Open this link on a larger screen to see the verification queue.
48 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | MAJULI(District Commissioner, Majuli) 1 high risk | 48 | 8 | ₹1.44 Cr | 17 | 33.4 | NITUL BORUAH 31% of spend · 8 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Gaurav Gogoi JORHAT | 46 | ₹1.04 Cr | 15 |
| Pabitra Margherita Sitting Rajya Sabha | 2 | ₹40.00 L | 2 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 18 | ₹33.69 L | 4 |
| Religious & Cultural | 12 | ₹47.96 L | 7 |
| Roads & Paving | 6 | ₹12.00 L | 0 |
| Education | 4 | ₹30.00 L | 2 |
| Boundary & Protection | 3 | ₹7.00 L | 2 |
| Sports | 2 | ₹7.00 L | 1 |
| Water | 1 | ₹2.50 L | 1 |
| Health | 1 | ₹1.52 L | 0 |
| Other | 1 | ₹2.50 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Stage at Lashit Yovak Sangha at 2 No. Kohalg ₹2,000,000 against a ₹200,000 median for Religious & Cultural works in MAJULI (900% above, 13 peer works) | MAJULI(District Commissioner, Majuli) | Recommended | ₹20.00 L | 178 d | +900% | 81.1 | HIGH |
| Construction of Smart Classroom at Majuli Auniati Hemchandra Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | MAJULI(District Commissioner, Majuli) | Completed | ₹20.00 L | — | 0% | 45.3 | MEDIUM |
| Construction of Jadavpur Kristi Kendra, Jadavpur, Pohumora, 261 days beyond expected completion | MAJULI(District Commissioner, Majuli) | Recommended | ₹2.00 L | 261 d | 0% | 44.4 | MEDIUM |
| Construction of Boundary Wall at 1 no Chelek Kamalpur Commun 262 days beyond expected completion | MAJULI(District Commissioner, Majuli) | Recommended | ₹2.00 L | 262 d | 0% | 44.4 | MEDIUM |
| Construction of Community Centre near at Pokajara 1 no ward 262 days beyond expected completion | MAJULI(District Commissioner, Majuli) | Recommended | ₹2.00 L | 262 d | 0% | 44.4 | MEDIUM |
| Construction of waiting Shed at Dhapak Santipur Chariali, Dh 262 days beyond expected completion | MAJULI(District Commissioner, Majuli) | Recommended | ₹2.00 L | 262 d | 0% | 44.4 | MEDIUM |
| Construction of Namghar at Kambong Gaon, Garamur Nagar Gaon, 262 days beyond expected completion | MAJULI(District Commissioner, Majuli) | Recommended | ₹2.00 L | 262 d | 0% | 44.4 | MEDIUM |
| Development of Bar Namghar at Major Chapori, Karatipar GP 262 days beyond expected completion | MAJULI(District Commissioner, Majuli) | Recommended | ₹2.00 L | 262 d | 0% | 44.4 | MEDIUM |
| Construction of Boundary Wall at 2 no Ward Sumoimari Rangham 262 days beyond expected completion | MAJULI(District Commissioner, Majuli) | Recommended | ₹2.00 L | 262 d | 0% | 44.4 | MEDIUM |
| Construction of Building Kala Krishti Kendra near at Rawnapa 262 days beyond expected completion | MAJULI(District Commissioner, Majuli) | Recommended | ₹2.00 L | 262 d | 0% | 44.4 | MEDIUM |
| Const. of Jyoti Samaj Kalyan Sangha Boundary Wall at 1No Kor 262 days beyond expected completion | MAJULI(District Commissioner, Majuli) | Recommended | ₹2.00 L | 262 d | 0% | 44.4 | MEDIUM |
| Construction of Jengrai Chapori Namoni Kristi Kendra, Jengra 262 days beyond expected completion | MAJULI(District Commissioner, Majuli) | Recommended | ₹2.00 L | 262 d | 0% | 44.4 | MEDIUM |
| Development of Simoluguri Rangamancha, Karkichuk, Phuloni GP 262 days beyond expected completion | MAJULI(District Commissioner, Majuli) | Recommended | ₹2.00 L | 262 d | 0% | 44.4 | MEDIUM |
| Construction of Gayan Gaon Ujani Chawkidarchuk Kristi Kendra 262 days beyond expected completion | MAJULI(District Commissioner, Majuli) | Recommended | ₹2.00 L | 262 d | 0% | 44.4 | MEDIUM |
| Infrastructure development at Shri Shri Pitambar Dev Goswami 262 days beyond expected completion | MAJULI(District Commissioner, Majuli) | Recommended | ₹5.00 L | 262 d | 0% | 44.4 | MEDIUM |