹1,500,000 against a ₹600,000 median for Community Buildings works in KAMRUP METRO (150% above, 47 peer works)
- 276 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 45% delay rate across its projects
| KAMRUP METRO | ₹15.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 22 | CONSTRUCTION OF LAKSHMIJAN BAGISA RANGAMANCHA, ADPURIA Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 23 | CONSTRUCTION OF OFFICE BUILDING OF GAON PRADHAN NAZIRA, WARD Community Buildings — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹1,200,000 against a ₹299,995 median for Community Buildings works in SIVASAGAR (300% above, 73 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹12.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 24 | CONSTRUCTION OF BAULIPUKHURI RANGAMANCHA, SENCHOA Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 25 | CONSTRUCTION OF LALIM CHAPORI BAGHJAN JARADHARA RANGA MANCHA Religious & Cultural — SIVASAGAR(Deputy Commissioner Sivsagar_IDA) - ₹700,000 against a ₹249,018 median for Religious & Cultural works in SIVASAGAR (181% above, 293 peer works)
- 178 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 46% delay rate across its projects
| SIVASAGAR | ₹7.00 L | HIGH 77
cost 25delay 25duplication 20 | |