| 1 | Construction of community Hall at Arpanpally Village, Kesamu Community Buildings — MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) - ₹2,000,000 against a ₹499,000 median for Community Buildings works in MAHABUBABAD (301% above, 28 peer works)
- 370 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MAHABUBABAD | ₹20.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 2 | Construction of community Hall at Arpanpally Village, Kesamu Community Buildings — MAHABUBABAD(DISTRICT COLLECTOR MAHABUBABAD_IDA) - ₹2,000,000 against a ₹499,000 median for Community Buildings works in MAHABUBABAD (301% above, 28 peer works)
- 370 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| MAHABUBABAD | ₹20.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 3 | Laying of 250mm dia swG Sewer line from H.no.1-4-873 to 1-4- Drainage & Sanitation — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 299 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- 61% of this agency's ₹55,429,086 spend went to one vendor (SANTRIX CONSTRUCTIONS), across 8 vendors and 45 transactions
| HYDERABAD | ₹10.50 L | MEDIUM 66
delay 25duplication 20cost 11 | |
| 4 | Estimate for Shifting of 11KV OH line at H.No.8-1-68 A 24 Sr Religious & Cultural — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - 252 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 61% of this agency's ₹55,429,086 spend went to one vendor (SANTRIX CONSTRUCTIONS), across 8 vendors and 45 transactions
| HYDERABAD | ₹1.05 L | MEDIUM 63
delay 25duplication 20agency 10 | |
| 5 | Construction of Gate on the land owned by the Municipal Coun Boundary & Protection — KAITHAL(DC CUM NODAL OFFICERS MPLADS) - ₹1,370,000 against a ₹400,000 median for Boundary & Protection works in KAITHAL (242% above, 19 peer works)
- 76 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 43% delay rate across its projects
| KAITHAL | ₹13.70 L | MEDIUM 62
cost 25duplication 20delay 11 | |
| 6 | Construction of Gate on the land owned by the Municipal Coun Boundary & Protection — KAITHAL(DC CUM NODAL OFFICERS MPLADS) - ₹1,370,000 against a ₹400,000 median for Boundary & Protection works in KAITHAL (242% above, 19 peer works)
- 76 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 43% delay rate across its projects
| KAITHAL | ₹13.70 L | MEDIUM 62
cost 25duplication 20delay 11 | |
| 7 | Laying of 250mm dia swG Sewer line from H.no.1-4-873 to 1-4- Drainage & Sanitation — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 299 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| HYDERABAD | ₹10.50 L | MEDIUM 61
delay 25duplication 20cost 11 | |
| 8 | Estimate for Shifting of 11KV OH line at H.No.8-1-68 A 24 Sr Religious & Cultural — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - 252 days beyond expected completion
- 100% similarity with another nearby work
| HYDERABAD | ₹1.05 L | MEDIUM 59
delay 25duplication 20cost 9 | |
| 9 | Formation and Metalling the road from Sandhi Ravinder Reddy Roads & Paving — WARANGAL(District Collector Warangal_IDA) - 372 days beyond expected completion
- 100% similarity with another nearby work
| WARANGAL | ₹5.00 L | MEDIUM 58
delay 25duplication 20cost 9 | |
| 10 | Formation and Metalling the road from Lethakula Anthireddy F Roads & Paving — WARANGAL(District Collector Warangal_IDA) - 372 days beyond expected completion
- 100% similarity with another nearby work
| WARANGAL | ₹5.00 L | MEDIUM 58
delay 25duplication 20cost 9 | |
| 11 | Providing Infrastructure Facilities at Sundaiah Park , Bagli Sports — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - ₹4,500,000 against a ₹2,499,500 median for Sports works in HYDERABAD (80% above, 8 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 61% of this agency's ₹55,429,086 spend went to one vendor (SANTRIX CONSTRUCTIONS), across 8 vendors and 45 transactions
| HYDERABAD | ₹45.00 L | MEDIUM 58
cost 20duplication 20agency 10 | |
| 12 | Formation and Metalling the road from Sandhi Ravinder Reddy Roads & Paving — WARANGAL(District Collector Warangal_IDA) - 372 days beyond expected completion
- 100% similarity with another nearby work
| WARANGAL | ₹5.00 L | MEDIUM 56
delay 25duplication 20cost 9 | |
| 13 | Formation and Metalling the road from Lethakula Anthireddy F Roads & Paving — WARANGAL(District Collector Warangal_IDA) - 372 days beyond expected completion
- 100% similarity with another nearby work
| WARANGAL | ₹5.00 L | MEDIUM 56
delay 25duplication 20cost 9 | |
| 14 | Providing LED Street Lights in Tirumalapur Village Cchunta( Street Lighting — MAHABUBNAGAR(DISTRICT COLLECTOR MAHABUBNAGAR_3) - Completed work has no photographic documentation on record
- ₹499,001 against a ₹250,000 median for Street Lighting works in MAHABUBNAGAR (100% above, 136 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 43% delay rate across its projects
| MAHABUBNAGAR | ₹4.99 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 15 | Providing LED Street Lights in Gudoor (Village) Chinna Chint Street Lighting — MAHABUBNAGAR(DISTRICT COLLECTOR MAHABUBNAGAR_3) - Completed work has no photographic documentation on record
- ₹499,001 against a ₹250,000 median for Street Lighting works in MAHABUBNAGAR (100% above, 136 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 43% delay rate across its projects
| MAHABUBNAGAR | ₹4.99 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 16 | Providing LED Street Lights in Tirumalapur Village Cchunta( Street Lighting — MAHABUBNAGAR(DISTRICT COLLECTOR MAHABUBNAGAR_3) - Completed work has no photographic documentation on record
- ₹499,001 against a ₹250,000 median for Street Lighting works in MAHABUBNAGAR (100% above, 136 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 43% delay rate across its projects
| MAHABUBNAGAR | ₹4.99 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 17 | Providing LED Street Lights in Gudoor (Village) Chinna Chint Street Lighting — MAHABUBNAGAR(DISTRICT COLLECTOR MAHABUBNAGAR_3) - Completed work has no photographic documentation on record
- ₹499,001 against a ₹250,000 median for Street Lighting works in MAHABUBNAGAR (100% above, 136 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 43% delay rate across its projects
| MAHABUBNAGAR | ₹4.99 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 18 | Providing High Mast Lights in Thirumalapur (Village) Chinna Street Lighting — MAHABUBNAGAR(DISTRICT COLLECTOR MAHABUBNAGAR_3) - Completed work has no photographic documentation on record
- ₹497,434 against a ₹250,000 median for Street Lighting works in MAHABUBNAGAR (99% above, 136 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 43% delay rate across its projects
| MAHABUBNAGAR | ₹4.97 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 19 | Providing High Mast Lights in Thirumalapur (Village) Chinna Street Lighting — MAHABUBNAGAR(DISTRICT COLLECTOR MAHABUBNAGAR_3) - Completed work has no photographic documentation on record
- ₹497,434 against a ₹250,000 median for Street Lighting works in MAHABUBNAGAR (99% above, 136 peer works)
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 43% delay rate across its projects
| MAHABUBNAGAR | ₹4.97 L | MEDIUM 56
cost 25duplication 20agency 6 | |
| 20 | Providing Infrastructure Facilities for Institute Of Child H Health — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - Completed work has no photographic documentation on record
- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
Read more (2 more)Show less- 100% similarity with another nearby work
- 61% of this agency's ₹55,429,086 spend went to one vendor (SANTRIX CONSTRUCTIONS), across 8 vendors and 45 transactions
| HYDERABAD | ₹60.00 L | MEDIUM 55
cost 21duplication 20agency 10 | |
| 21 | Laying of VDCC road from Sree Sai Nilayam to Suraj Fast Food Roads & Paving — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - ₹4,500,000 against a ₹1,600,000 median for Roads & Paving works in HYDERABAD (181% above, 39 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 61% of this agency's ₹55,429,086 spend went to one vendor (SANTRIX CONSTRUCTIONS), across 8 vendors and 45 transactions
| HYDERABAD | ₹45.00 L | MEDIUM 55
cost 25duplication 20agency 10 | |
| 22 | Drilling of 6.5 power borewell, Safe Drinking Water RO, Sola Water — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - ₹2,490,000 against a ₹597,761 median for Water works in HYDERABAD (317% above, 105 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 61% of this agency's ₹55,429,086 spend went to one vendor (SANTRIX CONSTRUCTIONS), across 8 vendors and 45 transactions
| HYDERABAD | ₹24.90 L | MEDIUM 55
cost 25duplication 20agency 10 | |
| 23 | Drilling of 6 .5 power borewell, Safe Drinking Water RO, Sol Water — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - ₹2,490,000 against a ₹597,761 median for Water works in HYDERABAD (317% above, 105 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 61% of this agency's ₹55,429,086 spend went to one vendor (SANTRIX CONSTRUCTIONS), across 8 vendors and 45 transactions
| HYDERABAD | ₹24.90 L | MEDIUM 55
cost 25duplication 20agency 10 | |
| 24 | Drilling of 6.5 power borewell, Safe Drinking Water RO, Sola Water — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - ₹2,490,000 against a ₹597,761 median for Water works in HYDERABAD (317% above, 105 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 61% of this agency's ₹55,429,086 spend went to one vendor (SANTRIX CONSTRUCTIONS), across 8 vendors and 45 transactions
| HYDERABAD | ₹24.90 L | MEDIUM 55
cost 25duplication 20agency 10 | |
| 25 | Digital Class Rooms, Safe Drinking Water RO, Solar and Allie Water — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) - ₹2,490,000 against a ₹597,761 median for Water works in HYDERABAD (317% above, 105 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- 61% of this agency's ₹55,429,086 spend went to one vendor (SANTRIX CONSTRUCTIONS), across 8 vendors and 45 transactions
| HYDERABAD | ₹24.90 L | MEDIUM 55
cost 25duplication 20agency 10 | |